PQQ039 SF1442.doc
To access pages 1 & 2 of Standard Form (SF) 1442, double-click on the above icon.
After obtaining the SF 1442, close the document and continue scrolling down from this point to obtain the remainder of the Invitation For Bid (IFB).
YOU MUST RETURN THE FOLLOWING. FAILURE TO DO SO
MAY DEEM YOUR BID NON-RESPONSIVE.
A. ONE (1) COMPLETE COPY OF THE STANDARD FORM 1442
(SOLICITATION OFFER AND AWARD) AND ALL AMENDMENTS.
B. SECTION B (SCHEDULE OF PRICES).
C. SECTION J (CONTRACTOR’S RESPONSIBILITY
QUESTIONNAIRE).
D. SECTION K (REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFEROR’S).
E. SECTION L (BID BOND (STANDARD FORM 24) IN THE AMOUNT
OF $2,000.
PLEASE MAIL YOUR BID TO THE FOLLOWING ADDRESS:
CONTRACTING OFFICER
Attn: Lilian Librodo
IFB HSCG88-16-B-PQQ039
USCG Civil Engineering Unit 1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203
Please do not call to inquire about the status of your bid, as this information will not be released.
Invitation For Bid Number: HSCG88-16-B-PQQ039
NOTICE FOR FILING AGENCY PROTESTS
United States Coast Guard Ombudsman Program
It is the policy of the Coast Guard to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time-consuming litigation. OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the General Accounting Office (GAO).
Interested parties are encouraged to seek resolution of their concerns within USCG as an Alternative Dispute Resolution (ADR) forum, rather than filing a protest with the GAO or some external forum. Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the Contracting Officer or Ombudsman.
Informal forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer. If the Contracting Officer is unable to satisfy the concerns, the interested parties are encouraged to contact the Coast U.S. Coast Guard Ombudsman for Agency Protests.
Under this informal process, the agency is not required to suspend contract award performance.
Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions. If the protester’s concerns are unresolved, an independent review is available by the Ombudsman. The protester may file a formal agency protest either to the Contracting Officer or as an alternative to that, the Ombudsman under the OPAP program.
Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth at FAR 33.103(d)(2). If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. To be timely, protests must be filed within the period specified in FAR 33.103(e). Formal protests filed under the OPAP program should be submitted electronically to OPAP@uscg.mil and the Contracting Officer or by hand delivery to the Contracting Officer.
Election of Forum. After an interested party protests a Coast Guard procurement to the Contracting Officer or the Ombudsman, and while the protest is pending, the protestor agrees not to file a protest with the GAO or other external forum. If the protest is file with an external forum, the agency protest will be dismissed.
The Ombudsman Hotline telephone number is 202.372.3695.
SECTION B
SCHEDUL OF PRICES
B.1 ATTACHMENTS
The following listed attachments are a part of this solicitation and any resulting contract:
1. Schedule of Prices, (Base Year and Option Years 1, 2, 3, and 4), Items 000001 through 492004
ITEM
NO.
DESCRIPTION EST.
QTY UNIT UNIT PRICE EST TOTAL
000001
Base Year: Provide all labor, materials, equipment, transportation, and supervision for the Term Pile contract in the Columbia River, WA and OR and the Snake River, WA and ID for US Coast Guard for the Base Period from April 1, 2016 to March 31, 2017.
010000 IMPROPER CHARACTERISTIC TASK ORDER
011000 MOBILIZATION / DEMOBILIZATION:
011001 Mobilize for Improper Characteristic Task Order in Area No. 1. 1 per Task Order.
1 EA
011002 Demobilize for Improper Characteristic Task Order in Area No. 1. 1 Per Task Order.
1 EA
011003 Mobilize for Improper Characteristic Task Order in Area No. 2. 1 Per Task Order.
1 EA
011004 Demobilize for Improper Characteristic Task Order in Area No. 2. 1 Per Task Order.
1 EA
011005 Mobilize for Improper Characteristic Task Order in Area No. 3. 1 Per Task Order.
1 EA
011006 Demobilize for Improper Characteristic Task Order in Area No. 3. 1 Per Task Order.
1 EA
011007
No. 4. 1 Per Task Order.
