B01 75H70122R00036 Amendment 01.pdf

PDF 405 KB Posted

Attached to
Replace Heating Plant
Solicitation number
75H70122R00036
Issued by

About this file

This document contains an amendment to a federal solicitation for replacement of a heating plant at a hospital in Pine Ridge, South Dakota. The Indian Health Service is seeking to replace the existing heating plant with three new boilers and associated equipment. Bids are due by June 6, 2022. The amendment provides responses to questions from prospective offerors to clarify requirements. It specifies that the existing heating water system must be drained and refilled with a 30% propylene glycol solution according to specifications. Alternative boiler manufacturers may be proposed subject to meeting design requirements and approval through the material submittal process. The estimated manufacture and delivery lead time must be indicated for any proposed boiler.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

The reason for this amendment is to provide a list of questions/answers.

DES - SEATTLE

701 5th Ave, Suite 1600 Seattle, WA 98104

75H70122R00036

06/06/2022

05/17/2022

129162

Solicitation 75H70122R00036 Amendment 01 Project: Replace Heat Plant– Pine Ridge, SD

QUESTIONS AND RESPONSES

Q1. Can you provide a FAR clause, number, or statement that the bidding contractors can view or lookup in reference to the Buy American Act or requirements for this?

A1. See Section I, FAR 52.225‐9 BUY AMERICAN ‐ CONSTRUCTION MATERIALS (NOV 2021).

Q2. Is there a roofing contractor that would carry or be responsible for the roof warranty for the hospital?

A2. There is no roof warranty above where we are conducting this work.

Q3. Can the maximum small business revenue limit increase to $39.5M?

A3. The NAICS for this procurement is 238220 Plumbing, Heating, and Air‐Conditioning Contractors. Per the Small

Business Administration (SBA), the size limit for this NAICS is set at $16.5M. IHS is unable to change the size limit set by the SBA.

Q4. The drawings and specifications are a little vague or don’t necessarily call out to drain and refill the system with 30% propylene glycol. Please clarify.

A4. Page 7 of the RFP and Attachment J02: Appendix A clearly defines what is required for this part of the project.

The intent and requirement is that the existing heating water system will be completed drained down as a part of the project and the system shall be refilled with a 30% propylene glycol / 70% clean water mix with proper inhibitors and water treatment according to the specification 232113 and 232500 which is part of the final required specifications for the project. Close coordination and scheduling with the hospital leadership staff will be required for this part of the project and the contractor shall plan to work at night and/or on weekends to carry out this part of the project.

Q5. After further site investigation for routing of the 3rd boiler combustion gas flue, it was determined that there was not room in the existing flue gas chase to add a 3rd boiler flue as depicted in the final design drawings. Please clarify.

A5. It was determined that the best solution to this problem may be to route the 3rd boiler 12‐inch combustion gas flue to the existing 12‐inch flue that connected the existing domestic water heaters. It is recommended that the bidding contractors plan to not demolish the existing 12‐inch combustion gas flue that is connected to the domestic water heaters and re‐route and connect it to the newly planned 3rd boiler inside the boiler room.

Q6. Will an alternative boiler manufacturer be accepted?

A6. A specific boiler manufacturer was not specified in the solicitation. Any manufacturer that meets the design requirements and specifications may be accepted. At minimum, the proposed manufacturer and make/model of the boiler should be indicated in Factor 3: Technical Approach, Schedule, and Organization of the offeror’s

Technical Proposal. A boiler that does not meet the requirements of the specifications will not be accepted and the offeror’s technical proposal will be considered ‘Unacceptable’. Offerors shall indicate estimated manufacture and delivery lead time for proposed boiler. Final approval of boiler manufacturer will be provided after award through the material submittal process.