This document provides answers to questions from potential offerors for solicitation N32205-20-R-4084, which seeks proposals for a midterm availability period of approximately 90 calendar days for ship repair work on the USNS ZEUS, commencing on or about November 16, 2020. The questions and answers clarify and revise various work items and requirements, such as removing the requirement to replace seals in gyro repeaters, deleting an item for annual voyage data recorder recertification since the ship does not have a VDR installed, and revising references and sources for authorized OEM repair contractors. The document aims to allow offerors sufficient time to review specifications, drawings and references and submit clear, unambiguous proposals that provide best value to the government.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-20-R-4084
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
QUESTION:
| 1. | Paragraphs 3.1.1.1-3.1.1.3 what is the exact location? 5-74-1-E example | |
| Paragraph 3.1.2.1 speaks of five tons frozen. What is the quantity just one? | ||
| Paragraph 3.1.2.2 speaks of two tons chill. What is the quantity just one? | ||
| Paragraph 3.1.2.3 speaks of square feet of area to be cleaned. What is the square footage? | ||
| Paragraph 5.3 states many terms found in Work Item 001 but could not find how this | spec is reference to that Item? |
ANSWER: Work item 0017 – Handling of Ships Stores has been revised and is included in this amendment.
2. Item 403 Paragraph 7.1.2 “Change the seals in the Bridge Wing Gyro Repeaters and all other outside Gyro Repeaters and service to ensure watertight integrity and accurate operation.” As per OEM Sperry Marine representative, “These repeaters are sealed and cannot be opened.”
The government’s response “This model of repeater has a rubber gasket between the top lens and the body of the repeater.”
Paragraph 7.1.2 continues to be rejected by the subject matter expert/OEM (Sperry Marine) whom stated “The repeaters on the Zeus cannot be opened up. I stand by my exception to removal and repair.”
ANSWER: Work Item 403 has been revised to remove requirement to replace the seals in the gyro repeaters, and is included in the this amendment.
3. Items 201, 203-205 Paragraph 7.10.1 – “Provide the services of an OEM authorized repair contractor to perform the work requirements of this specification.” Contractor has reached out to numerous vendors and received a “No Bid” response. If possible, please provide contact information/source for the GE components.
ANSWER: There are numerous companies that are OEM authorized service companies. This list includes, but is not limited to:
| MSI |
| Progress Rail Services |
| RPG Marine |
| 4. | Item 408 (ANNUAL VDR RECERTIFICATION) Paragraph 1.1 – “This work item | describes the requirements to inspect and service the ships Voyage Data Recorder | (VDR).” | |||
| The contractor has reached out to the suggested source (J&L Marine) for qualified | technicians provided by the specification in paragraph 7.15.1 and received a response | from J&L Marine stating “Not sure why they keep sending this out. We are | currently doing annuals on Zeus, they do not have a VDR installed and have a waiver | for it.” Please clarify/advise if Work Item 408 should deleted/removed from the | soliciation. |
ANSWER: Item 408 will be deleted from this specification package.
5. Please provide authorized OEM repair contractors to perform inspections on General Motors – Electromotive Division engines
ANSWER: This information was provided in the response to another bidder’s question.
6. The suggested OEM qualified service provider shown in paragraph 7.10.3 does not service these resilient mounts, please provide alternate(s).
ANSWER: The contractor may elect to provide a different OEM authorized service representative from the suggested source. Other possible companies include but are not limited to:
| RPG Marine |
| Progress Rail Services |
7. Paragraph 7.3.4 states that a number of bolts were already tested. Please provide the number of these bolts.
ANSWER: The requirements of Paragraph 7.3.4 of work items 609 & 610 have been deleted. These item have been revised and are included in this amendment.
8. Will MSC be providing parts: WG 105289, A304438, WG137731, and 2-908 that were required for the last availability?
ANSWER: MSC is providing all parts listed in paragraph 3.0 of subject work item. Any additional parts requiring replacement shall be the subject of a condition report at the time of identification.
It has been noted that the reference cited in paragraph 2.0 is incorrect. This item has been revised to provide the correct reference and is included in this amendment.
All of the above requested change is necessary to allow contractor time to review entire specification, references and drawings, submit requests to subcontractors, assemble and submit a proposal that will be clear, unambiguous and the best value to Government.