This solicitation is for the construction of infrastructure and utilities to support a Tactical Mobile Over-the-Horizon Radar system. The work includes electrical utilities, reinforced concrete pads and foundations, equipment tie downs, water and wastewater facilities, access roads, parking areas, security fencing, and site work. The facilities will be designed as semi-permanent structures in accordance with DoD criteria for non-permanent military facilities. The total value of the contract is estimated between $100 million and $250 million. The contract will have a period of performance of 1,106 calendar days and will be awarded on an unrestricted basis to qualified firms. The soliciting agency is the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RFP N62742-22-R-1322, PAF 198127 TACMOR UTILITIES AND INFRASTRUCTURE SUPPORT
Amendment No. 0005 is continued on page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N62742-22-R-1322
X 9B. DATED (SEE ITEM 11)
05 JAN 2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21 APR 2022
CODE
NAVFAC PACIFIC
CONSTRUCTION CONTRACTS BR (CON33)
4256 RADFORD DR., BLDG 62
HONOLULU, HI 96818-3296
N62742 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
FACILITY CODECODE
EMAIL:TEL:
N62742-22-R-1322 Amendment No. 0005
SF 30 BLOCK 14 CONTINUATION PAGE
This amendment is issued to revise the following:
1. Amendment 0004 is revised as follows. Revisions are shown in bolded red font.
“10. Section 03 30 00 CAST-IN-PLACE CONCRETE is revised as follows:
a. Paragraph 1.1 REFERENCES, ASTM International (ASTM), add the following after ASTM C78/C78M (2018) Standard Test Method for Flexural Strength of Concrete (using Simple Beam with Third –Point Loading):
ASTM C685/C685M- (2017) Standard Specification for Concrete Made by Volumetric Batching and Continuous Mixing
b. Paragraph 1.3 SUBMITTALS, add the following as noted:
SD-03 Product Data, add: Batching and Mixing Equipment
SD-06 Test Reports, add: Concrete Mix Proportions; G
c. Paragraph 3.6 BATCHING, MEASURING, MIXING, AND TRANSPORTING CONCRETE is revised to add the following paragraph as the second paragraph:
The option of using an on-site batching and mixing facility conforming to the requirements of either ASTM C94/C94M or ASTM C685/C685M is available. The facility must provide sufficient batching and mixing equipment capacity to prevent cold joints. Submit the method of measuring materials, batching operation, and mixer for review, and manufacturer's data for batching and mixing equipment demonstrating compliance with the applicable specifications.
12. Section 31 23 00.00 20, Paragraph 3.6.2 is revised to add the following after the first sentence:
Base bids on the assumption that the crushed/manufactured on-site soil is suitable to meet fill specifications.”
2. Section 01 30 00, ADMINISTATIVE REQUIREMENTS, is revised as follows:
a. Paragraph1.4.2.1 Workforce Housing Facilities for “Temporary Resident Workers” is revised to add the following paragraph b.:
b. Information on man-camps that may be available for rent on Angaur is attached at the end of this section.
b. Add paragraph 1.14 Registered Professional Engineers and Registered Architects as follows:
1.14 Registered Professional Engineers and Registered Architects
All references to the terms ‘professional engineer’ or ‘registered architect’ throughout this Specification refer to professional engineers and registered architects licensed in the United States, unless otherwise specified.
3. Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS is revised to delete the following from paragraph 1.5.2:
Base bids on the assumption that the Soil Disposal Site SD1 is sufficient to accommodate the excavated basalt and excess soil. Base bids on no fees or costs for the terms of use of SD1. Any fees of costs associated with the terms of use of the SD sites, SD1 or SD2, incurred will be handled as a changed condition. Submit the negotiated terms of use and any costs associated with complying with the terms of use to the Contracting Officer prior to commencing work.
4. Section 03 30 00 CAST-IN-PLACE CONCRETE is deleted in its entirety and replaced with the attached Section 03 30 00 CAST-IN-PLACE CONCRETE, AMENDMENT No. 0005, dated April 19, 2022.
5. Section 31 05 22 GEOTEXTILES USED AS FILTERS, paragraph 2.2.2 Site Verification and Testing is deleted in its entirety and not replaced.
6. Section 31 23 00.00.20 EXCAVATION AND FILL, paragraph 3.6.1 Common Fill Placement at Babeldaob Site is revised to delete paragraph 3.6.1 in its entirety and to replace it with the following:
The on-site excavated materials from Babeldaob site, conforming to satisfactory material, may also be used for fill below the top 0.6 meter of finished grade in non-load bearing areas, provided the contractor can achieve 85 percent of maximum dry density of the compacted soil. Place in lifts of 254 mm in loose thickness. Aerating on-site cohesive clayey and silty excavated material from Babeldaob excessively moistened by rain to satisfactory moisture content may not be practical due to inherent high moisture content. Mixing with drier soils may not be practical as cohesive clayey and silt soils are hard to break up sufficiently for mixing. On-site excavated materials form Babeldaob site must not be placed below antenna pad, antenna foundations, concrete slab foundations, spread footings, MSE Wall, concrete pavements, asphalt pavements, and tank foundations.
The Contractor shall base their bids on importing common fill that meets this specifications for placement at the Tx Babeldaob Site .
7. Section 32 05 33 LANDSCAPE ESTABLISHMENT, Paragraph 3.2, Groundcover Establishment Period, is deleted in its entirety and replaced with the following:
Groundcover establishment period will commence on the date that inspection by the Contracting Officer shows that the new turf furnished under this contract has been satisfactorily installed to a 95 percent stand of coverage. The establishment period must continue for a period of 60 calendar days.
