ITEM NO: 562-11-001

TITLE: Rudder, Steering Gear, and Skeg; repair

PARA. NO: 1.3.4, 1.3.5, 3.17

PAGE NO: 1, 5 of 7

ITEM NO: Solicitation

TITLE: Offer Submission Date

PARA. NO:

PAGE NO:

ITEM NO:

TITLE:

PARA. NO:

PAGE NO:

ITEM NO:

TITLE:

PARA. NO:

PAGE NO:

ITEM NO:

TITLE:

PARA. NO:

PAGE NO:

ITEM NO:

TITLE:

PARA. NO:

PAGE NO:

ITEM NO:

TITLE:

PARA. NO:

REQUEST FOR SPECIFICATION CLARIFICATION

28-Nov-18 SOLICITATION NO: N50054-19-R-0004

TITLE: USNS PREVAIL (TSV-1) Drydock Phased Maintenance Availability (DPMA) MARMC POC: Kelly Reusser

MARMC PHONE: (757) 400-0326

CONTRACTOR QUESTION : GOVERNMENT RESPONSE:

CONTRACTOR QUESTION 26: Paragraph 3.17 requires the contractor to furnish and install new RAM Cylinders listed in 1.3.4 and 1.3.5. Contractor has communicated with several potential vendors for supplying these cylinders, but none will provide pricing and delivery with so little information available. Does the Government have a source for these cylinders?

GOVERNMENT RESPONSE: The GOVT does not have a source at this time. If the Govt nor the contractor can find a source by the award an RCC will be written to refurbish vice replace.

CONTRACTOR QUESTION 27: Contractor is still experiencing delays with vendors and subcontractors providing necessary quotes, particularly through the recent Holiday span. Lacking all the necessary information not only affects the pricing proposal, but also various sections of the Pre-Award requirements. Please provide an extension of the proposal due date of five

(5) business days to allow contractor to finish procurring vendor and subcontractor information and to better prepare a competitive proposal.

GOVERNMENT RESPONSE:

The Proposal due date has been extended to Tuesday December 4, 2018 by 1:00pm

GOVERNMENT RESPONSE:CONTRACTOR QUESTION :

CONTRACTOR QUESTION : GOVERNMENT RESPONSE:

GOVERNMENT RESPONSE:

CONTRACTOR QUESTION : GOVERNMENT RESPONSE:

CONTRACTOR QUESTION :

PAGE NO:

CONTRACTOR QUESTION : GOVERNMENT RESPONSE: