J02 Appendix A Estimated Heating Water System Volume.pdf

PDF 134 KB Posted

Attached to
Replace Heating Plant
Solicitation number
75H70122R00036
Issued by

About this file

This document contains an appendix estimating the heating water system volume for the Pine Ridge Hospital replacement project. It provides pipe sizing, length, area, cubic feet, and gallons for the existing heating water supply and return systems for various buildings on site. It also includes notes on the basis of design for the heating plant and estimated volumes for air handling unit coils, VAV terminal units, unit heaters, and radiant panels. The related federal contract opportunity is a solicitation to replace the existing heating plant at Pine Ridge Hospital in Pine Ridge, South Dakota. The contractor will furnish all labor, equipment, materials, and transportation necessary to perform the project in accordance with the attached scope of work, technical provisions, and drawings. The soliciting agency is the Department of Health and Human Services Indian Health Service.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ESTIMATED HEATING WATER SYSTEM VOLUME

SITE: PINE RIDGE HOSPITAL

SYSTEM: HEATING WATER SUPPLY AND RETURN

REVISED: 4‐21‐2022

BUILDING AREA PIPE SIZE LENGTH (FT) AREA (FT2) CUBIC FEET GALLONS NOTES

A 0.50 235 0.001 0.3 2.4

A 0.75 1720 0.003 5.3 39.5

A 1 190 0.005 1.0 7.8

A 1.25 160 0.009 1.4 10.2

A 1.5 200 0.012 2.5 18.4

A 2 70 0.022 1.5 11.4

A 3 110 0.049 5.4 40.4

B 0.50 310 0.001 0.4 3.2

B 0.75 1340 0.003 4.1 30.8

B 1 490 0.005 2.7 20.0

B 1.25 190 0.009 1.6 12.1

B 1.5 100 0.012 1.2 9.2

B 2 60 0.022 1.3 9.8

B 4 80 0.087 7.0 52.2

C 0.5 465 0.001 0.6 4.7

C 0.75 620 0.003 1.9 14.2

C 1 210 0.005 1.1 8.6

C 1.25 170 0.009 1.4 10.8

C 2 70 0.022 1.5 11.4

C 4 370 0.087 32.3 241.5

D 0.50 740 0.001 1.0 7.5

D 0.75 765 0.003 2.3 17.6

D 1 290 0.005 1.6 11.8

D 1.25 175 0.009 1.5 11.2

D 1.5 110 0.012 1.3 10.1

D 2 150 0.022 3.3 24.5

D 3 50 0.049 2.5 18.4

E 0.50 725 0.001 1.0 7.4

E 0.75 310 0.003 1.0 7.1

E 1 260 0.005 1.4 10.6

E 1.25 60 0.009 0.5 3.8

E 1.5 70 0.012 0.9 6.4

E 2 100 0.022 2.2 16.3

E 2.5 55 0.034 1.9 14.0

E 3 60 0.049 2.9 22.0

F 0.75 350 0.003 1.1 8.0 HEATING PLANT PIPING.

F 1 80 0.005 0.4 3.3 AHU‐1 BRANCH PIPING.

F 1.25 100 0.009 0.9 6.4 AHU‐3 & 8 BRANCH PIPING.

F 1.25 160 0.009 1.4 10.2 HEATING PLANT PIPING.

F 1.5 130 0.012 1.6 11.9 AHU‐6 BRANCH PIPING.

VOLUME

VAV REHEAT AND FIN TUBE PIPING.

VAV REHEAT AND FIN TUBE PIPING.

VAV REHEAT AND FIN TUBE PIPING.

GENERAL NOTE: ALL FINAL PIPE LENGTHS INCLUDE SUPPLY AND RETURN PIPING AND ESTIMATED VERTICAL

RISERS.

VAV REHEAT AND FIN TUBE PIPING.

VAV REHEAT AND FIN TUBE PIPING.

APPENDIX A

BUILDING AREA PIPE SIZE LENGTH (FT) AREA (FT2) CUBIC FEET GALLONS NOTES

F 2.5 140 0.034 4.8 35.7 HEATING PLANT PIPING.

F 3 100 0.049 4.9 36.7 HEATING PLANT PIPING.

F 4 380 0.087 33.2 248.0 HEATING PLANT PIPING.

F 6 250 0.196 49.1 367.2 HEATING PLANT PIPING.

G 0.50 670 0.001 0.9 6.8

G 0.75 1200 0.003 3.7 27.5

G 1 175 0.005 1.0 7.1

G 1.25 260 0.009 2.2 16.6

G 1.5 210 0.012 2.6 19.3

G 2 290 0.022 6.3 47.3

G 2.5 120 0.034 4.1 30.6

G 3 150 0.049 7.4 55.1

H 0.50 420 0.001 0.6 4.3

H 0.75 1075 0.003 3.3 24.7

H 1 400 0.005 2.2 16.3

H 1.25 90 0.009 0.8 5.7

H 1.5 170 0.012 2.1 15.6

H 2 40 0.022 0.9 6.5

J 0.75 800 0.003 2.5 18.4

J 1 1400 0.005 7.6 57.1

J 1.25 170 0.009 1.4 10.8

J 1.5 340 0.012 4.2 31.2

J 2 80 0.022 1.7 13.1

J 2.5 30 0.034 1.0 7.6

J 3 230 0.049 11.3 84.5

J 4 400 0.087 34.9 261.1

K 0.5 125 0.001 0.2 1.3

K 0.75 1470 0.003 4.5 33.7

K 1 280 0.005 1.5 11.4

K 1.25 50 0.009 0.4 3.2

K 1.5 230 0.012 2.8 21.1

K 2 160 0.022 3.5 26.1

K 2.5 0.034 0.0 0.0

K 3 280 0.049 13.7 102.8

365.0

AVERAGE OF ALL VAV, UNIT HEATER,

AND RADIANT PANEL COILS. 365 UNITS

@ 1 GALLON AVG. PER UNIT.

400.0 ALDRICH 125 HP BASIS OF DESIGN.

400.0 ALDRICH 125 HP BASIS OF DESIGN.

400.0 ALDRICH 125 HP BASIS OF DESIGN.

10.0 ESTIMATED

5.0 ESTIMATED

12.0 ESTIMATED

15.0 ESTIMATED

5.0 ESTIMATED

15.0 ESTIMATED

12.0 FROM NEW AH‐7 SUBMITTAL.

8.0 ESTIMATED

BOILER 1

BOILER 1

BOILER 1

AHU‐1 COIL

AHU‐2 COIL

AHU‐3 COIL

AHU‐4 COIL

AHU‐5 COIL

AHU‐6 COIL

VAV REHEAT AND FIN TUBE PIPING.

VAV REHEAT AND FIN TUBE PIPING.

VAV REHEAT AND FIN TUBE PIPING.

VAV REHEAT AND FIN TUBE PIPING.

AHU‐7 COIL

AHU‐8 COIL

VAV, UNIT HEATER, AND RADIANT PANEL COILS

BUILDING AREA PIPE SIZE LENGTH (FT) AREA (FT2) CUBIC FEET GALLONS NOTES

10.0 ESTIMATED

8.0 ESTIMATED

15.0 ESTIMATED

10.0 ESTIMATED

515 FROM ORIGINAL DESIGN SCHEDULE.

464.7

5111.3GRAND TOTAL

EXPANSION TANK

10% MORE FOR MISCELLANEOUS OR ITEMS MISSED

AHU‐9 COIL

RTU‐1

AHU‐10 COIL

AHU‐11 COIL