Atch_4_Quick_Studies_PWS_Task_Order_1.pdf
PDF 51 KB Posted
- Attached to
- SDDC/TEA Traffic Engineering Services
- Solicitation number
- HTC711-15-R-D003
About this file
Atch 4 Task Order 0001 PWS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_26_Mar_15.pdf | ||
| 0003.pdf | ||
| 0002.pdf | ||
| Questions_and_Answers_24_Mar_15.pdf | ||
| Amended_Atch_3 _Sample_Task_Order_2.pdf | ||
| Questions_and_Answers_23_Mar_15.pdf | ||
| Amended_Atch_10_CLIN_Structure.docx | DOCX document | |
| 0001.pdf | ||
| Questions_and_Answers_11_Mar_15.docx | DOCX document | |
| Atch_3 _Sample_Task_Order_2.pdf | ||
| HTC711-15-R-D003.pdf | ||
| Atch_10_CLIN_Structure.docx | DOCX document | |
| Atch_8_Labor_Categories.pdf | ||
| Atch_2 _Sample_Task_Order_1.pdf | ||
| Atch_6_PPQ.doc | DOC document | |
| Atch_12_SF1407.pdf | ||
| Atch_5_PP_Reference.docx | DOCX document | |
| Atch_1_IDIQ_PWS_Traffic.pdf | ||
| Atch_11_QASP.pdf | ||
| Attach_9-Labor_Categories_ _Rates.xls | XLS spreadsheet |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HTC711-15-R-D003
Attachment 4
Performance Work Statement
Limited Scope Traffic Engineering Services and Analysis Task Order 0001
6 October 2014
1. OBJECTIVE
This Performance Work Statement (PWS) defines the specific tasks to be performed under the Indefinite Delivery, Indefinite Quantity (IDIQ) contract known as Surface Deployment Distribution Command (SDDC)/Transportation Engineering Agency (TEA) Traffic Engineering Services. The objective of this task order is to solicit engineering services for IDIQ Task 1 – Limited Scope Traffic Engineering Services and Analysis.
2. SCOPE OF WORK
The Contractor shall provide Traffic Engineering Services to SDDCTEA supporting Traffic Engineering Branch requirements in accordance with the details and specifications outlined herein. The contractor shall provide all personnel, management, supervision, equipment, tools, supplies, materials, transportation, and any other items and services necessary to perform the Task 1 – Limited Scope Traffic Engineering Services and Analysis.
3. SPECIFIC TASK: TASK 1 - LIMITED SCOPE TRAFFIC ENGINEERING SERVICES AND
ANALYSIS
3.1. The contractor shall provide approximately eight (8) limited-scope traffic engineering studies totaling 1,200 labor hours of effort per period of performance. Each study may include, but not be limited to, site visit(s), briefings, surveys, safety reviews, analyses, data collection, professional recommendations and development of a study report with Computer Aided Drafting and Design (CADD) exhibits. Examples of typical studies:
Traffic Data Collection; Automatic Traffic Recorder (ATR) and manual Entry Control Facility recommendations Installation technical support Roadside safety assessments Intersection and network capacity analysis Traffic Calming Localized Traffic Impact Study Master Plan review/assistance Traffic signing recommendations Guardrail warrant analysis Traffic Signal warrant analysis
Pedestrian Studies Parking Studies Conceptual CADD based geometric details and concepts Conduct plan reviews of DOD installation projects to include entry gate designs, signing and pavement marking plans, traffic signal designs, safety improvement projects, roadway design, traffic control plans, roadway lighting, and force protection and security designs. Data provided in support of the project may also be analyzed and/or reviewed. This may include traffic impact studies, design calculations, master planning studies, speed studies, and force protection guidelines.
Provide guidance on an as-needed basis to DOD installations as directed by SDDCTEA. Telephone, email and written guidance shall be provided in the general areas of traffic operations and traffic control devices, force protection as it relates to the control of traffic, entry gate design parameters, roadway lighting, and safety.
