USNS WALLY SCHIRRA
(T-AKE 8)
900-DRYDOCKING AND UNDOCKING
N33205-16-R-0000
03 JANUARY 2016
ITEM NO. 0910
CATEGORY "B"
MSC PM6/SA/NMK
DRY-DOCKING AND UNDOCKING VESSEL
1.0 ABSTRACT:
1.1 Continue dry-docking ship past the scheduled Contract Completion Date.
2.0 REFERENCES:
2.1 Work Item 901, Dry-Docking and Undocking Vessel.
3.0 ITEM LOCATION/DESCRIPTION:
3.1 Location/Quantity/ Description: In accordance with reference 2.1 (WI 901 Dry-Docking and Undocking Vessel).
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.
5.0 NOTES:
5.1 The Contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s including but not limited to GTR’s 1 through 7 and 29.
5.2 The Contractor and all subcontractors, regardless of tier, are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.
6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional.
7.0 STATEMENT OF WORK REQUIRED:
7.1 Arrangements and Outfitting:
7.1.1 Submit a unit price per day and extended price for up to a maximum of five (5) days to continue all services in accordance with Work Item 901.
7.2 Structural: None Additional.
7.3 Mechanical/Fluids: None Additional.
7.4 Electrical: None Additional.
7.5 Electronics: None Additional.
7.6 Preparation of Documents/Documents: None Additional.
7.7 Inspection/Test: None Additional.
7.8 Painting: None Additional.
7.9 Marking: None Additional.
7.10 Manufacturer’s Representative: None Additional.
8.0 GENERAL REQUIREMENTS:
8.1 If this CAT B Work Item is invoked, the work requirements in this work item shall be finalized and/or completed as required for meeting scheduled milestones as outlined in Work Item 013 “Project Planning and Production Status Monitoring Reports”, paragraph 7.1.7 “Milestones”.
8.2 Offers must provide both a unit price and an extended total price for accomplishing the above paragraph 7 scope of work.
0910 - 2