1 EA
011008 Demobilize for Improper Characteristic Task Order in Area No. 4. 1 Per Task Order.
1 EA
011009 Mobilize for Improper Characteristic Task Order in Area No. 5. 1 Per Task Order.
1 EA
011010 Demobilize for Improper Characteristic Task Order in Area No. 5. 1 Per Task Order.
1 EA
011011 Mobilize for Improper Characteristic Task Order in Area No. 6. 1 Per Task Order.
1 EA
011012 Demobilize for Improper Characteristic Task Order in Area No. 6. 1 Per Task Order.
1 EA
011013
Mobilize and Demobilize from one site in Area No. 1 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
011014
Mobilize and Demobilize from one site in Area No. 2 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
011015
Mobilize and Demobilize from one site in Area No. 3 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
011016
Mobilize and Demobilize from one site in Area No. 4 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
011017
Mobilize and Demobilize from one site in Area No.5 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
011018
Mobilize and Demobilize from one site in Area No. 6 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
012000 REMOVALS – IN WATER CONSTRUCTION
012001
Remove damaged single (1) steel pipe pile structure including platform assembly, ladder extensions.
Remove and return all ATON hardware, platform, and ladders if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 01 and ATON
STD 02.
1 EA
012002
Remove damaged three (3) steel pipe pile structure including platform assembly, ladder extensions.
Remove and return all ATON hardware, platform, and ladders if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 03 and ATON STD 04.
1 EA
012003
Remove damaged four (4) steel pipe pile structure including pile platform assembly, ladder extensions and sectional lower assembly. Remove return and all ATON hardware, pile platform, ladders and sectional tower parts if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 06 and ATON STD 08.
1 EA
012004
Remove damaged wood pile channel marking structure consisting of one (1) or multiple driven pile members, including platform assembly, ladders and bindings.
Remove and return all ATON hardware and metal platform, if used and reusable. Contractor shall dispose of all other materials.
1 EA
012005
Remove damaged wood pile range structure consisting of multiple driven pile members, including platform assembly, ladders and bindings. Remove and return all ATON hardware. Contractor shall dispose of all other materials.
1 EA
012006
Remove damaged wood pile range structure consisting of multiple driven pile members a platform assembly, sectional steel tower, ladders and bindings. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials.
012007
Remove pedestal assembly from either a break wall or submerged obstruction, consisting of a steel pipe and platform. Remove and return all ATON hardware.
Contractor shall dispose of all other materials.
1 EA
012008 Remove and dispose of one NON ATON piling using vibratory method
012500 Removals - Shore Construction
012501
Remove damaged wood pile structure consisting of driven pile members a platform assembly, sectional steel tower, ladders and bindings. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials.
1 EA
012502
Remove sectional tower assembly and disassemble.
Return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials. See drawings ATON STD 08.
1 EA
012503 Remove concrete foundation up to 6 Cubic Yards.
Contractor shall dispose of all other materials.
1 EA
012504 Remove an additional 1 Cubic Yard of concrete foundation. Contractor shall dispose of all other materials.
1 CY
013000 INSTALLATIONS
013100 IN WATER CONSTRUCTION - INSTALLATIONS
013101
Install single-pile steel beacon structure including single steel pile, install platform, platform ladder, and up to 3 day boards in accordance with drawing ATON STD 01, ATON STD 09, ATON STD 10 and ATON STD 13.
Remove and return temporary buoy.
1 EA
013102
Install single-pile steel range structure including single steel pile, install platform, platform ladder, range board frame, range board frame support bracket, and range board. In accordance with drawing ATON STD 02, ATON STD 10 and ATON STD 12. Remove and return temporary buoy.
013103
Install three-pile steel beacon structure including three steel piles, king pile, install platform, install platform ladder, and install up to 3 day boards. In accordance with drawing ATON STD 03, ATON STD 09, ATON STD 10 and ATON STD 13. Remove and return temporary buoy.
1 EA
013104
Install three-pile steel range structure, including: three steel piles, king pile, install platform, platform ladder, range board frame, range board frame support brackets, and range board. In accordance with drawing ATON STD 04, ATON STD 10 and ATON STD 12. Remove and return temporary buoy.
1 EA
013105
Install four-pile steel structure including four steel piles, install platform, platform ladder/safety rail, and fiberglass grating, may include installing up to 3 day boards. In accordance with drawing ATON STD 06. Remove and return temporary buoy.
1 EA
013106
Assemble and install on a four-pile steel structure a sectional tower either a 5 feet, 10 feet or 15 feet tall including top platform with fiberglass grating. In accordance with drawing ATON STD 06 and ATON STD 08.
1 EA
013107
Assemble and install on a four-pile steel structure an additional 5 foot, 10 foot or 15 foot sectional tower in accordance with drawing ATON STD 06 and ATON STD 08.
1 EA
013108 Install a concrete pedestal foundation on a break wall.
Using up to 5 Cubic Yards of concrete in accordance with drawing ATON STD 05.
1 EA
013109 Install an additional 1 cubic Yard of concrete for a pedestal foundation on a break wall in accordance with drawing ATON STD 05.
1 CY
013110
Install a submerged obstruction concrete foundation.
