RFP-RFQ_Q_and_A_9.docx
DOCX document 26 KB Posted
- Attached to
- USNS SPEARHEAD (T-EPF 1) Emergency Dry-Docking Federal contract opportunity
- Solicitation number
- N32205-16-R-4506
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP-RFQ_Q_and_A_8.docx | DOCX document | |
| RFP-RFQ_Q_and_A_5.docx | DOCX document | |
| RFP-RFQ_Q_and_A_7.docx | DOCX document | |
| RFP-RFQ_Q_and_A_6.docx | DOCX document | |
| RFP-RFQ_Q_and_A_4.docx | DOCX document | |
| RFP-RFQ_Q_and_A_1.docx | DOCX document | |
| RFP-RFQ_Q_and_A_3.docx | DOCX document | |
| RFP-RFQ_Q_and_A_2.docx | DOCX document | |
| N32205-16-R-4506-0001.doc | DOC document | |
| JA_for_USNS_SPEARHEAD_EDD_6-22-2016.pdf | ||
| USNS_SPEARHEAD_Dimensions.docx | DOCX document | |
| SPHD_EDD_Sources_Sought.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-16-R-4506
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
NAME OF CONTRACTOR: _______________________
SPECIFICATION ITEM NO.: __0101____
PARAGRAPH / SECTION NO:___4.2.1_________________
TITLE: _Government Furnished Material (GFM) _________
QUESTION:
Regarding the 110 M^2 Aluminum 5083 H111 Planking Material to be provided by the Government, will there be a standard size? If so, please provide dimensions and quantities, or clarify. Also, since we have been told that the rolling or shaping of this material is done using a proprietary method, can the Offeror assume that all planking material will be arrive in already-shaped condition, ready for installation?
ANSWER:
Specific lengths have not been determined at this time. Contractor shall assume that the planking lengths will be sufficient to perform the installations of WI 101, enclosure 1 using 5 transverse weld seams and 3 longitudinal weld seams on each hull.
Planking will be delivered in flat sheets. Shaping will be required of the contractor.