This solicitation is for the construction of infrastructure and utilities to support a system of research antennas in Palau. The work includes electrical utilities, reinforced concrete pads and foundations, water and wastewater systems, access roads, security fencing, and site work. The facilities will be designed as semi-permanent structures in accordance with DoD criteria. The magnitude of the project is estimated between $100 million and $250 million. The contract is classified under NAICS code 237990 with an average annual revenue of $39.5 million. The period of performance is 1,106 calendar days following notice to proceed. The acquisition will be conducted on an unrestricted basis, inviting proposals from all qualified firms.

View the file

Other files

File Type Posted
AMD07 22R1322.pdf PDF
22R1322 Note 7.pdf PDF
AMD06 22R1322.pdf PDF
22R1322 Note 6-FINAL.pdf PDF
AMD 05 22R1322.pdf PDF
22R1322 Note 5-Final.pdf PDF
AMD04 22R1322 Rev DWGS.pdf PDF
22R1322 Note 4-FINAL.pdf PDF
AMD04 22R1322.pdf PDF
AMD 03 22R1322.pdf PDF
AMD 02 22R1322 REV DWGS.pdf PDF
AMD 02 22R1322.pdf PDF
22R1322 Note 2 FINAL.pdf PDF
AMD 01 22R1322.pdf PDF
22R1322 Note 1 FINAL.pdf PDF
PAF 198127 Spec Section 5 of 5.pdf PDF
PAF 198127 Spec Section 1 of 5.pdf PDF
PAF 198127 TACMOR_DWGS 3 of 7.pdf PDF
PAF 198127 TACMOR_DWGS 1 of 7.pdf PDF
PAF 198127 Spec Section 3 of 5-a.pdf PDF
N62742-22-R-1322 Front End.pdf PDF
PAF 198127 TACMOR_DWGS 6 of 7.pdf PDF
PAF 198127 TACMOR_DWGS 7 of 7.pdf PDF
PAF 198127 TACMOR_DWGS 5 of 7.pdf PDF
PAF 198127 TACMOR_DWGS 2 of 7.pdf PDF
PAF 198127 TACMOR_DWGS 4 of 7.pdf PDF
PAF 198127 Spec Section 2 of 5.pdf PDF
PAF 198127 Spec Section 4 of 5-a.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC

258 MAKALAPA DRIVE, SUITE 100

JOINT BASE PEARL HARBOR HICKAM, HAWAII 96860-3134

Notice No. 3 25 March 2022

PRE-PROPOSAL QUESTIONS & ANSWERS

RFP N62742-22-R-1322

PAF 198127 TACMOR UTILITIES AND

INFRASTRUCTURE SUPPORT

NOTE: The following questions and answers are provided for INFORMATION ONLY.

The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

RESPONSES DEFERRED FROM NOTICE NO. 1

55. Drawing S-501, S-503, CG101,102,104,105, Tx Site - Drain Pipe Connection to MSE Wall Underdrain.

a. Please indicate which S-501 underdrain pipe run(s) applies to detail C2/S-503. It is unclear if detail C2/S-503 applies only to the underdrain at the MSE Wall levelling pad.

RESP: At each location shown on the grading plans, each of 3 underdrains shown on A1/S-501 requires an outlet per detail C2/S-503. Outlets may be combined such that only one pipe penetrates the MSE wall at each location. See forthcoming amendment.

b. Does the underdrain pipe located at the bottom of the reinforced fill and retained fill intersection (bottom right of S-501) receive an outlet pipe?

RESP: See response to Question No. RFI 55a.

78. Reference: SPEC SECTION 01 32 17.00 20 Page 10 - Subpart 1.10.2.8 Adverse Weather Lost Work Days – last paragraph reads: “The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time only extension for the difference of days between the anticipated and actual adverse weather delay if the number of actual adverse weather delay days exceeds the number of days anticipated for the month in which the delay occurs and the adverse weather delayed activities are on the longest path to contract completion in the period when delay occurred. A lost workday due to weather conditions is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity. Make changes to P6 project calendars to reflect as-built conditions where work occurred where originally anticipated as non-work days, and where work did not occur (lost work day).”

Please clarify how will the stated 50% of the day be calculated? Does it mean one period of several hours rain or sum of interrupted hours at different times of work day?

RESP is deferred.

If it is calculated based on sum of total interrupted hours at different times of work day, please be advised that due nature of this project (major earthwork and site concrete work) if the calculated 50% of rainy weather happens in different times of the day will lead to non-work day, because once crews commence working, prepare the site to recover from storm then another rain shower took place, crews have to stop before performing any work. However, if rain is continuous for 50% of work day (takes place in one continuous period) then contractor is able to get 50% of continuous ½ work day without interruption, in this case contractor’s crew can be to some extent productive.

RESP is deferred.

Accordingly, we respectfully request to add a clause in the spec to entitle the contractor to claim for weather lost work days if 50% of rainy weather in certain days took place during different times of work day.

RESP is deferred.

NOTICE NO. 3 QUESTIONS AND ANSWERS CONTINUE

119. Reference: Existing Man-Camp and Structures at Angaur Island. Question:

Please advise if NAVFAC is able to assist all bidders to contact the owners of existing vacant portable modular containers at the newly constructed Antenna site and old concrete structure barracks. There will be some cost saving if the contractor is able to utilize these temporary structures for man-camp. Contractor may purchase some of existing portable containers or renovate existing concrete structures if they are structurally sound.

RESP: Response is deferred.

120. Reference: Price Proposal Schedule – CLIN No. 0001AB – Mobilization and Demobilization. Questions:

a. Is there a limited amount or percentage of total price proposal allowed for mobilization and demobilization?

RESP: No.

b. Is it allowed to allocate cost of purchasing new heavy construction equipment to CLIN No. 0001AB?

RESP: No. In accordance with DFARS 252.236-7004 and DFARS 236.570(2)(b)(ii), the Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant equipment and material only.

c. Is it allowed to allocate cost of man-camp and all temporary facilities to CLIN No.

0001AB?

RESP: See response to Question No. 120.b.

d. Is it allowed to allocate cost of concrete batching plant(s) to CLIN No. 0001AB?