Includes one 6 foot section of concrete pipe, drilling, anchoring, grouting, rebar and concrete fill. In accordance with drawing ATON STD 05 .
1 EA
013111 Install an additional 1 foot of submerged obstruction concrete foundation. Includes concrete pipe, rebar and concrete fill. In accordance with drawing ATON STD 05.
013112
Install a pedestal beacon structure on a new or existing concrete breakwater foundation. Includes installing pedestal, platform, one ladder extension and brackets, drilling and anchoring (if required), leveling and grouting, and installing up to 3 day boards. In accordance with drawing ATON STD 05, ATON STD 09, ATON STD 10 and ATON STD 13.
1 EA
013113
Install a pedestal range structure on a new or existing concrete breakwater foundation or submerged obstruction foundation. Includes installing pedestal, platform, one ladder extension and brackets, drilling and anchoring (if required), leveling and grouting, and installing range board frame support bracket, and range board. In accordance with drawing ATON STD 05, ATON STD 10 and ATON STD 12.
1 EA
013114
Install on any type of steel pile structure, one each, 7 foot ladder extension including bolting ladder extension brackets to ladder and attaching ladder extension assembly to the structure with “U” bolts. In accordance with drawings ATON STD 01, ATON STD 02,ATON
STD 03, ATON STD 04, ATON STD 05, ATON STD 06,
ATON STD 09, ATON STD 10 and ATON STD 11.
1 EA
013115 Install one (1) NON ATON steel pile using the vibratory method
013500 SHORE CONSTRUCTION - INSTALLATION
013501 Install four “H” piles to receive a sectional tower assembly. In accordance with drawing ATON STD 07.
1 EA
013502 Install a concrete foundation to receive a sectional tower assembly. In accordance with drawing ATON STD 07.
1 EA
013503 Install a concrete foundation as a pile cap to receive a sectional tower assembly. In accordance with drawing
ATON STD 07.
1 EA
013504 Install a concrete pedestal foundation on a land location.
As per drawing ATON STD 05.
1 EA
013505
Install on any type of steel pile structure, one each, 7 foot ladder extension including bolting ladder extension brackets to ladder and attaching ladder extension assembly to the structure with “U” bolts. In accordance with drawings ATON STD 01, ATON STD 02, ATON
STD 03, ATON STD 04, ATON STD 05 ATON STD 06,
ATON STD 09, ATON STD 10 and ATON STD 11.
013506 Provide and install a chain link fence around a shore structure 10 foot by 10 foot including gate, razor wire
1 EA
013507 Provide and install an additional 4 linier feet of fence.
020000 EMERGENCY TASK ORDERS
021000 EMERGENCY MOBILIZATION / DEMOBILIZATION:
021001 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 1. 1 per Task Order.
1 EA
021002 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 2. 1 Per Task Order.
1 EA
021003 Mobilize and Demobilize or EMERGENCY Task Order in Area No. 3. 1 Per Task Order.
1 EA
021004 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 4. 1 per Task Order.
1 EA
021005 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 5. 1 Per Task Order.
1 EA
021006 Mobilize and Demobilize or EMERGENCY Task Order in Area No. 6. 1 Per Task Order.
022000 REMOVALS
022001 including platform assembly, ladder extensions under EMERGENCY Task Order. Remove and return all ATON hardware, platform, and ladders if reusable.
Contractor shall dispose of all other materials. See drawings ATON STD 01 and ATON STD 02.
1 EA
022002
Remove damaged three (3) steel pipe pile structure including platform assembly, ladder extensions under EMERGENCY Task Order. Remove and return all ATON hardware, platform, and ladders if reusable.
Contractor shall dispose of all other materials. See drawings ATON STD 03 and ATON STD 04.
1 EA
022003
Remove damaged four (4) steel pipe pile structure including pile platform assembly, ladder extensions and sectional lower assembly under EMERGENCY Task Order. Remove return and all ATON hardware, pile platform, ladders and sectional tower parts if reusable.
Contractor shall dispose of all other materials.
022004
Remove damaged wood pile channel marking structure consisting of multiple pile members, platform assembly, ladders and bindings under EMERGENCY Task Order.
Remove and return all ATON hardware and metal platform, if used and reusable. Contractor shall dispose of all other materials.
1 EA
022005
Remove damaged wood pile range structure consisting of multiple driven pile members a platform assembly, sectional steel tower, ladders and bindings under EMERGENCY Task Order. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials.
030000 TRANSIT COSTS
030001 A. Transit from one in water work location to another in water work location on the same Task Order per nautical mile (NM).
