AMD06 22R1322.pdf

PDF 135 KB Posted

Attached to
PAF 198127 TACMOR UTILITIES AND INFRASTRUCTURE SUPPORT
Solicitation number
N62742-22-R-1322
Issued by

About this file

This amendment modifies a solicitation for utilities and infrastructure support services. The scope of work includes construction of electrical utilities, concrete foundations, equipment tie downs, water and wastewater systems, access roads, parking areas, security fencing, and site work to support installation of transmission and receiver antennas and related equipment for a tactical mobile over-the-horizon radar system. Bids are to be based on using local aggregates, with contractors responsible for testing and submitting variations if aggregates do not meet specifications. The Navy Facilities Engineering Command Pacific is the contracting agency, with an estimated value between $100-250 million and a 1,106 calendar day period of performance.

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04 EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

RFP N62742-22-R-1322, PAF 198127 TACMOR UTILITIES AND INFRASTRUCTURE SUPPORT

Amendment No. 0006 is continued on page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA 15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer) (Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N62742-22-R-1322

X 9B. DATED (SEE ITEM 11)

05 JAN 2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02 MAY 2022

CODE

NAVFAC PACIFIC

CONSTRUCTION CONTRACTS BR (CON33)

4256 RADFORD DR., BLDG 62

HONOLULU, HI 96818-3296

N62742 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

FACILITY CODECODE

EMAIL:TEL:

N62742-22-R-1322 Amendment No. 0006

SF 30 BLOCK 14 CONTINUATION PAGE

This amendment is issued to revise the following:

1. Document 00 22 00, Paragraph 2.3 Technical Evaluation Factors, Factor 4 – Management Plan, subparagraph (a) Solicitation Submittal Requirements, 1st paragraph is deleted in its entirety and replaced with the following.

Revision is shown in red font.

The Offeror (as identified on the SF1442) shall provide (1) a detailed narrative of their management plan limited to a maximum of ten (10) single-sided pages, 8.5” x 11”, 1” margin left/right/top/bottom, 10-point font or larger AND (2) a proposed construction schedule not to exceed five (5) single-sided pages (11” x 17”). At a minimum, the following shall be addressed:

2. Section 01 33 00 Submittal Procedures, is revised to add the following paragraph 1.9.5:

1.9.5 Use of Local Aggregate:

Use of local aggregate has been determined to be advantageous to the Government. Contractors are to base bids on using the best available local aggregates that most closely meet the specification requirements. The Contractor must demonstrate that all local aggregates were evaluated for compliance with the applicable specifications, and that the aggregate included in the variation submittal has the least variation from contract requirements when compared to aggregates from other sources; specifically pointing out variations from the specification requirements. Failure to evaluate all available aggregate sources and to point out variations may cause the Government to reject the variation submittal. Contractor will be required to resubmit the variation submittal for aggregates from other local sources at no additional cost to the Government.

Should the variation submittal for the best available local aggregate be rejected by the Contracting Officer, the procurement of aggregate from an alternative source will be handled as a changed condition.

3. Section 03 30 00, paragraph 2.3.3.1, Normal-Weight Aggregate, subparagraph f. is deleted in its entirety and replaced with the following:

Base bids on using local aggregates. Contractor will be responsible to perform the required testing in accordance with the specifications. If aggregate is unable to meet the specified testing requirements the Contractor must discuss the variation(s) with the Contracting Officer and submit a variation submittal in accordance with Section 01 33 00, subsection 1.9 Variations. Should the variation submittal for the best available aggregate be rejected by the Contracting Officer, the procurement of aggregate from an alternative source will be handled as a changed condition.

4. Section 32 11 23 Aggregate Base Courses, is revised to add a second paragraph to paragraph 2.1 as follows:

Base bids on using local aggregates. Contractor will be responsible to perform the required testing in accordance with the specifications. If aggregate is unable to meet the specified testing requirements the Contractor must discuss the variation(s) with the Contracting Officer and submit a variation submittal in accordance with Section 01 33 00, subsection 1.9 Variations. Should the variation submittal for the best

5. Section 32 15 00 Aggregate Surfacing, is revised to add a second paragraph to paragraph 2.1 as follows:

Base bids on using local aggregates. Contractor will be responsible to perform the required testing in accordance with the specifications. If aggregate is unable to meet the specified testing requirements the Contractor must discuss the variation(s) with the Contracting Officer and submit a variation submittal in accordance with Section 01 33 00, subsection 1.9 Variations. Should the variation submittal for the best

N62742-22-R-1322 Amendment No. 0006

6. Section 32 13 13.06 Portland Cement Concrete Pavement for Roads and Site, is revised to add a second paragraph to paragraph 2.1.3 as follows:

Base bids on using local aggregates. Contractor will be responsible to perform the required testing in accordance with the specifications. If aggregate is unable to meet the specified testing requirements the Contractor must discuss the variation(s) with the Contracting Officer and submit a variation submittal in accordance with Section 01 33 00, subsection 1.9 Variations. Should the variation submittal for the best

7. The following previously issued drawing identified by number and title has been revised by this amendment and noted in the table below:

Drawing No.

NAVFAC

No. Drawing Title Revision CD051 17268003 Rx Overall Erosion Control and

Demolition Plan

1. Add note 10. “UXO/MEC contractor shall furnish, install, and maintain all erosion and dust control measures for the duration of their contract. All temporary erosion control measures will be removed at the completion of their contract.”

2. Add note 11. “All erosion control requirements need to be in-place prior to the start of earthmoving activities.”

8. All other terms and conditions remain unchanged.

End of Amendment