Amendment 0004.pdf

PDF 232 KB Posted

Attached to
Combat Integration & Identification Systems (CI&IDS) Lab Revitalization Project
Solicitation number
N0042120B0003
Issued by

About this file

This document contains an amendment to a solicitation for the construction of an office building and responses to requests for information related to the project. The amendment extends the contract duration from 365 days to 545 days in response to questions about lead times for materials and long lead equipment. It also provides responses to 115 questions submitted by potential offerors to clarify requirements. Key details include the location of the single-story, approximately 11,400 square foot office building in St. Inigoes, Maryland, under Solicitation Number N0042120B0003 issued by the Naval Air Warfare Center Aircraft Division for the Combat Integration and Identification Systems Lab Revitalization Project. The amendment incorporates changes and clarifications to specifications, drawings, and general project requirements.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the follow ing changes into the solicitation:

1. Provide responses to RFIs.

2. Revise the contract duration in block 11 from 360 calendar days to 545 calendar days.

1. CONTRACT ID CODE PAGE OF PAGES

1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Feb-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0042120B0003

X 9B. DATED (SEE ITEM 11)

07-Jan-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Feb-2021

CODE

NAWCAD PROCUREMENT GROUP

21983 BUNDY ROAD, BLDG 441

PATUXENT RIVER MD 20670

N00421 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0042120B0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been modified:

REQUESTS FOR INFORMATION

Requests for Information (RFI) Log

Question 036: Is the NPDES Permit required for this project?

Response 036: Yes

Question 037: Sheet V-101 – This sheet shows the removal of vegetation in the wetland buffer area. Has a wetlands permit been submitted to the Maryland Department of the Environment?

Response 037: The MDE Permit does cover all land disturbing activities associated with this project.

Question 038: Sheet C-101 – Please identify the concrete at the top right corner of the building.

Response 038: The concrete pad in question is a mechanical equipment pad for DSS-1. Please refer to sheet M-403.

Question 039: Sheet C-101 – The Base Bid is for a building that is approximately 141 feet long. This sheet shows a building approximately 161 feet long, incorporating the extra 20 feet in CLIN 0002. Will all the downspouts shown on this drawing be included in the base bid or are two of them in CLIN 0002?

Response 039: All downspouts shown on the drawing shall be included in base bid.

Question 040: Sheet C-101 – The LOD shown on this drawing does not include the sewer tie-in to the Pump Station. Should the LOD be revised to include this work on Sheets C-101, C-102, C-103, C-106, and C-107?

Response 040: As no permanent modification to the site conditions will result from the trenching/installation of the sewer tie-in, sheet C-107 LOD will be revised to include a 20-FT wide working area to extend to the existing pump station. Disturbed area shall be returned to existing grade and stabilized immediately following the installation of the sanitary pipe.

Question 041: Sheet C-103 – There is a valve located before the tee labeled W5 with no identification. Please identify.

Response 041: The valve located before the tee “W5” is an 8-inch valve, name: W3. Location information is provided on sheet C-103 Appurtenances Table.

Question 042: Sheet C-104 – The coordinate layout tables reflect the CLIN 0002 building size. Will new coordinates be provided for the base bid?

Response 042: Yes, a revised coordinate table will be provided.

Question 043: Specification Section 00 22 13.00 20, Part 1, item b states “The Government reserves the unilateral right to award CLIN 0002, CLIN 0003, CLIN 0004, and CLIN 0005 to the Contractor at the proposed price within 365 calendar days after the contract award. A firm fixed proposed price is required for CLIN 0001, CLIN 0002, CLIN 0003, CLIN 0004, and CLIN 0005. No provision is made for economic price adjustment. If Options are exercised, the contract completion date remains unchanged.” The contract duration is also for 365 calendar days, so technically, these CLIN’s could be awarded on the last day of the contract with no time to complete the work. All four CLIN’s will require time to complete and CLIN 0005 has a long lead item included that may take months to get approved, fabricated, delivered, installed and tested. Can this paragraph be modified to reflect that justifiable time will be added based on the availability of the items and length of contract time remaining?

Response 043: The following statement will be deleted from Section 00 22 13.00 20, Part 1, item b of the specifications. As stated on page 7 of the solicitation in the general bid notes, the base bid and only the options exercised at the time of award will be evaluated. Options that are not exercised at the time award will not be exercised at a later date. This does not apply to the CLIN 0006 FF&E planned modification.

Question 044: 3.2.1 states spot grout frames in dry wall partitions with mortar. Manufacturers only require minimum 6 lb PCF density mineral wool. Labor and time savings if rock wool can replace mortar/grouting as well.