At the request of SDDCTEA, the contractor may attend meetings that may include DOD agencies, state departments of transportation, federal agencies, or local municipal Government officials. Deliverables may include meeting minutes and tasks.
Assist with Traffic Engineering Workshop material development.
The description of the practices and deliverables for Task 1 are as follows:
Coordinate with the installation Point-of-Contact (POC) to schedule and conduct an on-site in-brief, with installation stakeholders, to review the scope of work, obtain necessary approvals and discuss data collection activities and outcomes.
Calculate future traffic demand projections utilizing Institute of Transportation Engineers (ITE) trip generation analysis, and independent forecasting based on known Base Realignment and Closure (BRAC), Grow the Army, and/or other known re-stationing. All stationing information shall be obtained through interview with the installation POC and through independent research. The traffic forecast design year shall be full build out year of all known improvements.
For studies involving Entry Control Facilities (ECFs), calculate the new lane requirements based on SDDCTEA Pamphlet 55-15, UFC 4-022-01, The Army Standard (AS) for Access Control Points (ACPs), and all other applicable service related requirements, latest versions. Utilize the SMART Decision Evaluator software (available on SDDCTEA’s website) to assist in identifying the existing, short-term, and long-term impacts of security, manpower, automation, and traffic.
For studies involving ECFs, interview the installation force protection and ID check personnel to query additional information concerning the current operations of internal and external access control points.
Provide conceptual scaled drawings of recommendations for new and modified ECFs. When applicable (sight distance triangle requirements, geometric adjustments, striping adjustments, design vehicle accommodations, sidewalks, etc.), provide conceptual scaled drawings of recommendations for intersections and/or roadways that are included as part of this study. This shall include all geometric data used in the roadway alignment, recommended lane configuration, active & passive vehicle barrier placement, striping, signing, environmental constraints, and a statement of feasibility of design. (This is intended to be 11” x 17” foldouts graphically identifying all recommendations - prepared in color to scale with MicroStation CAD software, and overlaid onto an aerial photograph).
Traffic and speed data collection, both manually and with automatic data collectors, shall be collected on a 15-minute period basis. The counting duration shall be subject to the requirements of the specific order.
Provide existing and future intersection capacity and network analysis utilizing HCS, or SYNCHRO, traffic capacity software. Provide a summary of results and recommendations based on Level of Service (LOS), with consideration of traffic flow and safety. Intersection summary shall include discussion of lane group LOS as well as intersection LOS. Analysis shall include queuing analysis for all intersection lane groups to identify congestion.
Road Safety Assessments shall, at a minimum, address the following items:
o Traffic control o Lane configuration o Signing o Striping o Design vehicle accommodation o Operational concerns o Roadside hazards o Improper traffic control devices o Bicycle and pedestrian access o Analysis of most recent five years of crash data, if available.
Categorize short-term and intermediate-term, recommendations Short-term recommendations are improvements that can be executed within six months utilizing normal installation maintenance resources that will provide immediate improvements to capacity, safety, and/or operations. Intermediate-term recommendations will are improvements that can be executed within one to two years and require some planning, design, and repair/construction authority to execute. Typically, intermediate-term recommendations can be implemented in stages with minimal impacts.
Provide construction and preliminary engineering cost estimates for all recommendations.
Provide a photographic record of all deficiencies and recommendations, where applicable. Locate them in the report.
Perform desktop analysis of specific safety or traffic engineering related roadway issues based on information and data provided by others.
Historical information on Quick Studies is provided in Attachment A.
3.2. This task requires responsiveness to Agency needs that arise from high priority issues. These projects require a 5 day response time as per the Deliverables Table below.
