CVN74_Turnover Memo Attachment 12

View the file

Other files

File Type Posted
Price_Submission_Worksheet_Amendment_1_Attachment_18.xls XLS spreadsheet
N4215817RN002_Questions_with_Responses_Pt2.docx DOCX document
Price_Submission_Worksheet_Attachment_18.xls XLS spreadsheet
N4215817RN002_Questions_with_Responses.docx DOCX document
N4215817RN0020001.docx DOCX document
CVN_74_QASP_and_MATRIX_Attachment_2.docx DOCX document
CVN74_Tech_Review_Transmittal_Attachment_13.xlsx XLSX spreadsheet
Attachment_15_WD_2015-4341_NC_Virginia.docx DOCX document
CVN74_Analysis_CLIN_Ceiling_Attachment_3.xlsx XLSX spreadsheet
CVN74_SID_MASTER_DRAWING_SCHEDULE_Attachment_6.xlsx XLSX spreadsheet
Past_Performance_Information_Form_Attachment_16.docx DOCX document
CVN74_Interferance_Log_Attachment_9.JPG JPG image
CVN_74_DD254_Attachment_1.pdf PDF
CVN74_TECH_ISSUES_Attachment_4.xls XLS spreadsheet
Addendum_DD254_Attachment_1a.docx DOCX document
N4215817RN002.docx DOCX document
Past_Performance_Report_Form_Attachment_17.docx DOCX document
CVN74_Shipcheck_Assistant_Attachment_8.JPG JPG image
CVN74_CVN_73_Design_Information_Memo_Attachment_10.pdf PDF
Attachment_14_WD_2015-5525_Kitsap_Bremerton.docx DOCX document
CVN74_DLAR_Attachment_11.pdf PDF
CVN74_In-Client_Roster_Attachment_5.xlsx XLSX spreadsheet
CVN74_Weekly_Hours_Expended_Attachment_7.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CVN74_Sample Turnover Memo_Attachment 12

Turnover Memo

To: Contractor

From: M. Anderson C271

CC: John Doe Date: 12/3/2013

Re: TURNOVER FOR SCD 12345

USS GEORGE H. W. BUSH (CVN 77) SCD 12345 FY15 PIA, CVN 77 Federation-

Install MCS and NCDS

MEMO:

a) CVN77-11872-01, MEMO (7/29/13)

b) CVN77-11872-02, MEMO (8/6/13)

c) CVN77-11872-03, MEMO (8/6/13)

d) CVN77-11872-04, MEMO (8/16/13)

e) CVN77-11872-05, MEMO (8/17/13)

f) CVN77-11872-06, MEMO (8/20/13)

g) CVN77-11872-07, MEMO (9/16/13)

h) CVN77-11872-08, MEMO (9/16/13)

i) CVN77-11872-09, MEMO (9/18/13)

j) CVN77-11872-10, MEMO (9/27/13)

k) CVN77-11872-11, MEMO (10/1/13)

l) CVN77-11872-12, MEMO (10/8/13)

m) CVN77-11872-13, MEMO (10/9/13)

n) CVN77-11872-14, MEMO (10/8/13)

o) CVN77-11872-15, MEMO (10/10/13)

p) SCD11872-271-016 , MEMO (10/9/13)

q) CVN77-11872-17, MEMO (10/11/13)

r) 271-SCD11872-18, MEMO (10/15/13)

NNSY CODE 271

s) 271-SCD11872-19, MEMO (10/17/13)

t) CVN77-11872-20, MEMO (10/22/13)

u) CVN77-11872-21, MEMO (10/24/13)

v) CVN77-11872-22, MEMO (10/24/13)

w) CVN77-11872-23, MEMO (10/24/13)

x) CVN77-11872-24, MEMO (10/25/13)

y) CVN77-11872-25, MEMO (10/31/13)

z) CVN77-11872-26, MEMO (10/31/13)

aa) CVN77-11872-27, MEMO (11/6/13)

bb) CVN77-11872-28, MEMO (11/6/13)

cc) CVN77-11872-29, MEMO (11/6/13)

NEW DRAWINGS REQ’D:

SEE ATTACHED SCOPE SHEET

NOTE: Drawings within the plan schedule that have (NSA) in the title is work to be done by NNSY personnel. The intent of these drawings is to split out the plant work from the AIT work.

Work concurrently with SCD 6613, 7567, 9780, 10216, 10810, 12622 & 12623.

Node Room No.1 (2-17-6-C)

See shipchecked ACAD drawing for Node Room No.1 removals

See shipcheck sketches for circuit 5PF1 modifications

See shipcheck sketch for circuit 3IV modifications

Node Room No.2 (03-30-6-C)

See shipchecked ACAD drawing for Node Room No.2 removals

Node Room No.3 (2-80-2-C)

See shipchecked ACAD drawing for Node Room No.3 removals

See ACAD drawing for Node Room No.3 MCS Rack installation See shipcheck sketches for circuit 5PF1 modifications

See shipcheck sketch for Node Room No.3 rack modifications. Racks will have to shift in order to accommodate new MCS Rack and to account for shock excursions.

See shipcheck sketch for Node Room No.3 arrangement modifications

Node Room No.4 (03-88-1-C)

See shipchecked ACAD drawing for Node Room No.4 removals

See shipcheck sketch for Node Room No.4 arrangement modifications

Node Room No.5 (03-108-6-C)

See shipchecked ACAD drawing for Node Room No.5 removals

See ACAD drawing for Node Room No.5 MCS Rack installation See shipcheck sketches for circuit 5PF1 modifications

See shipcheck sketch for Node Room No.5 arrangement modifications

Node Room No.6 (2-113-3-C)

See shipchecked ACAD drawing for Node Room No.6 removals

See ACAD drawing for Node Room No.6 MCS Rack installation

Continued on next page

See shipcheck sketch for Node Room No.6 arrangement modifications

See shipcheck sketch for Node Room No.6 MCS Rack installation circuit 1IM install (NSA) (cables to be run through the MMR to get to FWD IC)

FWD IC & Gyro Room & Node Room No.7 (4-113-0-C)

See shipchecked ACAD drawing for Node Room No.7 removals

See ACAD drawing for Node Room No.7 NCDS Rack installation See shipcheck sketches for circuit 5PF1 modifications

See shipcheck sketch for circuit 3IV modifications

See shipcheck sketch for Node Room No.7 arrangement modifications

See shipcheck sketch for Node Room No.7 circuit LN modification

See shipcheck sketch for Node Room No.7 circuit 1IM removal (NSA) (existing cables run through the MMR to get to Central Control)

Node Room No.8 (2-148-1-C)

See shipchecked ACAD drawing for Node Room No.8 removals

See ACAD drawing for Node Room No.8 MCS Rack installation See shipcheck sketches for circuit 5PF1 modifications

See shipcheck sketch for Node Room No.8 rack modifications. Racks will have to shift in order to accommodate new MCS Rack and to account for shock excursions.

See shipcheck sketch for Node Room No.8 arrangement modifications

See shipcheck sketch for Node Room No.8 MCS Rack installation circuit 1IM install (NSA) (cables to be run through the MMRs to get to Central Control and AFT IC)

Node Room No.9 (03-156-7-C)

Notes (Applicable to any/all dwgs):

Use memos, shipcheck and shipcheck sketches along with guidance drawings to produce SIDs.

The ACAD files included with the shipcheck package were for shipcheck purposes only. They are not intended for use as the base of the drawings to be produced.

Internal hookups for MCS and NCDS switches have yet to be determined. ISEA will provide a LAR to NNSY once hookup is complete.

For ckt 5PF1 & 3IV install drawings, draw internals of MCS racks to show placement of UPS units, batteries and/or 48VDC power supplies.

Standard mounting drawing is no longer used so all materials will have to be listed in the drawing.

When ferrules and/or lugs are required for hookup, provide in list of material.

When using tight mounting, provide the method applicable to the equipment being installed.

For HMIs currently installed on Reactor BHDs, write notes specifically to address keeping existing foundations in place and border the note within the body of the drawing to make it visible. C271 is working on talking with C2300 in getting their standard method of removing studs, clips, etc… from the Reactor BHD.

For installation of HMIs, IC/SMs and Prime Tech Receivers, install plates as detailed per shipcheck notes. Read any written shipcheck notes to prefab the plates and install them on existing foundations. Note: not all plates will be centered on existing foundations.

Make sure to clearly mark any Secondary Containment penetrations and add special notes to front sheet of drawing (where applicable).

Add RPPY NOTE to front sheet of drawing (where applicable)

Use latest version of GSO (2012 Edition)