1 NM
040000 REPAIRS
040001
Replace a beacon structure platform either 5’x5’ or 7’x7’ on either a one (1) pile structure, a three (3) pile structure or a pedestal structure and install up to 3 day boards. In accordance with drawing ATON STD 01, ATON STD 03, ATON STD 05, ATON STD 11, ATON
STD 12, ATON STD 13 and ATON STD 14.
1 EA
040002
Replace a range structure platform either 5’x5’ or 7’x7’ on either a one (1) pile structure, a three (3) pile structure or a pedestal structure. Including new range board frame and new range board. In accordance with drawing ATON STD 02, ATON STD 04, ATON STD 05, ATON STD 11, ATON STD 12 and ATON STD 14.
1 EA
040003
Replace one damaged ladder including ladder brackets on either a one (1) pile structure, a three (3) steel pile structure a pedestal structure or a four (4) pile structure, In accordance with drawing ATON STD 01, ATON STD
02, ATON STD 03, ATON STD 04, ATON STD 05,
ATON STD 06, and ATON STD 11.
050000 MATERIALS
050001 Provide 40 foot length of 18 inch diameter 3/8 inch wall strait seam steel pipe, priced per linear foot (LF).
1 LF
050002 Perform one (1) weld to join two (2) pieces of 18” diameter pile pipe together.
050003
Provide one fabricated pedestal base. To include all flat steel and welding. In accordance with drawing ATON STD 05. NOTE: Steel pipe will be cost out using line item “050001”.
1 EA
050004 Provide galvanizing of one pedestal base including base plate and 10 feet of pipe. In accordance with drawing
ATON STD 05.
1 EA
050005
Provide galvanizing of 10 feet of pipe. In accordance with drawings ATON STD 01. ATON STD 02, ATON STD 03, ATON STD 04, ATON STD 05 and ATON STD
06. 1 LFT
050006 Provide one fabricated 5’’x5’ platform in accordance with drawing ATON STD 09.
1 EA
050007 Provide one fabricated 7’x7’ platform in accordance with drawing ATON STD 10.
1 EA
050008 Provide one fabricated 7 foot ladder extension in accordance with drawing ATON STD 11.
1 EA
050009
Provide 1 set, consisting of 2 each brackets, fabricated ladder extension brackets; of either LEB 5x5-1, LEB 5x5-3, LEB 7x7-1, LEB 7x7-3 or LEB 10x10-1. Includes bracket, hoop and fasteners. In accordance with drawing ATON STD 11.
1 Set
050010 Provide a fabricated 10 foot square 4 pile platform. In accordance with drawing ATON STD 06.
1 EA
050011
Provide a fabricated unassembled 5 foot section of sectional tower. Includes tower members, platform assembly, and 4 each tower base column connectors and all fasteners. In accordance with drawing ATON
STD 08.
1 EA
050012
Provide a fabricated unassembled 10 foot section of sectional tower. Includes tower members, platform assembly, and 4 each tower base column connectors and all fasteners. In accordance with drawing ATON
STD 08.
1 EA
050013
Provide a fabricated unassembled 15 foot section of sectional tower. Includes tower members, platform assembly, and 4 each tower base column connectors and all fasteners. In accordance with drawing ATON
STD 08.
050014
Provide a fabricated unassembled 5 foot section of sectional tower, includes 4 each splice plates and all fasteners. (Does not include platform assy. or tower base column connectors) In accordance with drawing
ATON STD 08.
1 EA
050015
Provide a fabricated unassembled 10 foot section of sectional tower, includes 4 each splice plates and all fasteners. (Does not include platform assy. or tower base column connectors) In accordance with drawing
ATON STD 10.
1 EA
050016
Provide a fabricated unassembled 15 foot section of sectional tower, includes 4 each splice plates and all fasteners. (Does not include platform assy. or tower base column connectors) In accordance with drawing
ATON STD 10.
1 EA
050017 Provide a fabricated set of 4 each Tower Base Column Connector Bracket, including all fasteners. As per drawing ATON STD 08.
1 SET
050018 Provide a fabricated set of 4 each splice brackets, including all fasteners. As per drawing ATON STD 08.
1 SET
050019 Provide a fabricated 8KRW (8’x16’) Range Board Frame, including all fasteners. In accordance with drawing ATON STD 12.
1 EA
050020 Provide a fabricated 6KRW (6’x12’) Range Board Frame, including all fasteners. In accordance with drawing ATON STD 12.
1 EA
050021 Provide a fabricated 4KRW (4’x8’) Range Board Frame, including all fasteners. In accordance with drawing
ATON STD 12.
1 EA
050022 Provide a fabricated 3KRW (3’x6’) Range Board Frame, including all fasteners. In accordance with drawing
ATON STD 12.
1 EA
050023 Provide a manufactured cable type Safety Climb Device.
In accordance with drawing ATON STD 14.