4. DELIVERABLES
4.1 All products, studies and analysis that are developed or provided under this PWS are the sole property of the Government. The contractor shall not use, disclose, transfer, convert, or otherwise appropriate any technical data, processes, studies, or engineering analysis developed during performance of this PWS, unless written permission from the Contracting Officer is obtained. IAW DFARS 252.227-7013 and DFARS 252.227-7014, the Government obtains under this contract "unlimited rights" to all data, documentation, reports, briefings, publications, and similar non-commercial data developed exclusively at Government expense and delivered to the Government under this contract.
4.2 All deliverables shall be made electronically via email to the COR. If a delivery is submitted via email and the size or the firewall prevents its delivery, the Contractor shall provide a Secure File Transfer Protocol site that allows the Government to download the deliverable. If a site is not available or not feasible, the Government will make one available to the Contractor. In case no sites are available, the Contractor shall deliver via compact disk / digital videodisk (CD/DVD). The CD/DVD must be properly labeled to identify the content to include classification, version number, and date. Deliverables shall be identified on each individual task order. The Deliverables Table is for informational purposes only and does not constitute all deliverables that may be on individual task orders.
DELIVERABLES TABLE
TASK 1 – LIMITED SCOPE TRAFFIC ENGINEERING SERVICES AND ANALYSIS
Asserted Rights
Deliverable Delivery Schedule
(days are calendar) Medium/Format
Copy
* Submittal Requirements
Task Order Estimate and
Schedule
5 working days after scoping order with TEA Project
Engineer E-mail 1 COR
Unlimited
2 calendar days allowed for travel to/from work site - - - - - -
3 weeks for analysis and document preparation, following site visit and data collection
Draft Report and Out-Brief Meeting
1 week for wrap up, draft report, out-briefing as necessary.
Electronic.pdf / Contractor Format (email soft copy)
COR & Installation
(Note: Deliverables to the installation are to be provided after review & approval by SDDCTEA, but prior to the Out-brief Mtg.)
Unlimited
Final Report 1 week for completion of final report.
Electronic.pdf / Contractor Format (email soft copy)
COR & Installation (Note: Deliverables to SDDCTEA, the installation, & higher HQ, if required, are to be provided concurrently.)
Unlimited
* The higher HQ agency for submittal to be determined in coordination with SDDCTEA.
** File naming convention for electronic submittals shall have the following format:
Installation Name, State_Final/Draft Study Type_YYYYMMDD (Example: Vance AFB, OK_Final Parking and Safety Study_20120730)
*** The report and the appendices shall all be contained within one (1) PDF file for the electronic submittal of the Final Report.
Also, all working/raw data files such as drawing files, analyses, calculations, etc., shall be included with submittal of the Final Report.
5. SERVICE DELIVERY SUMMARY
5.1. The Service Delivery Summary (SDS) represents the most important contract objectives that, when met, will ensure contract performance is satisfactory. Although not all PWS requirements are listed in the SDS, the Contractor is fully expected to comply with all requirements in the PWS.
Performance Objective Performance Threshold Performance Threshold Final Report 100% compliance rate Inspection Review
6. INSPECTION AND ACCEPTANCE.
6.1. A deliverable is a specific measureable, tangible, and verifiable activity, outcome, result, item, or product that the Contractor shall provide and that will require formal Government acceptance and approval. The Government will review, assess, and provide comment, as required.
6.2. Unless otherwise specified within an individual task order, final inspection and acceptance of all work performed, reports, or other deliverables shall be performed at the place of delivery. The Contracting Officer Representative (COR) will notify the Contractor of deliverable acceptance or provide comments in writing.
7. GENERAL INFORMATION
7.1. PLACE OF PERFORMANCE: The primary place of performance varies with respect to each order. In general, most orders involve an on-site meeting and data collection activities at the installation, with analysis and report preparation at the contractor’s place of business.