RESP: See response to Question No. 120.b.

121. Reference: Cost of Soil Disposal area preparation. Question: There will be a significant effort required to prepare, maintain and store soil disposal area, please advise if this is acceptable to allocate this cost in CLIN No. 0001AB mobilization & demobilization pay item.

RESP: See response to Question No. 120.b.

122. Reference: Drilled shaft required for the security and light poles. Question:

Due to unavailability of drill rig on island of Palau, to perform drilling for the security and light poles foundation drill rig has to be shipped from off island for Tx & Rx sites.

Is it feasible for the engineer to re-design drilled shaft foundation to replace it with cast in place spread footing and concrete pedestal?

RESP: A shallow foundation/spread footing system may be used for the lightning and camera poles. See forthcoming amendment.

123. Reference: SPEC SECTION 03 30 00 Page 26 - Sub-section 3.6 BATCHING, MEASURING, MIXING, AND TRANSPORTING CONCRETE reads:

“In accordance with ASTM C94/C94M, ACI 301, ACI 302.1R and ACI 304R, except as modified herein. Batching equipment must be such that the concrete ingredients are consistently measured within the following tolerances: 1 percent for cement and water, 2 percent for aggregate, and 3 percent for admixtures. Furnish mandatory batch ticket information for each load of ready mix concrete.” Question: Please confirm that batching aggregate and cement shall be based on mass (weight) not volume per ASTM C94/C94M. In other words, volumetric mixer is not allowed to be used to batch and mix concrete.

RESP: On-site batching will be allowed. Volumetric batching will be allowed per ASTM

685. See forthcoming amendment.

124. Reference: RFP due date of March 21st, 2022. Question: Due to the complexity of this project, logistics, number of unanswered critical RFIs, required extensive time and effort to perform testing and investigation for available local materials to verify compliance with the specs, also taking into consideration long time required to search for alternative off-island suppliers we respectfully request to extend the RFP due date at least four weeks. Please be advised, additional time will help tremendously to submit competitive pricing which will eventually reduce the ultimate cost of this project.

RESP: See Amendment 0003.

125. Reference: Angaur Site – manufactured on site fill. Questions:

a. Can the government’ geotechnical engineer assure bidders that crushed / manufactured onsite soil is competent / suitable to meet fill spec and can be used to balance the site?

RESP: Base bids on the assumption that the crushed/manufactured onsite soil is suitable to meet fill specifications. See forthcoming amendment.

b. If onsite soil is not suitable to balance Angaur site, will the contractor be entitled for cost adjustment / change order?

RESP: If the onsite material is determined not suitable to use as fill, it will be handled as a changed condition. See forthcoming amendment.

c. Considering the massive risk associated with scenario of having on site soil not meeting spec of fill material which means imported material from other island and export excavated unsuitable soil off-Angaur bidders will include large contingency.

Accordingly, we respectfully provide guidance to all bidders to base price on certain scenario (e.g. using manufactured onsite material to balance the site), in this case all bidders price same scope.

RESP: See response to Question 125a.

126. Drawing S-001, Foundation Note: 7 States - “POCKETS OF ELASTIC SILTS

MUST BE REMOVED AND REPLACED WITH CONTROLLED LOW STRENGTH

MATERIAL (CLSM). PROBE HOLES AND CAVITIES MUST BE GROUTED WITH

CLSM AS SPECIFIED. “

For bidding purposes, please clarify extent of Elastic Silt pockets to be removed and replaced.

RESP: Pockets of elastic silt must be removed to a maximum of 1 meter under the slab subgrade and replaced with Controlled Low Strength Material (CLSM). The elastic silt pockets to be removed will not exceed 10% of the slab area. See forthcoming amendment.

127. Drawing s-501. TYPICAL MSE WALL SEC A1 shows “UNDERCUT TO 610

BELOW TOP OF BEDROCK AND REPLACE WITH SELECT FILL, SEE NOTE 2.”

For bidding purposes, please advise how above note will be applied in case of other materials?

With respect to this note, what assumptions should we use for bed rock elevations?

RESP: Undercut to 610 below top of bedrock and replace with select fill, see note 2;

undercut is limited to 1/2H (height of the wall). See forthcoming amendment.

128. Drawing CS106. Referring to CS106-Tx Site plan, FRP fence around the QVIS Antenna will be with barbed wire or not, please clarify.

RESP: Barbed wire is not required for Tx QVIS FRP Fence. See forthcoming amendment.

129. Drawings: CS101 to CS109. Referring to CS101 to CS109-Tx Site plans, fences not shown in these drawings but seen in CS004 will be under scope of contractor, please confirm.

RESP: CS004 is a general plan and not a technical plan. See CF sheets for fencing requirements.

130. Drawing: CS106. In CS106-Tx Site Plan, FRP fence around the QVIS Antenna shown as FRP but same fence is defined as composite cattle in drawing CF104-Tx Fencing & Grassing Plan, please clarify.

RESP: See revised CF104 in Amendment 0002.

131. N62742-22-R-1322+Front+End (1), page 9 of 28. Soil disposal site is pointed in referenced document, will there be any fee to dispose material to shown area, please clarify.

RESP: See Response to Question No. 9c.

132. General. Please clarify if workforce housing facilities will be permitted at the construction sites (TX & RX).

RESP: Response is deferred.

133. Contract Performance Period.

COMMENT: The Standard Form SF1442 and the Government’s response to RFI No. 12 appears to be at odds regarding the likely date of a common Notice to Proceed (NTP) for both the Transmit & Receive sites. SF1442 references a bid validity period of 180 calendar days following the proposal submission date. If this were to run its full course the forecasted NTP following the 21-day grace period for submission of bonds would be October 08, 2022. The government response to RFI No. 12 puts the anticipated completion of the separate contract for UXO/MEC clearance of the Receive Site as June 2023, an interval of some 240 calendar days later.

QUESTION: Are we to assume that each site will have separate NTP dates and that the period of performance confirmed as 1,095 calendar days (Notice 01) will be extended by approximately 240 calendar days to accommodate the latest of the two release date?

