RFP-RFQ_Q_and_A_5.docx

DOCX document 26 KB Posted

Attached to
USNS SPEARHEAD (T-EPF 1) Emergency Dry-Docking Federal contract opportunity
Solicitation number
N32205-16-R-4506
Issued by
Department of the Navy Military Sealift Command

View the file

Other files for this federal contract opportunity

Other files attached to USNS SPEARHEAD (T-EPF 1) Emergency Dry-Docking, newest first.
File Type Posted
RFP-RFQ_Q_and_A_9.docx DOCX document
RFP-RFQ_Q_and_A_8.docx DOCX document
RFP-RFQ_Q_and_A_7.docx DOCX document
RFP-RFQ_Q_and_A_6.docx DOCX document
RFP-RFQ_Q_and_A_3.docx DOCX document
RFP-RFQ_Q_and_A_2.docx DOCX document
RFP-RFQ_Q_and_A_1.docx DOCX document
RFP-RFQ_Q_and_A_4.docx DOCX document
JA_for_USNS_SPEARHEAD_EDD_6-22-2016.pdf PDF
N32205-16-R-4506-0001.doc DOC document
USNS_SPEARHEAD_Dimensions.docx DOCX document
SPHD_EDD_Sources_Sought.docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-16-R-4506

QUESTIONS AND ANSWERS

The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.

NAME OF CONTRACTOR: _______________________

SPECIFICATION ITEM NO.: __0011________

PARAGRAPH / SECTION NO:___7.1.12.1_________________

TITLE: _General Services for Ship__________________________________________

QUESTION:

The work specification states that the contractor shall “Clean the entire ship on a daily basis, Monday – Saturday, except federal holidays. All decks, passageways, and work areas shall be swept clean and debris free on a daily basis.” “Entire ship” implies all spaces on the ship, but the second sentence sounds like the intent is for the contractor to clean only those spaces in which it is specifically performing work, along with adjoining decks and passageways? Please clarify.

ANSWER:

Contractor shall clean the entire ship on a daily basis. Spaces which remain locked by ships force will not be required to be cleaned unless the contractor gains entry.