Response 044: Please adhere to the specifications provided.

Question 045: Are any hazardous materials present? If yes, please provide any available hazmat reports.

Response 045: No hazardous materials of significance were identified at this site as part of a Hazardous Material Inspection performed in June of 2019.

Question 046: Also, 3.2.1 states spot grout frames in dry wall partitions with mortar. Manufacturers only require minimum 6 lb PCF density mineral wool. Labor and time savings if rock wool can replace mortar/grouting as well.

Response 046: Please adhere to the specifications.

Question 047: Please advise if this specification is required? Referencing Section 01 78 30.00 23 CADD Data for GIS Deliverables.

Response 047: See specification section 01 78 30.00 23 CADD Data for GIS Deliverables requirement.

Question 048: Is there an existing system in the building to have to match and link up with? If yes, who is the contractor? Referencing 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM.

Response 048: A new combined fire alarm and mass notification is required for the building. All alarm, supervisory, and alarm conditions must be reporting to the Regional Dispatch Center via fire alarm dialer. The compatible dialer is DMP and manage by FCI/Johnson Controls.

Question 049: Is there an existing system in the building to have to match and link up with? If yes, who is the contractor? Referencing 27 40 00 AUDIO-VIDEO COMMUNICATIONS.

Response 049: No, there are no existing systems.

Question 050: Please confirm that the only items required as part of bid submission are: Pricing of all CLINs, completed and signed SF 1442 to include acknowledgment of solicitation amendments, completed SAM Representations and Certifications, and Bid Bond.

Response 050: Confirmed

Question 051: For electronic security, spec section 28 10 05, is there a preferred manufacturer which the programming integrates with the rest of the installation? Can you provide a list of manufacturers that are compatible with the installation's central monitoring system?

Response 051: Electronic security is infrastructure only.

Question 052: It appears that the security systems are rough in only, and provide by others? Is this the case or should the contractor be supplying and installing security, surveillance, access control, etc?

Response 052: Infrastructure only.

Question 053: Sec 01 14 00 – 1.5.3 States that a Backflow Prevention on domestic water is not a requirement unless a facility is considered high hazard. Backflow preventer is not shown on plans so please confirm this building is not high hazard and a BFP will not be required on the DCW.

Response 053: A backflow preventer is not required on the incoming domestic water line.

Question 054: Please confirm that per section 01 35 26 – 1.7.1.1.1 the SSHO may also serve as the site QC Manager and that the superintendent must be a separate individual making the required onsite staff 2 persons.

Response 054: Please refer to Specification 01 35 26 Section 1.7.1.1.1, as stated “The SSHO may serve as the Quality Control Manager. The SSHO may not serve as the Superintendent”.

Question 055: Please confirm that the onsite management team (Superintendent/QC Manager) must be employed by the general contractor awarded the project as has been required on past projects.

Response 055: Please refer to Specification 01 35 26.

Question 056: Detail 2/C-502 shows a free-standing yard type fire department connection which is more costly compared to the wall mount fire department connection which is shown on C-105, FX001, FX101 & FX501. Please confirm wall mount connection is acceptable.

Response 056: Please refer to C-103 of the drawing key note #4.

Question 057: Drawings make mention of painting sprinkler piping. Will this be required on all sprinkler piping throughout or only in certain areas. Please specify.

Response 057: Painting is in all areas, finished and unfinished. Please refer to Specification 09 90 00, Section

1.12.3.1 for specifics.

Question 058: Will building lighting protection require 3rd party testing and UL certification upon completion?

Response 058: If the question is in regards to building lightning protection, please see Specification 26 41 00 Section 1.4.4.

Question 059: On recent Navy projects we have been required to install conduit (EMT) either from data drops to data closet or from data drops to cable trays and using “J” hooks to hang cables between drops and tray/data room was not allowed. Please confirm this is the requirement for this project. If not, please specify where conduit will/will not be required.

Response 059: Please refer to TN010 of the drawings under general notes #19 and TN101, Keynote #1.

Question 060: How many conduits will be required from above ceiling to wall box for each data drop?

Response 060: Please refer to TN401 of the drawings.

Question 061: The specs mention project fencing. Since this project is in such a remote location, with very little pedestrian foot traffic, fencing seems unnecessary. Can the fencing requirement be removed to help project budget?

Response 061: Please adhere to the specifications.

Question 062: We have recently been informed of PEMB and FF&E lead times up to 6 months due to COVID. The listed project duration of 365 days would not accommodate these lead times. Can an additional 180 days be added to the project duration?

Response 062: An amendment will be issued to extend the contract duration from 365 calendar days to 545 calendar days.

