RFP_Q_and_A_5.pdf

PDF 46 KB Posted

Attached to
Auxiliary Pre-Stage Area Refrigeration System for MSC T-AKE Class Vessels
Solicitation number
N32205-16-T-4327
Issued by

View the file

Other files

File Type Posted
RFP_Q_and_A_6.pdf PDF
Amendment_5.pdf PDF
WORK_ITEM_PREP_GUIDE.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
RFP_Q_and_A_4.pdf PDF
Amendment_0002.pdf PDF
RFP_Q_and_A_3.pdf PDF
Amendment_0001.pdf PDF
RFP_Q_and_A_2.pdf PDF
RFP_Q_and_A_1.pdf PDF
PAST_PERFORMANCE_QUESTIONNAIRE_Attachment_2.pdf PDF
PAST_PERFORMANCE_DATA_SHEET_Attachment_1.pdf PDF
N32205-16-T-4327.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-16-T-4327

QUESTIONS AND ANSWERS

The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.

QUESTION 1: Is there a recommended area of installation due to the following strike between Para

3.4.1.7 and 3.4.1.8 of Amendment 0003 ? Refrigeration Units No. 1 & 2 shall be arranged in the Distributed Systems Compartment No. 3A (S) 4-58-1 and No. 3A (P) 4-58-2 respectively.

ANSWER:

The Distributed Systems Compartment is still the preferred area for installation; however, MSC recognizes that the Distributed Systems Compartment may not have sufficient air flow to maintain adequate air cooling to the refrigeration system's condensers. Installation locations where the system can achieve sufficient air cooling and provide adequate cooling to the pre-staging areas with minimal piping runs (all in accordance with the Statement of Work) is required.

QUESTION 2: Please define provide Shipyard Work Item? Shipyard Work Item (WI): The Contractor shall provide a shipyard Work Item, with the System design/modification drawings, specifying the requirements and instructions for shipyard contracted laborers to complete shipyard items in each ship's ROH. The Work Item shall be in accordance with the Work Item Prep Guide in Reference 2

ANSWER:

The reference indicated in the SOW for the Work Item Prep Guide is incorrect. The correct reference is 3 (MSC General Technical Requirements (GTR)). The GTR provides all the necessary details for development of a shipyard Work Item.

QUESTION 3: Please define "support installation" Para in 3.4.3? I assume this is defined as contractor to provide all support services such as rigging hazardous waste Waste removal, welding, piping, pier side services, etc. which would be provided in Shipyard work item in Para 3.4.2.2.

ANSWER:

Reference 3 (MSC General Technical Requirements (GTR)) provides guidance in planning for shipyard installation support.

QUESTION 4: Assuming 3.4.3.2 is directing Contractor to fully manage and coordinate job through Ship Yard Work item?

ANSWER:

The Shipyard contractors will install system components in accordance with the Work Item. The contractor shall coordinate with the shipyard and a designated MSC Technical Point of Contact to ensure the Work Item is executed correctly, and follow the installation with commissioning/operational testing of the system. Reference 3 (MSC General Technical Requirements (GTR)) provides guidance in planning for shipyard installation support.

QUESTION 5: Pertaining to 3.4.3.4,Assuming that the test plan to be outlined in 3.4.2.3 will include ABS guidelines with ABS inspector to inspect operational test?

ANSWER:

Reference 3 (MSC General Technical Requirements (GTR)) provides guidance for Operational Testing.

MSC will coordinate with the contractor, Shipyard, and ABS to inspect operational tests as required.

File details come from the government source that posted it. Updated .