8. Section 32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS, paragraph 2.2 Aggregates is deleted in its entirety and replaced with the following:
Provide aggregates consisting of crushed stone, crushed gravel, crushed slag, screenings, natural sand and mineral filler, as required. Submit sufficient materials to produce 90 kg of blended mixture for mix design verification. The portion of material retained on the 4.75 mm sieve is coarse aggregate. The portion of material passing the 4.75 mm sieve and retained on the 0.075 mm sieve is fine aggregate. The portion passing the 0.075 mm sieve is defined as mineral filler. Submit all aggregate test results and samples to the Contracting Officer at least 14 days prior to start of construction.
The Contractor shall base their bid on locally available imported aggregate that meets the specifications for HMA For Roads.
9. Section 32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE FACILITIES is revised as follows:
a. Paragraph 1.6.5 Field-Constructed Mockup is deleted in its entirety and replaced with the following:
Install a minimum 37 square meters to demonstrate typical joints, surface finish, texture, color, thickness, and standard of workmanship. Test panels must be placed using the mixture proportions, materials, and equipment as proposed for the project. Test mock up panels in accordance with requirements in FIELD
QUALITY CONTROL.
Test panel required at Tx and Rx sites.
When a test panel does not meet one or more of the requirements, the test panel must be rejected, removed, and replaced at the Contractor's expense. If the test panels are acceptable, they may be incorporated into the project with the approval of the Contracting Officer.
b. Paragraph 3.4.4 Fixed Form Paving is deleted in its entirety and replaced with the following:
Forms may be steel or wood. Forms may be built up with metal or wood, added only to the base, to provide an increase in depth of not more than 25 percent. The base width of the form must be not less than eight-tenths of the vertical height of the form, except that forms 200 mm or less in vertical height must have a base width not less than the vertical height of the form. Wood forms for curves and fillets must be adequate in strength and rigidly braced. Forms must be set on firm material cut true to grade so that each form section when placed will be firmly in contact with the underlying layer for its entire base. Forms must not be set on blocks or on built-up spots of underlying material. Forms must remain in place at least 12 hours after the concrete has been placed. Forms must be removed without injuring the concrete.
10. Section 32 31 26 WIRE FENCES, GATES, AND BACKING BERMS, paragraph 2.2 is revised to delete the first paragraph “Provide fence post, post caps,….with the following characteristics:” and to replace it with the following:
Provide fence post, post caps, rail, braces, gates, non-metal bollard (Detail B1 on CS501), and vertical slat of wood and plastic composite or reclaimed wood and plastic composite with integral coloring; free from toxic chemicals and preservatives with the following characteristics:
11. Section 32 92 19 SEEDING, paragraph 1.5.2.2 Topsoil is revised to delete paragraph 1.5.2.2 in its entirety and to replace with the following:
Prior to stockpiling topsoil, treat growing vegetation with application of appropriate specified non-selective herbicide. Clear and grub existing vegetation three to four weeks prior to stockpiling topsoil.
12. Section 33 30 00 SANITARY SEWERAGE, paragraph 1.3 is deleted in its entirety and replaced with “Not Used.”
13. The following previously issued drawings identified by number and title have been revised by this amendment and noted in the table below:
Drawing No.
NAVFAC
No. Drawing Title Revision
CE503 17267900
TX & RX EROSION CONTROL
DETAILS - 3
Detail B-4, Diversion Swale Cross Section:
Delete Swale B 1829mm
B-701 17267842 TX BORING LOGS - 1
Log of Test Pit, Dry Density units: change g/cc to lb./cu. ft
B-702 17267843 TX BORING LOGS - 2
Log of Test Pit, Dry Density units: change g/cc to lb./cu. ft
B-703 17267844 TX BORING LOGS - 3
Log of Test Pit, Dry Density units: change g/cc to lb./cu. ft
B-704 17267845 TX BORING LOGS - 4
Log of Test Pit, Dry Density units: change g/cc to lb./cu. ft
CS152
CS153
CS155
17268024 17268025 17268027
RX SITE PLAN Add note 4, “Surplus soil, not including unsatisfactory materials, can be disposed of in the onsite borrow pits.”