060000 RETURN OF GOVERNMENT MATERIALS
060001
At the completion of a Task Order return all government materials; ATON equipment, batteries (must be double bagged in plastic), usable platforms, ladders and brackets, and temp buoys to the ANT responsible for the structures built under this Task order.
070000 AS-BUILT PHOTOGRAPHS
070001
Take photographs of new structure from 3 positions 90 degrees apart of completed new construction. Provide 3 CD’s of photographs. (Photos of one structure on 3 each CD’s will be used for evaluation purposes only.)
NOTE: All photos taken under one Task Order may be combined on one CD.)
080000 DIVING SERVICES
080001
Diving services to search a 75 yard radius of last known position of old structure, attending retrieval process for found structure and cut of any metal pile extending above the mud line.
1 EA
080002 Diving services to investigate underwater condition of underwater portion of structure. Provide written report of dive findings.
090000 FIELD ENGINEERING
090001 Perform a geodetic survey as per the requirements of VERTICAL and HORIZONTAL methods.
091000 MARINE MAMMAL MONITORING
091001
Geographical Area 1 (Snake River from Lower Monumental Dam to Lewiston, ID): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
091002
Geographical Area 2 (Columbia River from McNary Dam to Richland, WA and Snake River up to Lower Monumental Dam): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
091003
Geographical Area 3 (Columbia River from John Day Dam to McNary Dam): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
091004
Geographical Area 4 (Columbia River from Bonneville Dam to Joh Day Dam): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
091005
Geographical Area 5 (Columbia River from Lewis and Clark Bridge to Bonneville Dam and Willamette River up to, and including, Multnomah Channel and Wilsonville, OR): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
091006
Geographical Area 6 (Columbia River from Lewis and Clark Bridge to Pacific Ocean including structures within a 10NM radius west of western most point of northern entrance jetty)): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
091007
Onsite Monitoring Services/per day: Includes labor, equipment and supplies for the biologist and team to perform monitoring services on the ATON site for one 8-hour day. Applies to Geographical Areas 1, 2, 3, 4, 5, and 6.
1 DY
091008
Standby for Marine Mammal(s): Includes labor and equipment for the construction crew to standby while waiting for a marine mammal to vacate the construction area.
1 HR
092000 EELGRASS SURVEY
092001
Geographical Area 1 (South of Seaside, OR to the waters north of Yaquina Head, OR, including inlets, bays, and waterways.): Mobilization of a boat, operator and an eelgrass monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
092002
Geographical Area 2 (South of Yaquina Head, OR to the waters north of Coquille Point, OR, including all inlets, bays, and waterways.): Mobilization of a boat, operator and an eelgrass monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
092003
Geographical Area 3 (South of Coquille Point, OR to the waters north of the California-Oregon border, including all inlets, bays, and waterways.): Mobilization of a boat, operator and an eelgrass monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
092004
Onsite Monitoring Services/per day: Includes labor, equipment and supplies for the biologist and team to perform eelgrass surveys on the ATON site for one 8-hour day. Applies to Geographical Areas 1,2 and 3.
1 DY
Total Base Year $ ________________________
100001
Option Year 1: Provide all labor, materials, equipment, transportation, and supervision for the Term Pile contract in the Columbia River, WA and OR and the
Base Period from April 1, 2017 to March 31, 2018.
110000 IMPROPER CHARACTERISTIC TASK ORDER
111000 MOBILIZATION / DEMOBILIZATION:
111001
No. 1. 1 per Task Order.
1 EA
111002 Demobilize for Improper Characteristic Task Order in Area No. 1. 1 Per Task Order.
1 EA
111003 Mobilize for Improper Characteristic Task Order in Area No. 2. 1 Per Task Order.
1 EA
111004 Demobilize for Improper Characteristic Task Order in Area No. 2. 1 Per Task Order.
1 EA
111005 Mobilize for Improper Characteristic Task Order in Area No. 3. 1 Per Task Order.
1 EA
111006 Demobilize for Improper Characteristic Task Order in Area No. 3. 1 Per Task Order.
1 EA
111007 Mobilize for Improper Characteristic Task Order in Area No. 4. 1 Per Task Order.
1 EA
111008 Demobilize for Improper Characteristic Task Order in Area No. 4. 1 Per Task Order.
1 EA
111009 Mobilize for Improper Characteristic Task Order in Area No. 5. 1 Per Task Order.
111010 Demobilize for Improper Characteristic Task Order in Area No. 5. 1 Per Task Order.
1 EA
111011 Mobilize for Improper Characteristic Task Order in Area No. 6. 1 Per Task Order.
1 EA
111012 Demobilize for Improper Characteristic Task Order in Area No. 6. 1 Per Task Order.
1 EA
111013
Mobilize and Demobilize from one site in Area No. 1 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
111014
Mobilize and Demobilize from one site in Area No. 2 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
111015
Mobilize and Demobilize from one site in Area No. 3 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
111016
Mobilize and Demobilize from one site in Area No. 4 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
111017
Mobilize and Demobilize from one site in Area No.5 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
111018
Mobilize and Demobilize from one site in Area No. 6 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
112000 REMOVALS – IN WATER CONSTRUCTION
112001 including platform assembly, ladder extensions.
