01100 Summary final.doc

DOC document 35 KB Posted

Attached to
Provide and Install Fall Protection Systems at RML
Solicitation number
NIHOF2008057
Issued by

About this file

Summary

View the file

Other files

File Type Posted
01770 ADG CLOSE OUT PROCEDURES final.doc DOC document
01140 Work Restrictions final.doc DOC document
01500 TEMP FACILITIES CONTROL final.doc DOC document
A3.3.pdf PDF
01400 Quality Requirements final.doc DOC document
01420 References final.doc DOC document
RFP RML Fall Protection Project.doc DOC document
01731 Cutting Patching final.doc DOC document
A0.1.pdf PDF
A3.0.pdf PDF
07725 FALL PROTECTION SYSTEM final.doc DOC document
A3.6.pdf PDF
INDEX Fall Protection.DOC DOC document
01310 Proj Mngmt Coord final.doc DOC document
A3.4.pdf PDF
01600 ADG PROD REQUIREMENTS final.doc DOC document
01330 SUBMTL PROCEDURES final.doc DOC document
SPEC COVER .doc DOC document
A3.2.pdf PDF
sf1449.pdf PDF
A3.1.pdf PDF
01320 Const Prog Doc final.doc DOC document
A3.5.pdf PDF
01700 Execution Requirements final.doc DOC document
07730 Roof Accessories final.doc DOC document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04-436

08-811

SECTION 01100 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Sections A through M of the Contract and other Division 1 Specification Sections, apply to this Section.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Fall Protection.

1. Project Location: NIH-NIAID Rocky Mountain Laboratories, 903 South Fourth Street, Hamilton, MT 59840.

2. Owner: National Institutes of Health, 9000 Rockville Pike, Bethesda, Maryland, 20892.

B. Architect Identification: The Contract Documents, dated August 3, 2007, were prepared for Project by Architects Design Group PC.

C. The Work consists of designing and providing the appropriate fall protection systems for the conditions shown. Installation will be complete by factory certified installers as necessary to obtain a certified OSHA compliant system.

1. Phase 1

a. Complete work required on the roof of Building 23, Incinerator before August 11, 2008

2. Phase 2

a. Complete the balance of the fall protection work on the remaining roofs by September 30, 2008.

1.3 CONTRACT

A. Project will be constructed under a general construction contract.

1.4 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC's "MasterFormat" numbering system.

1. Section Identification: The Specifications use section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of sections in the Contract Documents.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

1.5 MISCELLANEOUS PROVISIONS

A. The Government’s equipment shall be protected from the Contractor’s construction activities at all times. All equipment will be protected from dust and debris and protected from water during the work on the roof of the Building.

B. The Contractor’s personnel shall only occupy the portions of the building that are designated for work during each phase of the project.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01100

FALL PROTECTION ( NIH-NIAID RML ( HAMILTON, MT

SUMMARY 01100 - 1