CS156
CS158
17268028 17268030
14. All other terms and conditions remain unchanged.
End of Amendment
PROPOSED LOCATION
SITE PLAN
NOT DRAWN TO SCALE
CAMP, 11,694 SqM
LEGEND:
- - - - - 8' x 20" CONTAINER
6 UNITS
- - - - - 16' x 20" CONTAINER
22 UNITS
- - - - - EXISTING STRUCTURE
- - - - - THREE(3) UNITS 8'x20' CONTAINER
KITCHEN & DINING
AutoCAD SHX Text 041 S 01
AutoCAD SHX Text 041 S 02
AutoCAD SHX Text 041 S 03
AutoCAD SHX Text 041 S 04
AutoCAD SHX Text 041 S 05
AutoCAD SHX Text 022 S 04
AutoCAD SHX Text 040 S 05
AutoCAD SHX Text
LS1
AutoCAD SHX Text
LS2
AutoCAD SHX Text N49%%d46'38"W
AutoCAD SHX Text 268.38
AutoCAD SHX Text
LS3
AutoCAD SHX Text N44%%d20'02"E
AutoCAD SHX Text 95.49
AutoCAD SHX Text
LS4
AutoCAD SHX Text N0%%d39'06"W
AutoCAD SHX Text 22.86
AutoCAD SHX Text M184
AutoCAD SHX Text N40%%d32'53"E
AutoCAD SHX Text 79.60
AutoCAD SHX Text M106
AutoCAD SHX Text N29%%d05'26"E
AutoCAD SHX Text 5.90
AutoCAD SHX Text
SL182
AutoCAD SHX Text S64%%d14'01"E
AutoCAD SHX Text 18.27
AutoCAD SHX Text
SL180
AutoCAD SHX Text S43%%d21'21"E
AutoCAD SHX Text 34.97
AutoCAD SHX Text
SL178
AutoCAD SHX Text S28%%d03'14"E
AutoCAD SHX Text 32.39
AutoCAD SHX Text
SL134
AutoCAD SHX Text N55%%d51'06"E
AutoCAD SHX Text 42.05
AutoCAD SHX Text
SL135
AutoCAD SHX Text S85%%d02'20"E
AutoCAD SHX Text 35.38
AutoCAD SHX Text
SL136
AutoCAD SHX Text S0%%d13'34"W
AutoCAD SHX Text 44.36
AutoCAD SHX Text
SL137
AutoCAD SHX Text S60%%d01'57"E
AutoCAD SHX Text 34.87
AutoCAD SHX Text
SL138
AutoCAD SHX Text S0%%d22'24"W
AutoCAD SHX Text 27.83
AutoCAD SHX Text
SL139
AutoCAD SHX Text S69%%d44'11"E
AutoCAD SHX Text 26.37
AutoCAD SHX Text
SL141
AutoCAD SHX Text S25%%d11'33"E
AutoCAD SHX Text 41.95
AutoCAD SHX Text
LS5
AutoCAD SHX Text S3%%d39'14"E
AutoCAD SHX Text 16.15
AutoCAD SHX Text S40%%d20'08"W
AutoCAD SHX Text 178.26
AutoCAD SHX Text E 16291.57
AutoCAD SHX Text N 101631.29
AutoCAD SHX Text
LAUNDRY
AutoCAD SHX Text T & B
AutoCAD SHX Text
KITCHEN/DINING
AutoCAD SHX Text T & B
AutoCAD SHX Text T & B
QUOTATION
No.SLA0225-2022
To: BRENT CIBOCH, RA, LEED AP
AFIMSC Det 2/CEB, Project Manager
Description Unit Cost/mo Amount Total
Rental of 16ft x 20ft
Container House/contract 18 unit 3,500.00$ 8 mo $504,000.00 504,000.00
INCLUDES THE FOLLOWING AMENITIES:
1. AC UNIT INCLUDED FOR ALL CLU's.
2. BUNK BEDS/MATTRESS (3 SETS PER UNIT)
3. SHOWER AND FLUSHABLE TOILET FACILITIES WITH HOLDING TANK (SEE ATTACHED)
4. COVERED MESSHALL/CONFERENCE AREA (SEE ATTACHED)
5. LAUNDRY FACILITY (SEE ATTACHED)
Note: Includes 24-hr maintenance
$504,000.00
SUBMITTED BY:
BILLY TAKAMINE
Gen. Manager
DESCRIPTION
WILLIAMS CONSTRUCTION COMPANY
Design,Engineering & Build
Trust, Integrity & Commitment
P.O. Box 6110 Koror, Palau 96940 Tel No. 488-1189 / 775-1188 Email: info@wccbelau.com
February 25, 2022
SLEEPING/LIVING ACCOMODATIONS REQUIREMENTS
Item QTY # of mo
TOTAL COST PROPOSAL
QUOTATION
No.LSR0225-2022
To: BRENT CIBOCH, RA, LEED AP
AFIMSC Det 2/CEB, Project Manager
Description Unit Cost/mo Amount Total
1 Rental of Generator 100KVA 2 unit 22,500.00$ 8 mo $360,000.00 360,000.00
*CUMMINS 22OV 3PHASE
GFS-100KVA MODEL
***Includes 24hr Maintenance
***NOT INCLUDING FUEL
2 Wifi Service (hotspot) 1 LS 600.00$ 8 mo $4,800.00 4,800.00
3 Supply and Delivery of Potable Water 1 LS 18,000.00$ 8 mo $144,000.00 144,000.00
4 Removal and Disposal of Gray Water 1 LS 30,000.00$ 8 mo $240,000.00 240,000.00
5 Trash Collection and Disposal 1 LS 30,000.00$ 8 mo $240,000.00 240,000.00
TOTAL COST PROPOSAL $988,800.00
SUBMITTED BY:
BILLY TAKAMINE
Gen. Manager
WILLIAMS CONSTRUCTION COMPANY
Design,Engineering & Build
Trust, Integrity & Commitment
P.O. Box 6110 Koror, Palau 96940 Tel No. 488-1189 / 775-1188 Email: info@wccbelau.com
February 25, 2022
DESCRIPTION
LIFE SUPPORT REQUIREMENTS
Item QTY # of mo
Note: This price is enough to accommodate 50 personnel only.