Question 063: Please confirm we should use the gov’t provided, estimated FF&E cost listed in the solicitation to project cost for proposal.

Response 063: Please refer to Specification 00 22 13.00 Section 1.3 (A).

Question 064: Please confirm that ALL A/V equipment is included in the gov’t purchased FF&E. If not please specify (list) all equipment that the contractor will be required to purchase and install as part of the base bid in the proposal.

Response 064: The government will procure and install A/V equipment.

Question 065: Will building signage and window shades be included in base bid or FF&E option?

Response 065: Please refer to Specification 10 14 00.20 for building signage. Please refer to Specification 12 24 13 Section 1.4.1.1 for window shades.

Question 066: The interior designer, structural interior design and A/V consultant will be required in order to properly locate rough-ins for FF&E. Please confirm these consultants and their full scope of required services should be included in the base bid of this proposal.

Response 066: Please refer to Specification 01 30 01 00 20.

Question 067: Will wire, cable, and devices etc. for FF&E be included as part of the base bid or should it be included in the FF&E option with only rough-in included in the base bid?

Response 067: Please refer to Specification 01 30 01 00 20 Section 3.

Question 068: Will FPE stamp be required for fire alarm design or will NICET cert suffice? If NICET is acceptable, please specify minimum cert level.

Response 068: Please refer to Specification 01 45 00.00 20 Section 1.5.6.

Question 069: Will an additional (3rd party) FPE be required for design review and testing acceptance?

Response 069: A QFPE (qualified fire protection engineer) is required for shop drawing review and testing acceptance. The DFPE (designated fire protection engineer (i.e. NAVFAC)) is also required to review the shop drawings (after QFPE approval), and should be present for the testing acceptance. A third party FPE should not be required. Ref: Spec 21 13 13.00 20 Section 3.1, and UFC 4-021-01 Section 9-18.2.

Question 070: Please confirm that HPSB checklist will be required.

Response 070: Please refer to Specification 01 33 29 Section 1.4 thru Section 1.5.1.1

Question 071: Who will be responsible for insuring Sustainability requirements are adhered to? Will individual with GBCI cert be required?

Response 071: Please refer to Specification 01 33 29 Section 1.4 thru Section 1.5.1.1 .

Question 072: Please confirm all required MDE permits, including Air Permit (for generator), are by gov’t and NOI has been filed.

Response 072: The Stormwater Permit NOI needs to be submitted electronically by the contractor not the Gov’t. Once submitted the Gov’t will sign on as Property owner and allow the contractor to complete the process. There is a 1 day public comment period and if no adverse comments are received then the permit will be approved. In regards to the Air permit, the Contractor is responsible to pay for the permit and to also provide the Air Program Manager (PM) the permit application and a copy of the generator specs. The Air PM will submit both the application and check to MDE. Note, per MDE Form 42, Generators under 373 Kilowatts or 500 Brake Horsepower do not require an Air Quality Permit. The aire permit will not be required if the CLIN is not awarded.

Question 073: Please confirm VOC testing of domestic water is not required as part of this project.

Response 073: Please refer to Specification 22 00 00 Section 3.8.5.

Question 074: Please confirm GIS survey is required as part of this project.

Response 074: Please see response to question #47.

Question 075: Will the contractor be responsible for providing & keying of all lock cores or will cores be by gov’t?

Response 075: Please refer to Specification 08 71 00 Section 2.3.6.

Question 076: Please confirm that all walls below ceiling are level 4 finish. Please identify any walls that (for security purposes) will be required to be finished and painted to level 4 above ceiling.

Response 076: Please refer to Specification 09 29 00 Section 3.3.1.

Question 077: Should LED signs for FA system be fully programmable or will 2 message signs be acceptable?

Response 077: Please refer to Specification 28 31 79 Section 2.5.3.

Question 078: The specs mention employment of a Cybersecurity subject matter expert for to oversee or execute all cybersecurity related work listed in that section. This is an unusual requirement; please confirm the services (as listed in the specs) of this consultant should be included in this proposal.

Response 078: Please refer to Specification 25 05 11.01 Section 1.7 of the CI&IDS Specification (Please also see attached Building Communication Room Specification REV 8).

Question 079: Please provide minimum insulation R-Values for PEMB walls and Roof.

Response 079: Refer to Specification 13 34 19 Metal Building Systems, Sections 1.2.4.1 and 1.2.4.2. Values are given in terms of U-factors, which are the reciprocals of R-Values.

Question 080: Please confirm contractor will be required to provide the ACU and JCI dialer for the FA/Mass Notification System.