Alternately, are we to assume that the performance period for the Receive Site will be compressed by an identical period needed to complete the UXO/MEC removal, clearing and grubbing under a separate contract prior to granting possession to the Offeror?

RESP: There is only one contract completion date of 1,095 calendar days after NTP.

Base bids on receiving the Rx site no later than June 30, 2023.

134. Contract Performance Period.

COMMENT: Document 00 70 00 listed the period of performance to execute the entire work ready for use as 1,095 calendar dates following issuance of the Notice to Proceed.

The logistical challenge of undertaking twin operations of this magnitude on Babeldaob and the equally remote and austere island of Anguar is a monumental task with a low likelihood of success given the better part of 220 rainy days per year and the shortage of homegrown skilled labor.

QUESTION: It is our belief that the performance period needs to be extended by a further 240 calendar days to 1,338 calendar days in order to provide a reasonable opportunity for success.

RESP: The performance period remains unchanged. See Section 01 14 00, paragraph

1.3 and Section 01 32 17.00 20, paragraph 1.10.2.8.

135. Drawing sheets CG151 & CG152, Finish elevations at the borrow pits. Please clarify if the indicated finish elevations at the borrow pits can be adjusted to minimize surplus or allow a balanced site earthwork

RESP: See response to Question 17 for borrow pit elevations.

136. Dwg S-506/A2 & A4. Please provide the concrete strength for rapid setting concrete mentioned for settlement plate & slope inclinometer-piezometer well.

RESP: Minimum strength for rapid setting concrete shall be 3ksi (21 MPa). See forthcoming amendment.

137. Dwg S-001/Note 6. Please provide the diameter of probe & grout under slab on grade, please provide the area covering one probe.

RESP: 50mm diameter probe. Section 35 42 34, paragraph 3.2.1 will be revised in a forthcoming amendment.

138. Dwg S-001/ Design Note #3 & M-601 Schedule. The capacity of rainwater storage tank on Dwg S-001 the capacity is 3,786 liters. Per Dwg M-601 schedule the capacity is 2,650 Liters. Please clarify what the capacity of the tank should be.

RESP: Minimum capacity for the Rainwater Storage Tank on DWG M-601 is correct.

See forthcoming amendment.

139. Dwg CS106. Drawing CS106 shows QVIS Antenna, but rest of the drawing do not provide any details for foundations. Please provide the same.

RESP: See Response to Question No. 16a.

140. Dwg E-505/A2. Drawing E-505 shows Disconnect switch footing and encasement for conduit without providing required strength of concrete. Please provide strength of concrete and details.

RESP: Refer to Section 33 71 02, paragraph 2.11 Cast-in-place Concrete. Provide 30MPa minimum 28-day compressive strength.

141. Dwg ES-151 thru ES-156. Please provide typical details for manholes shown on drawings ES-151 thru ES-156.

RESP: Follow manhole detail on DWG E-506 for all manholes for both transmit and receive site except for manhole MH-T2 at transmit site. Follow manhole details on DWG E-507 for MH-T2. See forthcoming amendment.

142. Dwg CD-101 thru CD-118, CD-151 thru CD-164. Please provide the specification section for demolition of existing structures & existing utilities.

RESP: See forthcoming amendment.

143. Dwg TS151 thru TS155. Please provide the specification section for infrastructure for underground telecommunication distribution.

RESP: Follow Section 33 71 02 for both electrical and telecom underground distribution infrastructures.

144. Dwg CF511. Drawing CF511 shows details of fence signages, please provide missing specification section

RESP: See forthcoming amendment.

145. Dwg CS104 thru CS106. Drawings CS104 thru CS106 shows camera switch concrete pad, please provide the details for the same.

RESP: See response to RFI 122.

146. Dwg CS157 & CS161. Drawing CS157 & CS161 shows existing costal road, please provide details for transition from gravel access road A.

RESP: There is no overlap between the new gravel access road A and the existing coastal road.

147. Dwg’s CS154, CS157, CS161 & CS164. Please provide sectional details for existing coastal road for restoration purpose.

RESP: The as-built condition of the coastal road is unknown.

148. Dwg CF510. Please provide the location for cattle gate shown on Dwg CF510.

RESP: DWG CF510 was deleted in Amendment 0002.

149. Dwg CF104. Fence marked at QVIS Antenna area is indicated as Cattle Fence, but the legend shows FRP Fence. Please clarify.

RESP: See response to Question No. 130.

150. Dwg CF105. Dwg CF105 shows Installation of Warning sign @ 91.44 OC, whereas Note 1 on the same drawing says 30.458 OC. Please clarify.

RESP: See revised DWG CF105 issued under Amendment 0002.

151. Dwg CF511. Please provide locations of Metallic Signages shown on Dwg CF511

RESP: See revised CF DWGs included in Amendment 0002.

152. Dwg CS161. Please identify the black dots shown at the end of Access Road B and C and provide the details.

RESP: See revised DWG CS161 in Amendment 0002.

153. Dwg’s CD151, CD152, CD154, CD155, CD157, CD160, CD161, CD163, CD164.

Please provide construction fence details shown on Erosion Control and Demolition Plans.

RESP: See response to Question No. 22.

154. Dwg CD113. Please provide details of Gravel Bag Filter Berm shown on Plan

CD113.

RESP: See forthcoming amendment

155. Dwg CE503/B4. Please provide locations of Diversion swale Type B shown on Detail B4/CE503.

RESP: Response is deferred.

156. Spec Section Part 1 of 5/ Page 32/ 91-00609-00 Sheet 5 of 14. Please clarify what N10 represents in the term “N10 Mass concrete”.

RESP: Weak Mix (N10) Mass Concrete has a minimum compressive strength of 10 Mpa.

157. Spec Section Part 1 of 5/ Page 43 / 910061100 Sheet 2 of 4. Text on this sheet is not readable. Please provide readable copy.

RESP: See forthcoming amendment.

158. Dwg’s B-150, B-751, B-754, B-755, B-756. Per Dwg B-150, Bore Holes - B-1, B- 27, B-35, B-37, B-39, B-40, B-41 are in close vicinity.

For Bore Holes B-1, B-27, B-35, B-37, B-41, bore logs are showing top layer as GP or GM, but no ML. But for Bore Holes B-39, B-40, bore logs show ML as top layer but no GP or GM.