PAF 198127 TACMOR UTILITIES AND INFRASTRUCTURE SUPPORT 1596606
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
02/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO
ACI 301 (2016) Specifications for Structural Concrete
ACI 302.1R (2015) Guide for Concrete Floor and Slab Construction
ACI 304.2R (2017) Guide to Placing Concrete by Pumping Methods
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305.1 (2014) Specification for Hot Weather Concreting
ACI 305R (2010) Guide to Hot Weather Concreting
ACI 308.1 (2011) Specification for Curing Concrete
ACI 318M (2014; ERTA 2015) Building Code Requirements for Structural Concrete & Commentary
ACI SP-15 (2011) Field Reference Manual: Standard Specifications for Structural Concrete ACI 301-05 with Selected ACI References
ACI SP-2 (2007; Abstract: 10th Edition) ACI Manual of Concrete Inspection
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
SECTION 03 30 00 Page 1 AMENDMENT No. 0005
19 April 2022
ASTM INTERNATIONAL (ASTM)
ASTM A1060/A1060M (2016b) Standard Specification for Zinc-Coated (Galvanized) Steel Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM A1064/A1064M (2017) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A706/A706M (2016) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement
ASTM A780/A780M (2009; R 2015) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A970/A970M (2018) Standard Specification for Headed Steel Bars for Concrete Reinforcement
ASTM C1017/C1017M (2013; E 2015) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete
ASTM C1077 (2017) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation
ASTM C1107/C1107M (2017) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
ASTM C1218/C1218M (2017) Standard Test Method for Water-Soluble Chloride in Mortar and Concrete
ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C1293 (2008; R 2015) Standard Test Method for Determination of Length Change of Concrete Due to Alkali-Silica Reaction
ASTM C143/C143M (2015) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2018) Standard Specification for Portland Cement
ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations
SECTION 03 30 00 Page 2 of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)
ASTM C1602/C1602M (2018) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
ASTM C172/C172M (2017) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2016) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C31/C31M (2019) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C311/C311M (2018) Standard Test Methods for Sampling and Testing Fly Ash or Natural Pozzolans for Use in Portland-Cement Concrete
ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates
ASTM C330/C330M (2017a) Standard Specification for Lightweight Aggregates for Structural Concrete
ASTM C39/C39M (2018) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C42/C42M (2018a) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C494/C494M (2017) Standard Specification for Chemical Admixtures for Concrete
ASTM C595/C595M (2018) Standard Specification for Blended Hydraulic Cements
ASTM C618 (2019) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C685/C685M (2017) Standard Specification for Concrete Made by Volumetric Batching and Continuous Mixing
ASTM C78/C78M (2018) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam
SECTION 03 30 00 Page 3 with Third-Point Loading)
ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants
ASTM C94/C94M (2018) Standard Specification for Ready-Mixed Concrete
ASTM C989/C989M (2018a) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM D2628 (1991; R 2016) Standard Specification for Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements
ASTM D2835 (1989; R 2017) Standard Specification for Lubricant for Installation of Preformed Compression Seals in Concrete Pavements
ASTM D3042 (2017) Standard Test Method for Insoluble Residue in Carbonate Aggregates
ASTM D4832 (2016; E 2018) Standard Test Method for Preparation and Testing of Controlled Low Strength Material (CLSM) Test Cylinders
ASTM D5759 (2012) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses
ASTM D6690 (2015) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements
ASTM E329 (2018) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
CRSI 10MSP (2009; 28th Ed; Errata) Manual of Standard Practice
CRSI RB4.1 (2016) Supports for Reinforcement Used in Concrete
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST PS 1 (2009) DOC Voluntary Product Standard PS 1-07, Structural Plywood
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 572 (1974) Corps of Engineers Specifications for Polyvinylchloride Waterstops
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS SS-S-200 (Rev E; Am 1; Notice 1) Sealant, Joint, SECTION 03 30 00 Page 4
Two-Component, Jet-Blast-Resistant, Cold-Applied, for Portland Cement Concrete Pavement
1.2 DEFINITIONS
a. "Cementitious material" as used herein must include all portland cement, pozzolan, fly ash, and slag cement.
b. "Exposed to public view" means situated so that it can be seen from eye level from a public location after completion of the building. A public location is accessible to persons not responsible for operation or maintenance of the building.
c. "Chemical admixtures" are materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.
d. "Supplementary cementing materials" (SCM) include coal fly ash,slag cement, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in improvement to sustainability and durability and reduced cost.
e. "Design strength" (f'c) is the specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.
f. "Mass Concrete" is any concrete system that approaches a maximum temperature of 70 degrees C within the first 72 hours of placement.
In addition, it includes all concrete elements with a section thickness of 1 meter or more regardless of temperature.
g. "Mixture proportioning" is the process of designing concrete mixture proportions to enable it to meet the strength, service life and constructability requirements of the project while minimizing the initial and life-cycle cost.
h. "Mixture proportions" are the masses or volumes of individual ingredients used to make a unit measure (cubic meter or cubic yard) of concrete.
i. "Pozzolan" is a siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.
j. "Workability (or consistence)" is the ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality. Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SECTION 03 30 00 Page 5
SD-01 Preconstruction Submittals
Quality Control Plan; G
Quality Control Personnel Certifications; G
Laboratory Accreditation; G
Form Removal Schedule; G
Concrete Curing Plan; G
Probing and Grouting Plan; G
SD-02 Shop Drawings Formwork
Reinforcing Steel; G
SD-03 Product Data
Joint Sealants
Joint Filler
Formwork Materials
Cementitious Materials
Concrete Curing Materials
Reinforcement
Admixtures
Mechanical Reinforcing Bar Connectors
Waterstops
Biodegradable Form Release Agent
Conveying and Placing Concrete
Nonshrink Grout
Batching and Mixing Equipment
SD-04 Samples
Slab Finish Sample Surface Finish Samples
SD-05 Design Data
Concrete Mix Design; G
SD-06 Test Reports
Concrete Mix Design; G
SECTION 03 30 00 Page 6
Fly Ash
Pozzolan
Probing and Grouting Log; G
Slag Cement
Aggregates
Compressive Strength Tests; G
Chloride Ion Concentration
Air Content
Slump Tests
Water
SD-07 Certificates
Reinforcing Bars
Welder Qualifications Safety Data Sheets
Field Testing Technician and Testing Agency
SD-08 Manufacturer's Instructions
Joint Sealants
1.4 MODIFICATION OF REFERENCES
Accomplish work in accordance with ACI publications except as modified herein. Consider the advisory or recommended provisions to be mandatory.