Response 080: Please refer to FA001 of the drawing (Fire Alarm General Notes)

Question 081: Will the lab spaces be TEMPEST level SCIF, requiring single point of entry for Data/Electric/Water/etc., Fiber for data, dielectric Unions etc.? If not please provide security level of the lab spaces and list of security requirements?

Response 081: Please refer to TN102 General Notes # 1 of the drawing.

Question 082: Is fiber required for FA/MN where penetrating secure lab spaces?

Response 082: Please refer to Specification 28 31 76 Section 1.7.1.1.

Question 083: Man bars are shown in the ducts penetrating the lab spaces but not in the ducts or exhaust fans on the other end of the building. Please confirm man bars are not required outside of the lab spaces.

Response 083: Please refer to A-504 of the drawing’s Detail B3.

Question 084: Please confirm the security system is by the contractor and specify whether it should be included in the base bid or FF&E option.

Response 084: Contractor is responsible for the infrastructure only, which should be included in the base bid.

Question 085: Will telecom, data and cable trays be included as part of the base bid or FF&E option?

Response 085: This will be included in the base bid.

Question 086: The drawings show multiple data racks. Please list all racks/related equipment which will be provided by contractor and specify whether they are part of the base bid or FF&E option.

Response 086: Government will provide cabinet, rack and patch panels.

Question 087: Please confirm items listed on sheet TN011 will be provided by gov’t and specify which components will be installed by contractor. If this is incorrect, please specify equipment provided by contractor and whether they will be part of the base bid or FF&E bid option.

Response 087: Please see response to question #86.

Question 088: Will fencing, security or aesthetic, be required around any of the exterior HVAC units? If yes please specify.

Response 088: There is no fencing noted within the drawing around exterior HVAC units.

Question 089: Please provide specs for ATFP dampers listed in the drawings to be installed in the lab space ducts.

Response 089: ATFP dampers must comply with specification 230913, section 2.4. ATFP dampers must be Class 1A with a maximum leakage rate of 3 CFM/SF with a differential pressure of one inch of water gage across the damper.

Question 090: Sheet A-610 shows all walls butting to underside of roof deck but other details show fabric faced insulation between purlins and walls stopping at bottom of purlins. Please specify which is correct and if walls will stop at bottom of purlins please provide detail for acoustical sealant between top of wall and insulation.

Response 090: Please adhere to what is stated in A-610 of the drawing.

Question 091: Please confirm lab walls do not require expanded metal for security.

Response 091: Confirmed there is no specification for expanded metal.

Question 092: Please confirm commissioning specialist and the commissioning firm are to be employed by GC.

Response 092: Please refer to Specification 01 91 00.15.

Question 093: Which version of the UFC 4-010-01 will be used for this project? The attached version was updated August 2020 and the attached drawings where the reference is made are dated September.

Response 093: Use the version of UFC 4-010-01 as referenced in the drawings.

Question 094: What is the estimated distance for bid purposes from BLDG 8101 (FDN-15) to CMH-15.1; from CMH-15.1 to CMH-15.1.1; from CMH15.1.1 to CMH 15.1.2; and from CMH-15.1.2 to TR-202?

Response 094: Please refer to TN301 of the drawing; the contractor will only be responsible for going from CMH-15.1.2 (fiber exist) to TR-202.

Question 095: Please confirm that ALL Rack mounted CAT6 patch panels and ALL rack mounted fiber patch panels depicted and/or required for cable termination in TR-202 will be GOVERNMENT FURNISHED/CONTRACTOR

INSTALLED.

Response 095: Confirmed

Question 096: Will fusion splice enclosure in existing OCEF Cabinet in BLDG 8101 be GOVERNEMNT FURNISHED along with appropriate fusion splice trays?

Response 096: The OCEF enclosure is in Building 8101. The Government will not be furnishing fusion splice trays

Question 097: Where are Rooms TOP SEC LAB 135, and SECRET LAB 134 located? Are these rooms mislabeled on drawing TN301?

Response 097: Please refer to TN102 of the drawing for lab location.

Question 098: Will the RED STP CAT6 network drops be routed from and terminated in the Co-Lo cabinet in TR- 202, or will they be terminated on wall mounted patch panels in their respective LAB Rooms? Drawing TN301 suggest wall mounted?

Response 098: Please refer to TN402 of the drawing, Detail C-4

Question 099: What type of connectors will be used for Single mode fiber terminations – 24 strand interconnect between BLDG 8101 (FD-15) and TR-202 AND for the 6 strand interconnects between TR-202 and Rooms AV 110A, TOP SEC LAB 135, and SECRET LAB 134 as depicted in drawing TN301?

Response 099: Fiber from 8101 to new building is to use “SC” connectors as stated on page TN301, keynote 6 and #2 of keynote 6 of the drawing.