Remove and return all ATON hardware, platform, and ladders if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 01 and ATON
STD 02.
112002
Remove damaged three (3) steel pipe pile structure including platform assembly, ladder extensions.
Remove and return all ATON hardware, platform, and ladders if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 03 and ATON STD 04.
1 EA
112003
Remove damaged four (4) steel pipe pile structure including pile platform assembly, ladder extensions and sectional lower assembly. Remove return and all ATON hardware, pile platform, ladders and sectional tower parts if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 06 and ATON STD 08.
1 EA
112004
Remove damaged wood pile channel marking structure consisting of one (1) or multiple driven pile members, including platform assembly, ladders and bindings.
Remove and return all ATON hardware and metal platform, if used and reusable. Contractor shall dispose of all other materials.
1 EA
112005
Remove damaged wood pile range structure consisting of multiple driven pile members, including platform assembly, ladders and bindings. Remove and return all ATON hardware. Contractor shall dispose of all other materials.
1 EA
112006
Remove damaged wood pile range structure consisting of multiple driven pile members a platform assembly, sectional steel tower, ladders and bindings. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials.
1 EA
112007
Remove pedestal assembly from either a break wall or submerged obstruction, consisting of a steel pipe and platform. Remove and return all ATON hardware.
Contractor shall dispose of all other materials.
1 EA
112008 Remove and dispose of one NON ATON piling using vibratory method
112500 Removals - Shore Construction
112501 driven pile members a platform assembly, sectional steel tower, ladders and bindings. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other
112502
Remove sectional tower assembly and disassemble.
Return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials. See drawings ATON STD 08.
1 EA
112503 Remove concrete foundation up to 6 Cubic Yards.
Contractor shall dispose of all other materials.
1 EA
112504 Remove an additional 1 Cubic Yard of concrete foundation. Contractor shall dispose of all other materials.
113000 INSTALLATIONS
113100 IN WATER CONSTRUCTION - INSTALLATIONS
113101 steel pile, install platform, platform ladder, and up to 3 day boards in accordance with drawing ATON STD 01, ATON STD 09, ATON STD 10 and ATON STD 13.
Remove and return temporary buoy.
1 EA
113102
Install single-pile steel range structure including single steel pile, install platform, platform ladder, range board frame, range board frame support bracket, and range board. In accordance with drawing ATON STD 02, ATON STD 10 and ATON STD 12. Remove and return temporary buoy.
1 EA
113103
Install three-pile steel beacon structure including three steel piles, king pile, install platform, install platform ladder, and install up to 3 day boards. In accordance with drawing ATON STD 03, ATON STD 09, ATON STD 10 and ATON STD 13. Remove and return temporary buoy.
1 EA
113104
Install three-pile steel range structure, including: three steel piles, king pile, install platform, platform ladder, range board frame, range board frame support brackets, and range board. In accordance with drawing ATON STD 04, ATON STD 10 and ATON STD 12. Remove and return temporary buoy.
1 EA
113105
Install four-pile steel structure including four steel piles, install platform, platform ladder/safety rail, and fiberglass grating, may include installing up to 3 day boards. In accordance with drawing ATON STD 06. Remove and return temporary buoy.
113106
Assemble and install on a four-pile steel structure a sectional tower either a 5 feet, 10 feet or 15 feet tall including top platform with fiberglass grating. In accordance with drawing ATON STD 06 and ATON STD 08.
1 EA
113107
Assemble and install on a four-pile steel structure an additional 5 foot, 10 foot or 15 foot sectional tower in accordance with drawing ATON STD 06 and ATON STD 08.
1 EA
113108 Install a concrete pedestal foundation on a break wall.
Using up to 5 Cubic Yards of concrete in accordance with drawing ATON STD 05.
1 EA
113109 Install an additional 1 cubic Yard of concrete for a pedestal foundation on a break wall in accordance with drawing ATON STD 05.
1 CY
113110
Install a submerged obstruction concrete foundation.
Includes one 6 foot section of concrete pipe, drilling, anchoring, grouting, rebar and concrete fill. In accordance with drawing ATON STD 05 .
