RFC QandA 1 Solicitation N32205-20-R-4084.docx
DOCX document 24 KB Posted
- Attached to
- USNS ZEUS MTA SHIP REPAIR
- Solicitation number
- N3220520R4084
About this file
This document provides answers to questions from potential offerors regarding solicitation N32205-20-R-4084 for a midterm availability period ship repair of the USNS ZEUS from the Military Sealift Command. The solicitation seeks proposals for repair work during a 90 calendar day period commencing on or around November 16, 2020. The answers clarify that the solicitation includes annual repair requirements to be completed before the vessel resumes its mission. Interested contractors must complete a non-disclosure agreement to receive work specifications and references. The solicitation involves the Department of the Navy's Military Sealift Command for repair of the USNS ZEUS at the Norfolk contracting office.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-20-R-4084
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
QUESTION:
1. Upon review of USNS ZEUS (T-ARC 7) R-4084 it was found that the following items appear to be duplicate items that are listed under USNS ZEUS (T-ARC 7) RDOP #110 *Amendment 01* which is currently being worked. Please advise contractor if the items listed below are duplicates and if they should be removed from USNS ZEUS (R-4084).
201, 401, 402, 403, 408, 501-503, 505, 601, 604-605, 607-610 and 655. Please clarify which contract these items are scheduled to be worked under.
All of the above requested change is necessary to allow contractor time to review entire specification, references and drawings, submit requests to subcontractors, assemble and submit a proposal that will be clear, unambiguous and the best value to Government.
ANSWER:
“The items in question are annual requirements. We are currently executing the same work at the end of FY20 window to complete. The Fall MTA goes through winter and ends in the middle of the FY21 cycle and needs to be complete again before going on mission.”