7.2. PERIOD OF PERFORMANCE : The period of performance for this contract is:
Base: 1 August 15 to 31 July 16 1st Option Period: 1 August 16 to 31 July 17 2 nd Option Period: 1 August 17 to 31 July 18
7.3. TRAVEL: The contractor shall be available to work CONUS and OCOUS at military installations. Contractor personnel may be required to travel within the U.S. and OCONUS to perform this task. The Government shall reimburse the contractor for travel expenses subject to the Federal Acquisition Regulation (FAR) and Federal Travel Regulation (FTR). The Government shall not reimburse local travel and related expenses to the contractor daily travel to or from the place of performance.
ATTACHMENT A: Historical Information
The following studies are examples of actual projects completed under a previous contract. They are provided herein to assist the Contractor in understanding the requirements of this performance work statement.
Air National Guard Entry Control Facility Study - 225 Labor Hour effort
Conduct an informal in-brief meeting with the POC. Out-brief with the installation POC via web-meeting or teleconference.
Collect and document the weekday traffic as well as the weekend drill traffic into the facility.
Collect and document the peak-hour traffic volumes into the installation for the weekday traffic as well as the weekend traffic.
Collect and document the pedestrian traffic into the installation.
Locate and size the future parking lots for the weekday users and weekend users; i.e., secure and non-secure lots.
Calculate the ECF lane requirements.
Provide conceptual scaled drawings of modifications recommended.
Provide a photographic record of all deficiencies and recommendations, where applicable.
Summarize data in an abbreviated report format. Reports will be delivered electronically.
Army Installation Speed Study (Residential/School) - 100 Labor Hour effort
Conduct an informal in-brief meeting with the POC. Out-brief with the installation POC via web-meeting or teleconference.
For both areas, validate that the current posted speed.
Conduct a speed study to determine the adequacy of the current posted speed, as well as the
85th percentile speed.
Provide recommendations on the proper speed limit posting. Ten (10) speed study locations are required for each study area, for a total of 20. Locations to be determined in coordination with the installation POC.
Collect and document the 24-hour ADT of the roadway where speed data is obtained.
Verify the need for and appropriateness of pedestrian traffic calming measures in both study areas. Provide specific recommendations.
Summarize data in an abbreviated report format. Reports will be delivered electronically.
Installation Data Collection – 105 Labor Hour effort
Conduct 10 Automatic Traffic Recorder [ATR] counts in 5 different locations identified in
Attachment #1. Three day duration, including Saturday.
The counts shall be summarized at 15-minute intervals and the results recorded in machine readable format.
Installation Roadway Corridor Safety Study – 200 Labor Hour effort
Conduct an informal in-brief meeting with the POC to collect information and data; and to determine what is occurring with future growth. Out-brief with the installation POC via web-meeting or teleconference.
Collect and document the 24-hour ADT of the roadway.
Determine specific signage requirements along route with sign type and exact location to be given.
Field verify/determine guardrail requirements along route with specific lengths, locations, and offsets to be given.
Conduct a Roadway Safety Assessment (RSA). Provide remedial recommendations. The
RSA shall inventory and, at a minimum, address the following:
Traffic control Lane configuration Signing Striping Design vehicle accommodation Operational concerns Roadside hazards Clear zone Improper traffic control devices Analysis of the most recent five years of crash data
Determine the roadway shoulder requirement based on the roadway classification and traffic volumes.
Conduct a speed study to determine the adequacy of the current posted speed, as well as the 85th percentile speed.
Field verify the stopping sight distance (SSD) and passing sight distance (PSD) of all curves.
Verify the roadway design for current and future capacity.
Summarize data in an abbreviated report format, essentially an Executive Summary.
Installation Entry Control Data Collection – 250 Labor Hour effort
Collect 24 hour traffic and operational data for 5 Entry Control Points as per the process outlined in SDDCTEA Pamphlet 55-15 using ATR or manual methods
Collect manual intersection turning movements for four intersections adjacent to ECF’s Identify ECF roadside safety and signing deficiencies Compile raw data and submit.
File details come from the government source that posted it. Updated .