RFP-RFQ_Q_and_A_3.docx
DOCX document 25 KB Posted
- Attached to
- USNS SPEARHEAD (T-EPF 1) Emergency Dry-Docking Federal contract opportunity
- Solicitation number
- N32205-16-R-4506
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP-RFQ_Q_and_A_9.docx | DOCX document | |
| RFP-RFQ_Q_and_A_8.docx | DOCX document | |
| RFP-RFQ_Q_and_A_5.docx | DOCX document | |
| RFP-RFQ_Q_and_A_7.docx | DOCX document | |
| RFP-RFQ_Q_and_A_6.docx | DOCX document | |
| RFP-RFQ_Q_and_A_4.docx | DOCX document | |
| RFP-RFQ_Q_and_A_2.docx | DOCX document | |
| RFP-RFQ_Q_and_A_1.docx | DOCX document | |
| N32205-16-R-4506-0001.doc | DOC document | |
| JA_for_USNS_SPEARHEAD_EDD_6-22-2016.pdf | ||
| USNS_SPEARHEAD_Dimensions.docx | DOCX document | |
| SPHD_EDD_Sources_Sought.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-16-R-4506
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
NAME OF CONTRACTOR: _______________________
SPECIFICATION ITEM NO.: __0901 – Dry-Docking and Undocking Vessel________
PARAGRAPH / SECTION NO:___7.1.7_________________
TITLE: _Arrangement/Outfitting____________________________________________
QUESTION:
The work specification states that applicable stability calculations must be submitted to MSCREP for approval, fourteen (14) calendar days prior to docking. Offeror does not yet have access to the references and has no docking plans or modifications on file with MSC. Given the anticipated 6 July docking date, will the Government waive this requirement, or will Offeror be judged ineligible/unqualified?
ANSWER:
Fourteen day requirement for stability calculations is waived. Stability calculations shall be submitted to MSCREP at least two normal working days prior to docking for approval. Docking plan is included with work item 901 references and will be available upon receipt of references.