Interpret reference to the "Building Official," the "Structural Engineer," and the "Architect/Engineer" to mean the Contracting Officer.
1.5 DELIVERY, STORAGE, AND HANDLING
Follow ACI 301 and ACI 304R requirements and recommendations. Do not deliver concrete until forms, reinforcement, embedded items, and chamfer strips are in place and ready for concrete placement. Do not store concrete curing compounds or sealers with materials that have a high capacity to adsorb volatile organic compound (VOC) emissions. Do not store concrete curing compounds or sealers in occupied spaces.
1.5.1 Reinforcement
Store reinforcement of different sizes and shapes in separate piles or racks raised above the ground to avoid excessive rusting. Protect from contaminants such as grease, oil, and dirt. Ensure bar sizes can be accurately identified after bundles are broken and tags removed.
SECTION 03 30 00 Page 7
1.6 QUALITY ASSURANCE
1.6.1 Design Data
1.6.1.1 Concrete Mix Design
Sixty days minimum prior to concrete placement, submit a mix design for each strength and type of concrete. Submit a complete list of materials including type; brand; source and amount of cement, supplementary cementitious materials, and admixtures; and applicable reference specifications. Submit mill test and all other test for cement, supplementary cementitious materials, aggregates, and admixtures. Provide documentation of maximum nominal aggregate size, gradation analysis, percentage retained and passing sieve, and a graph of percentage retained verses sieve size. Provide mix proportion data using at least three different water-cementitious material ratios for each type of mixture, which produce a range of strength encompassing those required for each type of concrete required. If source material changes, resubmit mix proportion data using revised source material. Provide only materials that have been proven by trial mix studies to meet the requirements of this specification, unless otherwise approved in writing by the Contracting Officer. Indicate clearly in the submittal where each mix design is used when more than one mix design is submitted. Resubmit data on concrete components if the qualities or source of components changes.
For previously approved concrete mix designs used within the past twelve months, the previous mix design may be re-submitted without further trial batch testing if accompanied by material test data conducted within the last six months. Obtain mix design approval from the contracting officer prior to concrete placement.
1.6.1.2 Probing and Grouting Plan
Submit a probing and grouting plan at least 20 working days prior to the start of probing. The plan shall describe the equipment and procedures for probing and grouting to check for and grout subsurface cavities and voids.
Furnish a complete list of materials, including type, brand, source, admixture, applicable reference specifications, and test reports showing that the concrete pressue grout mix has been successfully tested to produce grout consisting of a sand, cement, and water mixture and is suitable for the project conditions. The grout mix design will be provided by the Contractor's supplier. Submit grout mix design and the mix design's historical supporting unconfined compressive strength records with the Probing and Grouting Plan submittal. Include a plan showing the locations and numbering system to be used for probes.
1.6.1.3 Probing and Grouting Log
Submit complete probing and grouting logs and records and a plan showing probe locations and probe numbers. Submit probing and grouting logs and plans within 3 days of probing and grouting.
1.6.1.4 Controlled Low Strength Material (CLSM)
Submit a mix design for CLSM at least 15 days prior to the start of construction. Furnish a complete list of materials, including type, brand, source, admixture, applicable reference specifications, and test reports showing that the mix has been successfully tested to produce CLSM meeting the properties specified and is suitable for the project conditions.
SECTION 03 30 00 Page 8
1.6.2 Shop Drawings
1.6.2.1 Formwork
Drawings showing details of formwork including, but not limited to;
joints, supports, studding and shoring, and sequence of form and shoring removal. Indicate placement schedule, construction, location and method of forming control joints. Include locations of inserts, conduit, sleeves and other embedded items. Reproductions of contract drawings are unacceptable. Submit form removal schedule indicating element and minimum length of time for form removal.
Design, fabricate, erect, support, brace, and maintain formwork so that it is able to support, without failure, all vertical and lateral loads that may reasonably be anticipated to be applied to the formwork.
1.6.2.2 Reinforcing Steel
Indicate bending diagrams, assembly diagrams, splicing and laps of bars, shapes, dimensions, and details of bar reinforcing, accessories, and concrete cover. Do not scale dimensions from structural drawings to determine lengths of reinforcing bars. Reproductions of contract drawings are unacceptable.
1.6.3 Control Submittals
1.6.3.1 Concrete Curing Plan
Submit proposed materials, methods and duration for curing concrete elements in accordance with ACI 308.1 .
1.6.3.2 Conveying and Placing Concrete
Convey and place concrete in accordance with ACI 301 , Section 5. Submit proposed materials and methods for pumping concrete. Submittal must include mix designs, pumping equipment including type of pump and size and material for pipe, and maximum length and height concrete is to be pumped.
