J06 Submittal Log.pdf

PDF 134 KB Posted

Attached to
Georgeville Wastewater System Improvements
Solicitation number
75H70120R00026
Issued by

About this file

This solicitation is for the Georgeville Wastewater System Improvements project, a construction contract with the Indian Health Service. Key details include: the scope of work is to make improvements to the sewer system owned by the Yakama Nation near Goldendale, Washington; the period of performance is 120 calendar days from notice to proceed; the construction magnitude is estimated between $500,000 and $1,000,000; the contract type is firm fixed price; the acquisition will use lowest price technically acceptable procedures; the proposal due date is March 26, 2020 by 2:00pm PST; registration in the System for Award Management is required; the set-aside is for small businesses in NAICS code 237110 with a size standard of $39.5 million.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR:

Item No. Item Description and Reference Type, Model No., Manufacturer, etc.

Received Date Approval Status

1 Product Data 2 Shop Drawings

3 Water Service Line 4 Fittings 5 Curb Stop Valve 6 Curb Stop Valve Box

7 Drain Piping 8 Plumbing Fixtures

9 Top Soil - supplier and gradation

10 Crushed Surfacing Top Course -supplier and gradation

11 Ballast - supplier and gradation

Quarry Spalls - supplier and gradation

13 Pipe Embedment - supplier and gradation

14 Drainage Sand - supplier and gradation

Standard Proctor with Proctor curve for each soil type encountered and used on the job

16 Compaction Test Results

17 13lb sample and gradation of imported fill materials

Proctor curve with maximum density and optimum moisture content indicated

19 Field density and moisture test results

Section 31 23 17 - Rock Excavation

MATERIAL SUBMITTAL REVIEW FORM - CONSTRUCTION

YAKAMA NATION

GEORGEVILLE WASTEWATER SYSTEM IMPROVEMENTS

[CONTRACT #]

Section 13 34 23 - Fiberglass Control Building

SUBMITTALS REQUIRED

Section 22 11 12 - Facility Water Service

Section 22 42 50

Section 31 05 15 - Basic Site Soils and Aggregates

Section 31 23 10 - Excavation, Trenching and Backfill

Section 31 23 15 - Strutural Excavation and Fill

Contractor blasting license and/or blasting permit

21 Silt Fence Material (or alternate)

Temporary Erosion and Sediment Control Plan (TESC Plan)

Seed mixture and application rate data

24 Fertilizer and application rate

Mulching material and application rate

26 Hydro-seeding equipment

Temporary sewer bypass pumping plan

28 Non-shrink grout 29 Crack filling solution

30 Manifold Pipe and Fittings 31 Distribution Pipe and Fittings 32 Subsurface Drip Dispersal Line

33 Product Data 34 Shop Drawings

35 Product Data 36 Shop Drawings

37 Manifold Pipe, Fittings, Valves, Valve Boxes

Subsurface Drip Dispersal Line and Fittings

39 Plumber's License

Piping and Appurtenances: pipe and fittings, joint restraint, backwash filter, ball valves, solenoid valves, air vent/vac relief valve, pressure gauge, flow meter, sample taps

Section 33 34 35 - Packaged Filtration Unit

Section 33 34 50 - Drip Drainfield Construction

Section 40 23 10 - Process Piping

Section 31 25 00 - Erosion and Sedimetn Control

Section 32 21 13 - Chain Link Fence and Gate

Section 32 90 20 - Topsoiling, Seeding, Fertilizing, and Mulching

Section 33 01 34 - Existing Septic Tank Repair

Section 33 31 25 - Wastewater Force Main Piping

Section 33 34 10 - Prefabricated Fiberglass Equalization Tank

CONTRACTOR:

Item

No.

Item Description and Reference Type, Model No., Manufacturer, etc.

Received

Date Approval Status

1 Shop Drawings - See section 26 60 00

2 Testing Procedures

3 Reporting Forms

4 Test Data and Results

5 Operational Certification

6 Certification

7 Calibration List

8 Test Log

9 Shop Drawings - see section 26 60 00

Shop Drawings - See sections 26 60 00 and 26 01 26

11 Shop Drawings - See section 26 60 00

12 Shop Drawings - See section 26 60 00

13 Shop Drawings - See section 26 60 00

14 Shop Drawings

15 Record (as-installed) Drawings

16 Certifications and Test Reports

17 Operating and Maintenance Manuals

18 Warranties (Guarantees)

19 Shop Drawings - See section 26 60 00

20 Shop Drawings - See section 26 60 00

Section 26 01 26 - Electrical Testing

Section 26 05 19 - Wire and Cable

SUBMITTAL REVIEW FORM - ELECTRICAL

YAKAMA NATION

GEORGEVILLE WASTEWATER SYSTEM IMPROVEMENTS

[CONTRACT #]

SUBMITTALS REQUIRED

Section 26 28 16 - Safety Disconnect Switches

Section 26 28 00 - Overcurrent Protective Devices

Section 26 05 33 - Raceways

Section 26 05 26 - Grounding

Section 26 90 25 - Control Components

Section 26 60 02 - Basic Materials and Methods

Section 26 60 00 - Electrical General Provisions

File details come from the government source that posted it. Updated .