Question 100: Div 28 security (according to the door schedule in the TY series of drawings) that the responsibility for the security contractor is to provide conduit with a pull string only. There are few details in the CSI Div 28 specs that indicate what system the client wants except to state COTS. There are no details for the intrusion or video systems. Please confirm that they want a turn key system and if yes, where can the Div 28 details be found?

Response 100: As per drawing, infrastructure only.

Question 101: Drawing #TN011, within the equipment schedule, GFCI for patch panels. Please confirm products that are to be government provided versus contractor provided.

Response 101: The government will provide cabinet, equipment rack and patch panels.

Question 102: Please provide a distance to or location of building #8101 for fiber optic cable as noted on #TN301.

Response 102: Please refer to TN301 of the drawing; the contractor will only be responsible for going from CMH-15.1.2 (fiber exist) to TR-202.

Question 103: Drawing #TN301, key note #7 states to splice the new 100 pair copper cable to the existing 1200 pair cable. Will a new splice case be required? Will the contractor need to re-seal an existing splice case for the 1200 pair cable?

Response 103: Cables will be spliced in existing manhole CMH-15.1.2, the contractor will not need to re-seal existing splice case.

Question 104: Will the basket tray be installed by the electrical contractor or by the low voltage contractor?

Response 104: Please refer to TA201 of the drawing.

Question 105: Plan sheet C-503 indicates the aggregate base is 21A, however this is a Virginia specification not Maryland. The Maryland typically GAB (Graded Aggregate Base), can this be changed or do you want a Virginia material, which will have to be imported. Spec section 321216 indicates using Maryland State Highway Standards.

Response 105: Please refer to Specification 32 12 16.

Question 106: Should the concrete pad, duct bank and interior box for the ATS shown for the generator option be included in the base bid and be installed even if the generator option is not awarded or will these tasks only be completed if the generator option is awarded?

Response 106: All costs associated with the generator option shall only be included in CLIN 0005.

Question 107: I still do not understand THE FF&E Portion, the original Solicitation had CLIN 0006 FF&E WITH A 5% MARKUP, with a given value for the FF&E- AMEND1 STATES FF&E IS TO BE DELETED, AMEND2 then states we are to purchase the FF&E . What about the bid Form, will this be modified to reflect the ff&e, and don’t forget the Bid option 1 affects the FF&E count and there is no reflection shown for this, if bid option 1 expands the building by 1600 sqft, that would increase the FF&E and this is not reflected in anyway. Please clarify the FF&E portion.

Response 107: The FF&E was calculated with BID option 1 included.

Question 108: The Equipment Schedule in Drawing TA012 indicates that Table Box TB1 should have a 5” touch panel. However, the connectivity required exceeds the capacity of the cable cubby with a 5” touch panel. The larger cable cubby with a 7” touch panel is required to accommodate the specified connectivity (regardless of whether the connectivity in TA012 or TA601 is correct). Please, confirm approval to use the larger size cable cubby.

Response 108: Infrastructure only required.

Question 109: Who has the controls for this project?

Response 109: NAWCAD in conjunction with NAVFAC requirement.

Question 110: What is the clearance required to work on base?

Response 110: Please refer to Specification 01 14 00 Section 1.4.

Question 111: Could you please provide the correct specifications/drawing set for this project? The Specs and Drawings do not correlate with one another. The Division 27 specs do not match drawings.

Response 111: Please refer to the drawing.

Question 112: Bid Option 2 conflicts with bid Option 1- Bid option 2 is also part of bid option1 so how will this be priced?

Response 112: BID Option 2 is for the partition and door with sidelight for all offices as noted on the drawing on A-101.

Question 113: Air barrier is shown on the drawings, but no specs were provided, please provide spec for the air barrier.

Response 113: Please refer to Specification 07 05 23.

Question 114: Bid option 2 is not shown on the door schedule A-601, please provide- Response 114: Please refer to A-601 of the drawing, door 125 and 126.

Question 115: The bid for option 2 States Rm 130 – please designate what exactly is the bid option 2, nothing is explained in the finish schedule either.

Response 115: Please refer to A-601 of the drawing. Option is for offices 120 through 129.

Question 116: 3M Dusted Crystal window film is listed in the finish schedule but I do not see a description as to where it is to be applied. Please Clarify.

Response 116: Please refer to A-620 of the drawing, Remark #3.

*Responses to all remaining RFIs that were submitted timely will be issued via amendment.

SECTION 00 10 00 - SOLICITATION

The contractor period of performance end date has increased by 180 days from 365 days to 545 days.

(End of Summary of Changes)