1.6.3.3 Safety Data Sheets
Submit Safety Data Sheets (SDS) for all materials that are regulated for hazardous health effects. SDS must be readily accessible during each work shift to employees when they are at the construction site.
1.6.4 Test Reports
1.6.4.1 Fly Ash and Pozzolan
Submit test results in accordance with ASTM C618 for fly ash and pozzolan. Submit test results performed within 6 months of submittal date.
1.6.4.2 Slag Cement
Submit test results in accordance with ASTM C989/C989M for slag cement.
Submit test results performed within 6 months of submittal date.
SECTION 03 30 00 Page 9
1.6.4.3 Aggregates
Submit test results in accordance with ASTM C33/C33M, or ASTM C330/C330M for lightweight aggregate, and ASTM C1293 or ASTM C1567 as required in the paragraph titled ALKALI-AGGREGATE REACTION.
1.6.5 Field Samples
1.6.5.1 Slab Finish Sample
Install minimum of 3000 mm by 3000 mm slab. Slab finish sample may be part of the final project if accepted by the Contracting Officer. Finish as required by specification.
1.6.5.2 Surface Finish Samples
Provide a minimum of three sample concrete panels for each finish for each mix design, one m by one m, 75 mm thick. Use the approved concrete mix design(s). Provide sample panels on-site at locations directed. Once approved, each set of panels must be representative of each of the finishes specified and of the workmanship and finish(es) required. Do not remove or destroy samples until directed by the Contracting Officer.
1.6.6 Quality Control Plan
Develop and submit for approval a concrete quality control program in accordance with the guidelines of ACI 121R and as specified herein. The plan must include approved laboratories. Provide direct oversight for the concrete qualification program inclusive of associated sampling and testing. All quality control reports must be provided to the Contracting Officer, Quality Manager and Concrete Supplier. Maintain a copy of ACI SP-15 and CRSI 10MSP at project site.
1.6.7 Quality Control Personnel Certifications
The Contractor must submit for approval the responsibilities of the various quality control personnel, including the names and qualifications of the individuals in those positions and defining the quality control hierarchy and the responsibility of the various positions. Quality control personnel must be employed by the Contractor.
Submit American Concrete Institute certification for the following:
a. CQC personnel responsible for inspection of concrete operations.
b. Lead Foreman or Journeyman of the Concrete Placing, Finishing, and Curing Crews.
c. Field Testing Technicians: ACI Concrete Field Testing Technician, Grade I.
1.6.7.1 Quality Manager Qualifications
The quality manager must hold a current license as a Professional Engineer in a U.S. state or territory. The quality manager must have experience on at least five similar projects. Evidence of extraordinary proven experience may be considered by the Contracting Officer as sufficient to act as the Quality Manager
SECTION 03 30 00 Page 10
1.6.7.2 Field Testing Technician and Testing Agency
Submit data on qualifications of proposed testing agency and technicians for approval by the Contracting Officer prior to performing testing on concrete.
a. Work on concrete under this contract must be performed by an ACI Concrete Field Testing Technician Grade 1 qualified in accordance with ACI SP-2 or equivalent. Equivalent certification programs must include requirements for written and performance examinations as stipulated in ACI SP-2 .
b. Testing agencies that perform testing services on reinforcing steel must meet the requirements of ASTM E329.
c. Testing agencies that perform testing services on concrete materials must meet the requirements of ASTM C1077. Testing agencies that perform testing services that do not meet ASTM C1077 requirements must use an approved testing system. Submit alternate testing system to Contracting Officer for approval.
1.6.8 Laboratory Qualifications for Concrete Qualification Testing
The concrete testing laboratory must have the necessary equipment and experience to accomplish required testing. The laboratory must meet the requirements of ASTM C1077. A testing laboratory that does not meet the requirements of ASTM C1077 must submit qualifications to the Contracting Officer for approval.
1.6.9 Laboratory Accreditation
Laboratory and testing facilities must be provided by and at the expense of the Contractor. The laboratories performing the tests must be accredited in accordance with ASTM C1077 or approved equal, including ASTM C78/C78M and ASTM C1260. The accreditation must be current and must include the required test methods, as specified. Furthermore, the testing must comply with the following requirements:
a. Aggregate Testing and Mix Proportioning: Aggregate testing and mixture proportioning studies must be performed by an accredited laboratory and under the direction of a registered professional engineer in a U.S. state or territory competent in concrete materials.
b. Acceptance Testing: Furnish all materials, labor, and facilities required for molding, curing, testing, and protecting test specimens at the site and in the laboratory. Furnish and maintain boxes or other facilities suitable for storing and curing the specimens at the site while in the mold within the temperature range stipulated by
ASTM C31/C31M.
c. Contractor Quality Control: All sampling and testing must be performed by an approved, independent, accredited laboratory.
1.7 ENVIRONMENTAL REQUIREMENTS
1.7.1 Submittals for Environmental Performance
a. Provide data indication the percentage of post-industrial pozzolan (fly ash, slag cement) cement substitution as a percentage of the full
SECTION 03 30 00 Page 11 product composite by weight.
b. Provide data indicating the percentage of post-industrial and post-consumer recycled content aggregate.
c. Provide product data indicating the percentage of post-consumer recycled steel content in each type of steel reinforcement as a percentage of the full product composite by weight.
d. Provide product data stating the location where all products were manufactured
e. For projects using reusable formwork, provide data showing how formwork is reused.
f. Provide SDS product information data showing that concrete adhesives meet any environmental performance goals including low emitting, low volatile organic compound products.