For Bidding purposes, please confirm B-39, B-40 can be discarded and remaining can be used.

RESP: No

159. Notice Number 1 Q&A # 104. The response to Question 104 stated that DFARS 252.204-7012 is a required clause for all solicitations and contracts. We agree that the clause is required, however, please confirm if anything in the solicitation has been determined by the Government to be “covered defense information” as defined in the clause?

RESP: See Section 01 31 23.13 20, paragraph 1.6.1.

160. Notice Number 1 Q&A # 105. The response to Question 105 stated that DFARS 252.204-7012 is a required clause for all solicitations and contracts. We agree that the clause is required, however, please clarify does the Government anticipate that any of the deliverables to be provided under the contract will be “covered defense information” as defined in the clause?

RESP: See Section 01 31 23.13 20, paragraph 1.6.1.

161. Spec Section 00 01 15 Page 7 Paragraph 1.3. Spec references three types of antennas at both the TX & RX sites. Please specify the location and detailed drawing of Diagnostic Antenna for TX-Site.

RESP: See response to Question No. 16a.

162. Spec Section 00 01 15 Page 7 Paragraph 1.3. Please provide detailed drawing of Delta QVIS Antenna for TX Site

RESP: See response to Question No. 16a.

163. Reference: Supplementary Drawing 91-00609-00 – HF Radar Tx Site Layout TACMOR. Question:

a. The abovementioned drawing shows that a wire grid has to be installed in the Antenna Earth Mat area. Who is responsible for the installation of this wire grid? If installed by others, please confirm that the grid will be installed during construction.

RESP: The wire grid will be installed by others after the completion of the construction contract. See DWGs CG301 and CG302 for Antenna Earth Mat area requirements.

b. What’s the duration required to install the grid? This info is required to incorporate it in the project overall schedule.

RESP: See response to Question No. 163a

164. Reference: Supplementary Drawing 91-00560-00 – RX Site Layout TACMOR – Detail C. Question:

a. Detail C of this drawing shows a ground mat 0.10x0.10 grid to be installed in the Earth Mat area. In the Site Drawings (Sheet CS051) of PAF 198127 TACMOR Drawings, the same area is indicated to be covered with Aggregate Surface Course Gravel per detail B1/CP501.

RESP: See response to Question No. 163a.

b. Who has to install the ground mat 0.10x0.10 grid in the Earth Mat area? If the general contractor has to install it, please provide Specs and details for this scope.

RESP: See response to Question No. 163a

c. If installed by others, does it have to be installed during the duration of the current project? What’s the duration required to install the grid? This info is required to incorporate it in the project overall schedule.

RESP: See response to Question No. 163a

165. Reference: Supplementary Drawing 91-00560-00 – RX Site Layout TACMOR Question: Who has to install the cables and cable trenches indicated in this drawing?

RESP: Cable and cable trenches and are to be installed by others after completion of the construction contract.

166. Reference: Supplementary Drawing 91-00560-00 – RX Site Layout TACMOR Question: There is a note in this drawing about cable pit dimensions being 2mx2mx2m.

In the Telecom Drawings (Sheets TS151-TS155) of PAF 198127 TACMOR Drawings, there is a Telecom Handhole to be installed in the same location of the cable pits. THH dimensions per detail A2/E501 are 1.41mx1.21mx1.135m. Please clarify which dimensions to follow?

RESP: Response is deferred.

167. Reference: CLIN 0001AC & CLIN 0001AD. Question:

a. Please clarify how will the quantity of the above two items be measured? Will it be measured as a stockpile at disposal areas (SD1 & SD2)? If so, what’s the height of stockpile? Please note that reduction in volume of stockpiled material depends on the height of stockpile, in other words the higher stockpile will lose more volume due to consolidation. Therefore, for fair price comparison, please provide stockpile plan or at min provide standard height of the stockpile to allow all bidders price this item based on same condition.

RESP: See response to Question No. 37a and Amendment 0002.

b. Description of the above items indicates excavation and removal off-site. Since Excavation is part of earthwork scope please confirm that the contractor has to allocate cost of excavation in the above CLIN items and does not have to include any excavation cost in CLIN 0001AA.

RESP: Yes, allocate cost of basalt excavation in SLIN 0001AC and soil excavation in

SLIN 0001AD.

c. If there is a discrepancy in provided quantity in price schedule and actual quantity based on field measurements, does this means that the contractor will be compensated based on actual quantities to be determined during construction? Please clarify, this is a very critical cost item.

RESP: Yes, see SF1442, Price Schedule, Note 8.

d. Do the above CLIN items cover only mass grading? Or do they cover other site structural excavation and trench excavation?

RESP: SLIN 0001AC and SLIN 0001AD only cover mass grading.

e. What’s the criteria to classify to determine excavated material as basalt rock / hard material?

RESP: Unweathered basalt bedrock is defined in Section 31 23 00.00 20, paragraph 1.2.3.

f. If certain excavated soil is encountered with hardness between basalt rock and soil, how will this material be paid?

RESP: It will be paid as soil.

g. During bidding stage, if there is a discrepancy between provided quantities in price schedule and contractor’s take off quantities, please clarify how the two cases will be addressed:

Case (1) If the contractor’s quantity is more than provided quantity in price schedule, does this mean that the contractor has to follow the price schedule quantity with the intent to get compensated for additional quantity during construction?

RESP: If the actual quantity is more than the estimated quantity stated in the price schedule, FAR 52.211-18, Variation in Estimated Quantity will apply. See SF1442, Price Schedule, Note 8.

Case (2) If the contractor’s quantity is less than provided quantity in price schedule, does this mean that the contractor has to price based on higher quantity provided in the price schedule with the intent to give credit during construction?

