RFP-RFQ_Q_and_A_7.docx
DOCX document 26 KB Posted
- Attached to
- USNS SPEARHEAD (T-EPF 1) Emergency Dry-Docking Federal contract opportunity
- Solicitation number
- N32205-16-R-4506
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP-RFQ_Q_and_A_8.docx | DOCX document | |
| RFP-RFQ_Q_and_A_9.docx | DOCX document | |
| RFP-RFQ_Q_and_A_5.docx | DOCX document | |
| RFP-RFQ_Q_and_A_6.docx | DOCX document | |
| RFP-RFQ_Q_and_A_1.docx | DOCX document | |
| RFP-RFQ_Q_and_A_4.docx | DOCX document | |
| RFP-RFQ_Q_and_A_3.docx | DOCX document | |
| RFP-RFQ_Q_and_A_2.docx | DOCX document | |
| JA_for_USNS_SPEARHEAD_EDD_6-22-2016.pdf | ||
| N32205-16-R-4506-0001.doc | DOC document | |
| USNS_SPEARHEAD_Dimensions.docx | DOCX document | |
| SPHD_EDD_Sources_Sought.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-16-R-4506
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
NAME OF CONTRACTOR: _______________________
SPECIFICATION ITEM NO.: __0104________
PARAGRAPH / SECTION NO:___Reference 2.3, Sheet 4A_________________
TITLE: _ SFP-60 Minute Fire Rated Lagging System _________
QUESTION:
Lagging attachment pins identified in item 0104 are called out on 8444207, SFP-60 Minute Fire Rated Lagging System, sheet 4a, details A, B, and C. Insulation pins (items 7 and 9) are specified as 10 ga. bi-metallic stainless steel/aluminum, blunt end, 61mm and 112mm, respectively, to be capacitor discharge welded w/ Midwest Fastener CD-100 welder or Equivalent. To minimize aluminum welding and possible sensitization to structure, can these pins be substituted with similar pins with exception of installation using click-bond type method?
ANSWER:
Alternative methods of stud attachement will be considered. Contractor shall submit alternative proposal along with fire rating compatability documents.