1.8 QUALIFICATIONS FOR WELDING WORK
Welding procedures must be in accordance with AWS D1.4/D1.4M .
Verify that Welder qualifications are in accordance with AWS D1.4/D1.4M and Section 05 50 13 Miscellaneous Metal Fabrications for welding of reinforcement or under an equivalent qualification test approved in advance. Welders are permitted to do only the type of welding for which each is specifically qualified.
PART 2 PRODUCTS
2.1 FORMWORK MATERIALS
a. Form-facing material in contact with concrete must be wood, structural plywood, steel, or other material that can absorb air and some of the high water-cementitious materials ratio surface paste that may be trapped in pockets between the form and the concrete. Submit product information on proposed form-facing materials if different from that specified herein.
b. Design formwork, shores, reshores, and backshores to support loads transmitted to them and to comply with applicable building code requirements.
d. Design formwork to withstand pressure resulting from placement and vibration of concrete and to maintain specified tolerances.
e. Design formwork to accommodate waterstop materials in joints at locations indicated in Contract Documents.
f. Provide temporary openings in formwork if needed to facilitate cleaning and inspection.
g. Design formwork joints to inhibit leakage of mortar.
h. Limit deflection of facing materials for concrete surfaces exposed to view to 1/240 of center-to-center spacing of facing supports.
i. Submit product information on proposed form-facing materials if
SECTION 03 30 00 Page 12 different from that specified herein.
j. Submit shop drawings for formwork, shoring, reshoring, and backshoring. Shop drawings must be signed and sealed by a licensed design engineer.
k. Submit manufacturer's product data on form liner proposed for use with each formed surface.
2.1.1 Wood Forms
Provide lumber that is square edged or tongue-and-groove boards, free of raised grain, knotholes, or other surface defects. Provide plywood that complies with NIST PS 1 , B-B concrete form panels or better, hardboard for smooth form lining. Submit data verifying that composite wood products contain no urea formaldehyde resins.
2.1.1.1 Concrete Form Plywood (Standard Rough)
Provide plywood that conforms to NIST PS 1 , B-B, concrete form, not less than 16 mm thick.
2.1.1.2 Overlaid Concrete Form Plywood (Standard Smooth)
Provide plywood that conforms to NIST PS 1 , B-B, high density form overlay, not less than 16 mm thick.
2.1.2 Steel Forms
Provide steel form surfaces that do not contain irregularities, dents, or sags.
2.2 FORMWORK ACCESSORIES
a. Use commercially manufactured formwork accessories, including ties and hangers.
b. Form ties and accessories must not reduce the effective cover of the reinforcement.
2.2.1 Form Ties
a. Use form ties with ends or end fasteners that can be removed without damage to concrete.
b. Where indicated in Contract Documents, use form ties with integral water barrier plates or other acceptable positive water barriers in walls.
c. The breakback distance for ferrous ties must be at least 50 mm for Surface Finish-2.0 or Surface Finish-3.0, as defined in ACI 301 .
d. Submit manufacturer's data sheet on form ties.
2.2.2 Waterstops
Submit manufacturer's data sheet on waterstop materials and splices.
SECTION 03 30 00 Page 13
2.2.2.1 PVC Waterstop
Polyvinylchloride waterstops must conform to COE CRD-C 572 .
2.2.3 Biodegradable Form Release Agent
a. Provide form release agent that is a colorless biodegradable.
b. Provide product that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.
c. Provide form release agent that reduces formwork moisture absorption, and does not contain diesel fuel, petroleum-based lubricating oils, waxes, or kerosene. Submit documentation indicating type of biobased material in product and biobased content. Indicate relative dollar value of biobased content products to total dollar value of products included in project.
d. Submit manufacturer's product data on formwork release agent for use on each form-facing material.
2.2.4 Chamfer Materials
Use lumber materials with dimensions of 19 x 19 mm unless otherwise noted.
2.2.5 Construction and movement joints
a. Submit details and locations of construction joints in accordance with the requirements herein.
b. Locate construction joints within middle one-third of spans of slabs and beams.
c. Make construction joints perpendicular to main reinforcement.
d. Provide movement joints where indicated in Contract Documents or in accepted alternate locations.
e. Submit location and detail of movement joints if different from those indicated in Contract Documents.
f. Submit manufacturer's data sheet on expansion joint materials.
g. Provide keyways where indicated in Contract Documents. Longitudinal keyways indicated in Contract Documents must be at least 37.5 mm deep, measured perpendicular to the plane of the joint.
2.2.6 Other Embedded items
Use sleeves, inserts, anchors, and other embedded items of material and design indicated in Contract Documents.
SECTION 03 30 00 Page 14
2.3 CONCRETE MATERIALS
2.3.1 Cementitious Materials
2.3.1.1 Portland Cement
a. Unless otherwise specified, provide cement that conforms to ASTM C150/C150M Type II and meets low alkali content requirements.
b. Use one brand and type of cement for formed concrete having exposed-to-view finished surfaces.
c. Supplier must certify that no hazardous waste is used in the fuel mix or raw materials.
d. Submit information along with evidence demonstrating compliance with referenced standards. Submittals must include types of cementitious materials, manufacturing locations, shipping locations, and certificates showing compliance.
e. Cementitious materials must be stored and kept dry and free from contaminants.