1 EA
113111 Install an additional 1 foot of submerged obstruction concrete foundation. Includes concrete pipe, rebar and concrete fill. In accordance with drawing ATON STD 05.
1 EA
113112
Install a pedestal beacon structure on a new or existing concrete breakwater foundation. Includes installing pedestal, platform, one ladder extension and brackets, drilling and anchoring (if required), leveling and grouting, and installing up to 3 day boards. In accordance with drawing ATON STD 05, ATON STD 09, ATON STD 10 and ATON STD 13.
1 EA
113113
Install a pedestal range structure on a new or existing concrete breakwater foundation or submerged obstruction foundation. Includes installing pedestal, platform, one ladder extension and brackets, drilling and anchoring (if required), leveling and grouting, and installing range board frame support bracket, and range board. In accordance with drawing ATON STD 05, ATON STD 10 and ATON STD 12.
1 EA
113114
Install on any type of steel pile structure, one each, 7 foot ladder extension including bolting ladder extension brackets to ladder and attaching ladder extension assembly to the structure with “U” bolts. In accordance with drawings ATON STD 01, ATON STD 02,ATON
STD 03, ATON STD 04, ATON STD 05, ATON STD 06,
ATON STD 09, ATON STD 10 and ATON STD 11.
1 EA
113115 Install one (1) NON ATON steel pile using the vibratory method
113500 SHORE CONSTRUCTION - INSTALLATION
113501 assembly. In accordance with drawing ATON STD 07.
1 EA
113502 Install a concrete foundation to receive a sectional tower assembly. In accordance with drawing ATON STD 07.
1 EA
113503 Install a concrete foundation as a pile cap to receive a sectional tower assembly. In accordance with drawing
ATON STD 07.
1 EA
113504 Install a concrete pedestal foundation on a land location.
As per drawing ATON STD 05.
1 EA
113505
Install on any type of steel pile structure, one each, 7 foot ladder extension including bolting ladder extension brackets to ladder and attaching ladder extension assembly to the structure with “U” bolts. In accordance with drawings ATON STD 01, ATON STD 02, ATON
STD 03, ATON STD 04, ATON STD 05 ATON STD 06,
ATON STD 09, ATON STD 10 and ATON STD 11.
1 EA
113506 Provide and install a chain link fence around a shore structure 10 foot by 10 foot including gate, razor wire
1 EA
113507 Provide and install an additional 4 linier feet of fence.
120000 EMERGENCY TASK ORDERS
121000 EMERGENCY MOBILIZATION / DEMOBILIZATION:
121001 in Area No. 1. 1 per Task Order.
1 EA
121002 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 2. 1 Per Task Order.
1 EA
121003 Mobilize and Demobilize or EMERGENCY Task Order in Area No. 3. 1 Per Task Order.
1 EA
121004 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 4. 1 per Task Order.
1 EA
121005 Mobilize and Demobilize for EMERGENCY Task Order in Area No. 5. 1 Per Task Order.
1 EA
121006 Mobilize and Demobilize or EMERGENCY Task Order in Area No. 6. 1 Per Task Order.
122000 REMOVALS
122001 including platform assembly, ladder extensions under EMERGENCY Task Order. Remove and return all ATON hardware, platform, and ladders if reusable.
Contractor shall dispose of all other materials. See drawings ATON STD 01 and ATON STD 02.
1 EA
122002
Remove damaged three (3) steel pipe pile structure including platform assembly, ladder extensions under EMERGENCY Task Order. Remove and return all ATON hardware, platform, and ladders if reusable.
Contractor shall dispose of all other materials. See drawings ATON STD 03 and ATON STD 04.
1 EA
122003
Remove damaged four (4) steel pipe pile structure including pile platform assembly, ladder extensions and sectional lower assembly under EMERGENCY Task Order. Remove return and all ATON hardware, pile platform, ladders and sectional tower parts if reusable.
Contractor shall dispose of all other materials.
1 EA
122004
Remove damaged wood pile channel marking structure consisting of multiple pile members, platform assembly, ladders and bindings under EMERGENCY Task Order.
Remove and return all ATON hardware and metal platform, if used and reusable. Contractor shall dispose of all other materials.
1 EA
122005
Remove damaged wood pile range structure consisting of multiple driven pile members a platform assembly, sectional steel tower, ladders and bindings under EMERGENCY Task Order. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials.
130000 TRANSIT COSTS
130001 water work location on the same Task Order per nautical mile (NM).
140000 REPAIRS
140001 on either a one (1) pile structure, a three (3) pile structure or a pedestal structure and install up to 3 day boards. In accordance with drawing ATON STD 01, ATON STD 03, ATON STD 05, ATON STD 11, ATON
STD 12, ATON STD 13 and ATON STD 14.