RESP: Base bids on the estimated quantity stated in the price schedule. Should the actual quantity be less than the estimated quantity stated in the price schedule, FAR 52.211-18, Variation in Estimated Quantity will apply. See SF1442, Price Schedule, Note 8.

h. Since the actual surplus quantities of basalt rock and soil be derived by the contractor’s means and methods, therefore if a contractor “A” intends to process and utilize onsite material will be compensated less because he/she will generate less surplus than contractor “B”, if contractor “B” intends not to maximize utilizing onsite material. This case will cause unfair price evaluation. Therefore, we respectfully remove these two CLIN items CLIN 0001AC & CLIN 0001AD and have all bidders to include these costs in base bid and direct all bidders to just haul surplus soil to designated soil disposal site. In this case contractor who is planning to balance the site using processed on site material will be rewarded for this effort due to reducing the cost and not on the contrary to be at price disadvantage. Please review this critical matter and advise.

RESP: Response is deferred

168. Reference: RFP due date of March 21st, 2022. Question:

We have been approached by several vendors requesting to extend the proposal due date. Please be advised, after receiving clarifications to all RFIs, we need to modify or complete relevant quantity take off or scope of works then send the info to the vendors and shipping companies for pricing. Due to pending answers to critical RFIs have been / will be submitted, we respectfully extend the RFP submittal due date to at least 4 weeks from date of receiving answers to all RFIs

RESP: See response to Question No. 124.

169. Reference: Supplemental drawing No 91-00560-00 indicates mass concrete.

Question:

We did not find any spec related to mass concrete. Please confirm that there is no structural element qualified to be as mass concrete.

RESP: See response to Question No. 156.

170. Reference: Man-Camp / Temporary Facilities. Question:

a. Is it allowed to leave Man-Camp / Temporary Facilities on site at free charge to be utilized by others (e.g. subsequent contractor(s))?

RESP: Response is deferred.

b. After construction is completed, is it allowed to dispose crushed concrete. green waste and other uncontaminated materials on site at designated location(s) to be provided by NAVFAC? If yes, please provide locations of onsite designated dump sites.

RESP: Response is deferred.

171. Follow-up to Q&A No. 9C, Terms for the use of SD 1 (disposal site 1).

Negotiations with the Ngaraard state for the use of SD 1 cannot be concluded before the submission of the bid, we suggest the Government provide an allowance for this purpose which is subject to change after negotiation.

RESP: Base bids on no cost for the terms of use of the SD sites. Any fees or costs associated with the terms of use of the SD sites incurred will be handled as a changed condition. See forthcoming amendment.

172. Spec. Section 35 42 34 /para 3.2.1 & Dwg S-001/Foundation Note #6. Please provide Specification Section for Probe and Grout for MSE wall on TX Site and Slab on Grade on RX Site.

RESP: There is no separate specification section for probing and grouting. See Section 35 42 34, paragraph 3.2.1. for MSE wall probing requirements and DWG S-001 for Rx Site probing and grouting requirements

173. Spec. Section 35 42 34 /para 3.2.1. Please provide the diameter for Probe and Grout for MSE wall on TX Site.

RESP: See response to Question No. 137.

174. Spec. Section 05 50 13 / Para 2.2.2. Please provide the location for Structural Tubing referenced in Spec. Section 05 50 13 Para 2.2.2.

RESP: No structural tubing is included in this project. See forthcoming amendment.

175. Spec. Section 05 50 13 / Para 2.3.4.2. Para 2.3.4.2 Pretreatment, Priming and Painting- references Spec. Section 09 97 13.26 Coating of Steel Waterfront structures.

Please provide Spec. Section 09 97 13.26.

RESP: Any reference to Section 09 97 13.26 will be removed from the specifications.

See forthcoming amendment.

176. Dwg S-522 / B5 & C5. Dwg S-522 details B5 & C5 reference “Galvanized Removable Grating” Please provide Spec. Section for Galvanized Removable Grating.

RESP: Section 05 50 13 will be revised in a forthcoming amendment.

177. Dwg CE503 TX & RX Erosion Control Details-3 / Detail A3. Please provide the dimensions (length and width) of Rock Check Dams for Bidding Purpose.

RESP: Response is deferred.

178. Dwg’s CD117, CE503 / Detail A3 Rock Check Dam. Please provide Gravel Check Dam Detail.

RESP: Gravel Check Dam will be revised to Check Dam. See forthcoming amendment.

179. Spec. Section 05 50 13 / Para 3.10. Please provide the location for Safety Chain referenced in Spec. Section 05 50 13 Para 3.10.

RESP: Safety chains specified in Section 05 50 13, paragraph 3.10 are not required.

Paragraph 3.10 will be deleted in a forthcoming amendment.

180. Dwg S-520 TYPICAL SLAB-ON-GRADE PLAN, SECTION, AND SCHEDULE.

Slab-on-Grade Schedule Dwg S-520 reference “Transformer (Secure Compound) TX / RX Site”. Please provide location for Transformer (Secure compound) on TX plans.

RESP: There is no transformer slab at the Tx site. See forthcoming amendment.

181. Spec Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, 2.3 FENCING. Subpart 2.3 describes three types of temporary fencing:

2.3.1 - Polyethylene Mesh Safety Fencing

2.3.2 - Chain Link Panel Fencing and

2.3.3 - Post-Driven Chain Link Fencing.

Please advise which type/s of Temporary Fencing is/are applicable to this project and provide the location/s for the same.

RESP: The three types of temporary fencing described in Section 01 50 00 are permitted options from which the contractor can choose. See forthcoming amendment.

182. Spec Section 01 45 35 SPECIAL INSPECTIONS, SCHEDULE OF SPECIAL INSPECTIONS. Subpart 1.5 SPECIAL INSPECTOR QUALIFICATIONS does not list any Special Inspector or Associate Special Inspector for PLUMBING or MECHANICAL or ELECTRICAL trades. But, SCHEDULE OF SPECIAL INSPECTIONS has a checkbox in front of PLUMBING/MECHANICAL/ELECTRICAL DESIGNATED SEISMIC SYSTEMS SECTION. Please clarify if PLUMBING/MECHANICAL/ELECTRICAL DESIGNATED SEISMIC SYSTEMS SECTION is applicable?

If it applicable, please provide qualifications required for Special Inspector or Associate Special Inspector.

RESP: Confirmed. See forthcoming amendment.