2.3.1.2 Blended Cements
a. Blended cements must conform to ASTM C595/C595M, Type IP or IS, including the optional requirement for mortar expansion and sulfate soundness and consisting of a mixture of ASTM C150/C150M Type II cement and supplementary cementing material.
b. Slag cement added to the Type IS blend must meet ASTM C989/C989M.
c. The pozzolan added to the Type IP blend must be ASTM C618 Class F fly ash and must be interground with the cement clinker. The manufacturer must state in writing that the amount of pozzolan in the finished cement will not vary more than plus or minus 5 percent by mass of the finished cement from lot-to-lot or within a lot. The percentage and type of pozzolan used in the blend must not change from that submitted for the aggregate evaluation and mixture proportioning.
2.3.1.3 Fly Ash
a. ASTM C618, Class F, except that the maximum allowable loss on ignition must not exceed 3 percent.
b. Fly ash content must be a minimum of 15 percent by weight of cementitious material, provided the fly ash does not reduce the amount of cement in the concrete mix below the minimum requirements of local building codes. Where the use of fly ash cannot meet the minimum level, provide the maximum amount of fly ash permittable that meets the code requirements for cement content. Report the chemical analysis of the fly ash in accordance with ASTM C311/C311M. Evaluate and classify fly ash in accordance with ASTM D5759.
2.3.1.4 Slag cement
ASTM C989/C989M, Grade 120. Slag content must be a minimum of 25 percent by weight of cementitious material.
SECTION 03 30 00 Page 15
2.3.1.5 Other Supplementary Cementitious Materials
Natural pozzolan must be raw or calcined and conform to ASTM C618, Class N, including the optional requirements for uniformity and effectiveness in controlling ASR and must have an ignition loss not exceeding 3 percent.
Class N pozzolan for use in mitigating ASR must have a Calcium Oxide (CaO) content of less than 13 percent and total equivalent alkali content less than 3 percent.
Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) must conform to ASTM C618, Class F or N, and the following additional requirements:
a. The strength activity index at 28 days of age must be at least 95 percent of the control specimens.
b. The average particle size must not exceed 6 microns.
c. The sum of SiO2 + Al2O3 + Fe2O3 must be greater than 77 percent.
2.3.2 Water
a. Water or ice must comply with the requirements of ASTM C1602/C1602M .
b. Minimize the amount of water in the mix. Improve workability by adjusting the grading of the aggregate and using admixture rather than by adding water.
c. Water must be potable; free from injurious amounts of oils, acids, alkalis, salts, organic materials, or other substances deleterious to concrete.
d. Protect mixing water and ice from contamination during storage and delivery.
e. Submit test report showing water complies with ASTM C1602/C1602M .
2.3.3 Aggregate
2.3.3.1 Normal-Weight Aggregate
a. Aggregates must conform to ASTM C33/C33M.
b. Aggregates used in concrete must be obtained from the same sources and have the same size range as aggregates used in concrete represented by submitted field test records or used in trial mixtures.
c. Provide sand that is at least 50 percent acid insoluble based on
ASTM D3042.
d. Store and handle aggregate in a manner that will avoid segregation and prevents contamination by other materials or other sizes of aggregates. Store aggregates in locations that will permit them to drain freely. Do not use aggregates that contain frozen lumps.
e. Submit types, pit or quarry locations, producers' names, aggregate supplier statement of compliance with ASTM C33/C33M, and ASTM C1293 expansion data not more than 18 months old.
f. Base bids on using local aggregate supplier.
SECTION 03 30 00 Page 16
2.3.4 Admixtures
a. Chemical admixtures must conform to ASTM C494/C494M.
b. Air-entraining admixtures must conform to ASTM C260/C260M.
c. Chemical admixtures for use in producing flowing concrete must conform to ASTM C1017/C1017M .
d. Do not use calcium chloride admixtures.
e. Use a corrosion-inhibiting admixture for concrete classified under exposure category C2. Where used, adjust the quantity of concrete mixing water for the mass of water in the admixture. Accelerating and set adjusted versions are acceptable. Concrete setting time and mixture workability must be evaluated.
f. Admixtures used in concrete must be the same as those used in the concrete represented by submitted field test records or used in trial mixtures.
g. Protect stored admixtures against contamination, evaporation, or damage.
h. To ensure uniform distribution of constituents, provide agitating equipment for admixtures used in the form of suspensions or unstable solutions. Protect liquid admixtures from freezing and from temperature changes that would adversely affect their characteristics.
i. Submit types, brand names, producers' names, manufacturer's technical data sheets, and certificates showing compliance with standards required herein.
2.4 MISCELLANEOUS MATERIALS
2.4.1 Concrete Curing Materials
Provide concrete curing material in accordance with ACI 301 Section 5 and ACI 308.1 Section 2.
2.4.1.2 Impervious Sheeting
ASTM C171; waterproof paper, clear or white polyethylene sheeting, or polyethylene-coated burlap.
2.4.1.2 Pervious Sheeting
AASHTO M 182 or carpet covering the free surface and kept continuously wet throughout the curing period.
2.4.1.3 Liquid Membrane-Forming Compound
Liquid membrane-forming compound must not be used.
2.4.2 Nonshrink Grout
Nonshrink grout in accordance with ASTM C1107/C1107M . Nonshrink grout must have a minimum compressive strength of 50 MPa. Nonshrink grout must
SECTION 03 30 00 Page 17 be non-metallic. Pea gravel must be added in accordance with the grout manufacturer's recommendations when used for thicker applications.
2.4.3 Joint Sealants
2.4.3.1 Horizontal Surfaces, 3 Percent Slope, Maximum
ASTM D6690 or ASTM C920, Type M,…