RFP-RFQ_Q_and_A_2.docx
DOCX document 25 KB Posted
- Attached to
- USNS SPEARHEAD (T-EPF 1) Emergency Dry-Docking Federal contract opportunity
- Solicitation number
- N32205-16-R-4506
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP-RFQ_Q_and_A_8.docx | DOCX document | |
| RFP-RFQ_Q_and_A_9.docx | DOCX document | |
| RFP-RFQ_Q_and_A_5.docx | DOCX document | |
| RFP-RFQ_Q_and_A_7.docx | DOCX document | |
| RFP-RFQ_Q_and_A_6.docx | DOCX document | |
| RFP-RFQ_Q_and_A_4.docx | DOCX document | |
| RFP-RFQ_Q_and_A_1.docx | DOCX document | |
| RFP-RFQ_Q_and_A_3.docx | DOCX document | |
| N32205-16-R-4506-0001.doc | DOC document | |
| JA_for_USNS_SPEARHEAD_EDD_6-22-2016.pdf | ||
| USNS_SPEARHEAD_Dimensions.docx | DOCX document | |
| SPHD_EDD_Sources_Sought.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-16-R-4506
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
NAME OF CONTRACTOR: _______________________
SPECIFICATION ITEM NO.: __0901 – Dry-Docking and Undocking Vessel________
PARAGRAPH / SECTION NO:___7.1.1_________________
TITLE: _Arrangement/Outfitting___________________________________________________
QUESTION:
The work item states that the Contractor shall provide a single section steel or concrete floating dock, marine railway or graving dock certified in accordance with Reference 2.1.5. Offeror has a steel floating dock that is comprised of six (6) sections of structural grade steel with a lift capacity of 40,000LT. It is ABS certified. Will the Government waive the requirement for a single section dock?
ANSWER:
Floating docks comprised of sections will be considered and evaluated on a case by case basis using the contractor provided specifics of the dock. Contractor shall submit the dock qualifications in accordance with the original solicitation.