183. RFP N62742-22-R-1322, SF 1442 (Continued), Page 3 of 4. Reference: RFP N62742-22-R-1322 document- 5 page 93- "SLINs 0001AC-0001AG " subject has mentioned at the 4th note, the SLIN 0001AG not included in the price proposal schedule table. Please confirm that the SLIN 0001AG is SCLIN 0001AD?

RESP: Confirmed. See Amendment 0002.

184. RFP SF 1442 Rev 1 AMD 1 Page 3 of 4 (Bid Form) Item SLIN 0001AC. Item 000 AC Basalt Rick Removal Qnty is 49,600 M3. Please clarify if the quantity listed is bank M3 volume or loose M3 volume.

RESP: See response to Question No. 37a.

185. RFP SF 1442 Rev 1 AMD 1 Page 3 of 4 (Bid Form) Item SLIN 0001AD. Item 0001AD Surplus Soil Removal Qnty is 291,560 M3. Please clarify if the quantity listed is bank M3 volume or loose M3 volume.

RESP: See response to Question No. 37a.

186. Follow-up to Q&A No. 34 Notice 1, Hydroseeding without topsoil at Rx Site. Since top soil is not required prior to the hydroseeding at Rx Site, please advise what is the minimum growth requirement for acceptance at project turn-over

RESP: Final inspection and acceptance is 95% groundcover of established species.

See Section 32 05 33, paragraph 3.2.7.

187. Dwg. CF509 and Spec Section 32 31 16, TX Site – Composite Cattle Fence Post & Brace Material. Drawing CF509 detail calls out for composite posts and braces. Spec.

section 32 31 16 includes para 2.2 Wood composite composition (wood and plastic composite), whereas para 2.3 states “Provide wood composite post and rails cut from sound and solid trees free from short or reverse bends in more than one plane.” (Which seems to indicate solid treated wood with no composite). Please clarify.

RESP: Paragraph 2.3 Wood Posts and Rails will be deleted from Section 32 31 26.

See forthcoming amendment.

188. S-001, Foundation note #6, Probe Holes & Grouting. Please clarify the following:

a. Please provide the minimum area of slab on grade per 1 probe hole for the RX slab.

RESP: Probing must be performed at a center-to-center spacing of not more than 4.6m and at least one probe for every 21.1 square meters of slab/spread footing foundation, but not less than one probe per a foundation. See forthcoming amendment.

b. For RX Monopole pile footing (296 locations), is probing & grouting required?

189. S-506, detail A4, Slope Inclinometer – Piezometer Well. The TX slope inclinometer (5 locations-approximate depths of 84 feet) as shown on detail A4/S-506 the bore hole at lower portion required only 135mm dia. while on the upper portion required 170mm dia. Please advise if 170mm bore hole may be used for lower portion instead of 135mm dia.

RESP: 170mm bore hole diameter may be used for the lower portion instead of 135mm diameter. See forthcoming amendment.

190. RFP Factor 2 Past Performance. Factor 2 of the RFP states: “PPQ shall be completed and signed by the contracting agent and/or their representative responsible for the construction contract administration. A PPQ shall not be from a prime contractor to a subcontractor. The Offeror shall provide completed PPQs in the proposal. Offerors may submit PPQs previously submitted for other solicitations. We presume a subcontractors’ past performance will be acceptable if a PPQ is provided by the “contracting agent”. In this case the contracting agent is a prime contractor that issued a subcontract. We are interrupting the language above to mean the prime contractor for this Palau RFP is unacceptable to prepare a PPQ for a subcontractor. Is this correct?

RESP: No, a PPQ cannot be from a prime contractor to a subcontractor.

191. Spec. Section 31 23 00.00 20, Para. 2.1.1 / 2.1.5. At the Tx site, any common fill must meet the requirements of Section 31 23 00.00 20, Para. 2.1.5. Para. 2.1.5 states that Common Fill must comply with Para. 2.1.1, Satisfactory Materials. According to the Geotechnical Report, it does not appear likely that the excavation will meet the requirements of Satisfactory Materials under Para. 2.1.1 as GW, GM, GW-GM, SW, SM, or SW-SM. The specified requirement makes this material a select material. The majority of the material mined is MH or ML. Does the Government anticipate that the common fill for the Tx site will need to be imported as well?

RESP: Yes

192. Spec. Section 31 23 00.00 20, Para. 2.1.1 / 2.1.5. At the Rx site, any common fill must meet Section 31 23 00.00 20, Para. 2.1.5. Para. 2.1.5 states that Common Fill must comply with Para. 2.1.1, Satisfactory Materials. According to the Geotechnical Report, it does not appear likely that much of the excavation will meet the requirements of Satisfactory Materials under Para. 2.1.1 as GW, GM, GW-GM, SW, SM, or SW-SM & 75 mm minus, without substantial processing. The majority of the material mined is coralline limestone. Does the Government anticipate that the majority of the common fill for the Rx site will need to be processed in order to meet the contract requirements?

RESP: See response to Question No. 125a

193. Spec. Section 01 50 00, Para. 3.5.8. Are we are responsible for the integrity and maintenance of the existing asphalt paved haul road from the Tx site to the soil disposal area? If so, please provide the existing structural section.

194. Sheet CU508, Detail C1 & C3, Spec. Section 32 12 16. The amount of new asphalt concrete is minimal on the project. Materials meeting the specification requirements of Section 32 12 16 in its current form are not locally available. Will the government relax specification requirements to allow for use of locally available materials for this small amount of asphalt concrete?

RESP: No

195. Sheet CP501 / Detail B1. On the Rx site, is the entire earth mat also the antenna area? Detail B1 (page CP501) specifically requires 610 mm of select material for the antenna area, but the plan sheets do not distinguish between the earth mat and the antenna area on the Rx site.

RESP: Rx Antenna Area is the same as the Earth Mat.

196. Spec. Section 31 23 00.00 20, Para. 2.1.7. The Rx site geotechnical report does not provide Liquid Limit or Plastic Index values to determine if Select Fill can be found on site or not? Section 31 23 00.00 20, Para. 2.1.7 requires a Plasticity Index less 12 and a Liquid Limit less than 35 in accordance with ASTM D4318. Can the Government provide additional geotechnical data or is it the intention of the government is for this material to be imported? Please provide full geotechnical report for both the Tx and Rx sites.

RESP: Response is deferred.

197. Spec. Section 32 11 23, Para. 2.1.1.1. Can the Government provide LA Abrasion (ASTM C131 / C131M) and Sodium Soundness (ASTM C88) test result for the in-situ material at the Rx site?

RESP: Tests were not performed to determine suitability of onsite material to be used as graded-crushed aggregate base course.

198. Plan Sheet CG302 / Detail A1 & C1. Page CG302 Detail C1 and A1 shows all fill material under the antenna area and out at a 2:1 slope to be Select Material at the Tx site. Is this correct?

RESP: Yes. See CG001 Notes 2 and 3.

199. Drawing set Vol 1 thru 7. The scale was incorrect for this drawing set. An example of this is in drawing sheet CX-704, the scale on bottom of page is for 1:1000, but the correct scale shall be 1:2000 in order for everything to dimensioned correctly. Please verify and update.

RESP: Follow graphic scale bars. Forthcoming amendment will revise DWGs CF107, CR101, CR102, CP104, CU101, and CP151.

200. Drawings CD-111, CD-118 and CD-601. For a more accurate estimate, please provide as-built drawings for Existing structures/Buildings A1, A2, A3, A4 and A5 to be demolished.

RESP: As-built drawings for the existing structures/buildings on the Tx site are not available.

201. Drawings B-100, B-705, B-706, CX-001 and CX-704. Per Drawing sheet CX-704, the average excavation depth is greater than 10 meters for stations 02+00 thru 0+160.

Please provide additional proposed contour lines in this area for accurate cut/fill calculation.

RESP: Response is deferred.

202. Drawings CS-102 and CS-501. Non-metal bollard is shown as per detail drawing B1/CS-501. Please specify type, material and foundation detail.

RESP: See response to Question No. 32. Foundation not required.

203. Spec Section 31 11 00, Page 4, Para 3.3.1. Spec Section 31 11 00, page 4, para

3.3.1 Tree removal noted "Dispose of trees as specified in paragraph DISPOSAL OF MATERIALS." Information is missing in the noted paragraph. Please specify the required process to dispose demolished trees.

RESP: See response to Question No. 13b.

204. Supplementary Drawing 91-00611-00, TX FMS Curtain. Please confirm that footing foundations are installed by Contractor. If so, please provide elevation of top of footings.

RESP: Footing foundations will be installed by the Contractor. The elevation of the top of footing is based on the LENCOM drawings and adjacent finished grade.

205. Supplementary Drawing S02-01, TX Antenna Array. Please confirm that footing foundations are installed by Contractor. If so, please provide elevation of top of footings.

RESP: See response to Question No. 204.

206. Section 03 30 00, par 2.3.3, Concrete Aggregates. Question:

The only concrete and aggregate supplier in Palau does not have all the testing records required of the local aggregates for evaluation. Additional tests are required to determine if it complies with the project requirement, the ASR test, LA abrasion test, sand test per ASTM D304, aggregates test per ASTM C33 test for deleterious materials are not available. Turn around for these tests is approx. 60 days which includes shipping of samples to an off-island laboratory.

Note: Without these test results, we have no recourse but to use imported concrete aggregates at a very high premium

Proposed solution:

1. Extend the bid date by 60 days to allow completion of the necessary testing.

2. For bid purposes, allow the use of the local aggregates subject to a change condition if found to be unacceptable after contract award.

For bid purposes provide bid allowance, a per ton U/C of aggregates FOB plant.

RESP: Base bids on using local aggregates. Contractor will be responsible to perform the required testing in accordance with the specifications. Should the aggregate be found to be unacceptable, it will be handled as a changed condition.

207. Reference: Notice 2 – Answers to Question 59 a & d indicate that Topographic surveys and soil boring logs of SD1 and SD2 are not available.

Question:

RFP specs - Figure 6 is provided as a Reference Images of the Proposed Soil Disposal 1.

RFP specs - Figure 11 is provided Slope of access route to proposed SD 1. One-meter contours are extrapolated from the 1980 USGS topographic map and are not precise.

RFP specs - Figure 23 indicates Location of SD 2.

Based on the above provided information:

a. SD1: Total Area is approximately 10 Acres site, with elevation difference more than 60 ft North South. In order to utilize the SD 1 site as stockpile to accommodate all surplus basalt & soil, major site grading and retaining walls (60 ft tall) will be required to provide safe flat area for trucks to access the site. In order to avoid constructing costly retaining walls @ SD 1, please advise if the government is able to expand SD1 area to allow sloping / daylighting cut / fill to encroach into adjacent property to SD1?

Otherwise, we respectfully request the project design team to provide design for the SD1 site preparation including permanent structures (retaining walls), drainage..etc this is a design bid build solicitation and bidders are not responsible for design.

Please be advised, this is a major cost (millions of dollars) that all bidders shall include in the bid and more information is required from designers to avoid costly assumptions.

b. Assuming that existing SD 1 is flat or the wining contractor will make it flat, based on volume of surplus materials and in order to provide safe access and safe stockpile plan, please be advised that 10 Acres Area is not sufficient to accommodate two separate stockpile (basalt & soil).

Please advise if all bidders shall assume that the government will be able to expand SD 1 area to accommodate ALL generated surplus materials. Please provide clear directions regarding this matter to allow all bidders to fairly price same conditions.

c. SD2: Total Area is approximately 5 Acres site, assuming that existing SD 2 is flat, please be advised that based on volume of surplus materials and in order to provide safe access and safe stockpile plan, the 5 Acres Area is not sufficient to accommodate two separate stockpile (basalt & soil). The 5 Acres SD 2 site will accommodate small portion of surplus basalt / soil which does not justify the cost to prepare access, BMPs, grading ..etc.

Please advise if all bidders shall assume that the government will be able to expand SD 2 area to accommodate ALL generated surplus materials. Please provide clear directions regarding this matter to allow all bidders to fairly price same conditions.

RESP: Response is deferred.

d. In case SD1 & SD2 are inadequate to accommodate stockpiles of surplus soil and basalt rock, will the contractor be entitled for price modification / change order?

Please provide clear directions regarding this matter to allow all bidders to fairly price same conditions.

208. Reference: Price Proposal Schedule – CLIN No. 0001AB – Mobilization and Demobilization. Questions:

a. Please confirm that payment under CLIN No. 0001AB shall be made in accordance with “DEFARS 252.236-7003 Payment for Mobilization and Preparatory Work” which indicates:

“As prescribed in 236.570 (b)(2), use the following clause:

PAYMENT FOR MOBILIZATION AND PREPARATORY WORK (JAN 1997)

(a) The Government will make payment to the Contractor under the procedures in this clause for mobilization and preparatory work under item no.

(b) Payments will be made for actual payments by the Contractor on work preparatory to commencing actual work on the construction items for which payment is provided under the terms of this contract, as follows—

(1) For construction plant and equipment exceeding $25,000 in value per unit (as appraised by the Contracting Officer at the work site) acquired for the execution of the work;

(2) Transportation of all plant and equipment to the site;

(3) Material purchased for the prosecution of the contract, but not to be incorporated in the work;

(4) Construction of access roads or railroads, camps, trailer courts, mess halls, dormitories or living quarters, field headquarters facilities, and construction yards;

(5) Personal services; and

(6) Hire of plant.”

RESP: Payment under CLIN 0001AB will be made under DFARS 252.236-7004, Payment for Mobilization and Demobilization.

b. Please confirm that there is no limited amount or percentage of total price for CLIN No. 0001AB.

RESP: Payment will be based on 60% of CLIN 0001AB upon completion of the mobilization work and 40% of CLIN 0001AB upon completion of the demobilization work.

c. Please confirm that all costs related to temporary facilities, man-camp(s), stockpile area preparation, access roads, batching plant, onsite water treatment & sewage plant, generators, and all purchased heavy construction equipment for this projects can be allocated and paid under CLIN No. 0001AB.

RESP: In accordance with DFARS 252.236-7004 and DFARS 236.570(2)(b)(ii), the Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant equipment and material only.

209. Specification section 32 13 13.06, Paragraph 3.4. The quantity of road pavement work is relatively small. The Specifications require a self-propelled paver finisher. Can other finishing means be employed if they meet the same performance and tolerances required by the design?

RESP: Response is deferred.

210. Specification section 31 23 00.00 20, paragraph 2.1.1. Specification section 31 23

00.00 20, paragraph 2.1.1 defines the satisfactory materials as GW, GM, GW-GM, SW, SM or SW-SM. The geotechnical analysis shows that these types of materials are not existent within the project boundaries. The required conforming material will need to be selected and transported from outside of the project site/Palau. Can you please confirm the in-situ material cannot be reused by the Contractor?

RESP: Response is deferred.

211. RFP N62742-22-R-1322 Front End. Reference Item 001AC Basalt Rock is identified for removal at TX site. Please clarify if “alternate” methods (Chemical or blasting) can be used for breaking rock at TX site.

RESP: No.

212. RFP N62742-22-R-1322, DOCUMENT 00 73 00 Para 1.5. Paragraph 1.5 details a location for the COMPACT OF FREE ASSOCIATION (COFA) AND SUBSIDIARY

AGREEMENT OF THE COFA (SOFA) BETWEEN THE UNITED STATES AND THE

GOVERNMENT OF PALAU.

The link included in the RFP is broken and does not work.

The following message appears: Error message. The page you requested does not exist.

Can the Navy Provide working access to this documentation?

RESP: Please use the updated links shown in Amendment 0002.

213. RFP N62742-22-R-1322, DOCUMENT 00 73 00 Para 1.5. It appears the United States is currently in discussions with the Government of Palau regarding changes to the COFA to be revised by 2023. How will these changes impact the execution of work? The period of performance for construction will span both agreements.

RESP: NAVFAC Pacific is not involved in the COFA negotiation process and can provide no information or assurances regarding the scope of potential revisions to the COFA or whether the SOFA might be revised during the period of performance.

214. RFP N62742-22-R-1322 Amendment No. 0002, SF 30 BLOCK 14 CONTINUATION PAGE. We are discovering impacts to project execution, related to detailed international agreements between the United Sates and the Government of Palau. This combined with the numerous outstanding RFI’s and logistical complexity of the job requires additional response time. We need this time to properly vet all answered RFI Questions with our local and international subcontractors.

We understand the Mission Critical importance/Time constraints placed upon the Navy for award. We respectfully request the Navy consider allowing approximately 4 additional weeks of time for submission (5/3/22 @ 1400HST).

Extending the solicitation date will provide adequate time to coordinate details for best-value pricing.

RESP: See Amendment 0003.

215. PAF 198127 TACMOR_DWGS 7 of 7. Note 6 on Sheet S-001 requires performing probe testing to define voids and cavities under the foundations and slab on grade concrete. According to this note after finding the voids or cavities these locations must be grout-filled under at least 25 PSI air pressure with high slump sand-cement mixture or low strength concrete having at least 1500 PSI of 28-day compressive strength. Because of the unknown condition of voids/cavities how this grouting works should be included in the proposal?

RESP: Approximate volume of pressurized grout is 60 m3. See forthcoming amendment.

216. Specification section0 0033 30 00. Air content for concrete is essential for the freezing and thawing climate conditions. Project area is located at hot climate condition.

Concrete air content requirement will be useless for this climate condition. Please confirm that air content is mandatory or not for all type of concretes.

RESP: Yes, air entrainment is mandatory for all types of concrete.

217. CG-101, S-501 Detail A-1, S-503 Detail C-1, C-2, C-3. There is no detailed drawing on how the drainage channels specified in the dwg. S501/A1 will drain the water with perforated drainpipes (beside the foundation& top of the MSE wall and end of reinforced soil) to the drainage collection areas specified in the grading plan 101.

Please provide connection details for three lines drain for reinforced soil located behind the wall.

RESP: See Response to Question No. 55a.

218. Specification 00 01 15 Drawing : 02-00502-00,91-00560-00, 91-00609-00 Drawing S-001. Referring to the drawings prepared by LENCOM, It is mentioned that all steel work to be hot dip galvanized as per AS2312.2. However, referring to the drawing S-001, there is no hot dip galvanized requirement.