140002
Replace a range structure platform either 5’x5’ or 7’x7’ on either a one (1) pile structure, a three (3) pile structure or a pedestal structure. Including new range board frame and new range board. In accordance with drawing ATON STD 02, ATON STD 04, ATON STD 05, ATON STD 11, ATON STD 12 and ATON STD 14.
1 EA
140003
Replace one damaged ladder including ladder brackets on either a one (1) pile structure, a three (3) steel pile structure a pedestal structure or a four (4) pile structure, In accordance with drawing ATON STD 01, ATON STD
02, ATON STD 03, ATON STD 04, ATON STD 05,
ATON STD 06, and ATON STD 11.
150000 MATERIALS
150001 strait seam steel pipe, priced per linear foot (LF).
1 LF
150002 Perform one (1) weld to join two (2) pieces of 18” diameter pile pipe together.
1 EA
150003
Provide one fabricated pedestal base. To include all flat steel and welding. In accordance with drawing ATON STD 05. NOTE: Steel pipe will be cost out using line item “050001”.
1 EA
150004 Provide galvanizing of one pedestal base including base plate and 10 feet of pipe. In accordance with drawing
ATON STD 05.
1 EA
150005
Provide galvanizing of 10 feet of pipe. In accordance with drawings ATON STD 01. ATON STD 02, ATON STD 03, ATON STD 04, ATON STD 05 and ATON STD
06. 1 LFT
150006 Provide one fabricated 5’’x5’ platform in accordance with drawing ATON STD 09.
1 EA
150007 Provide one fabricated 7’x7’ platform in accordance with drawing ATON STD 10.
1 EA
150008 Provide one fabricated 7 foot ladder extension in accordance with drawing ATON STD 11.
1 EA
150009
Provide 1 set, consisting of 2 each brackets, fabricated ladder extension brackets; of either LEB 5x5-1, LEB 5x5-3, LEB 7x7-1, LEB 7x7-3 or LEB 10x10-1. Includes bracket, hoop and fasteners. In accordance with drawing ATON STD 11.
1 Set
150010 Provide a fabricated 10 foot square 4 pile platform. In accordance with drawing ATON STD 06.
150011 sectional tower. Includes tower members, platform assembly, and 4 each tower base column connectors and all fasteners. In accordance with drawing ATON
STD 08.
1 EA
150012
Provide a fabricated unassembled 10 foot section of sectional tower. Includes tower members, platform assembly, and 4 each tower base column connectors and all fasteners. In accordance with drawing ATON
STD 08.
1 EA
150013
Provide a fabricated unassembled 15 foot section of sectional tower. Includes tower members, platform assembly, and 4 each tower base column connectors and all fasteners. In accordance with drawing ATON
STD 08.
1 EA
150014
Provide a fabricated unassembled 5 foot section of sectional tower, includes 4 each splice plates and all fasteners. (Does not include platform assy. or tower base column connectors) In accordance with drawing
ATON STD 08.
1 EA
150015
Provide a fabricated unassembled 10 foot section of sectional tower, includes 4 each splice plates and all fasteners. (Does not include platform assy. or tower base column connectors) In accordance with drawing
ATON STD 10.
1 EA
150016
Provide a fabricated unassembled 15 foot section of sectional tower, includes 4 each splice plates and all fasteners. (Does not include platform assy. or tower base column connectors) In accordance with drawing
ATON STD 10.
1 EA
150017 Provide a fabricated set of 4 each Tower Base Column Connector Bracket, including all fasteners. As per drawing ATON STD 08.
1 SET
150018 Provide a fabricated set of 4 each splice brackets, including all fasteners. As per drawing ATON STD 08.
1 SET
150019 Provide a fabricated 8KRW (8’x16’) Range Board Frame, including all fasteners. In accordance with drawing ATON STD 12.
1 EA
150020 Provide a fabricated 6KRW (6’x12’) Range Board Frame, including all fasteners. In accordance with drawing ATON STD 12.
1 EA
150021 Provide a fabricated 4KRW (4’x8’) Range Board Frame, including all fasteners. In accordance with drawing
ATON STD 12.
150022 Provide a fabricated 3KRW (3’x6’) Range Board Frame, including all fasteners. In accordance with drawing
ATON STD 12.
1 EA
150023 Provide a manufactured cable type Safety Climb Device.
In accordance with drawing ATON STD 14.
160000 RETURN OF GOVERNMENT MATERIALS
160001 materials; ATON equipment, batteries (must be double bagged in plastic), usable platforms, ladders and brackets, and temp buoys to the ANT responsible for the structures built under this Task order.
170000 AS-BUILT PHOTOGRAPHS
170001 degrees apart of completed new construction. Provide 3 CD’s of photographs. (Photos of one structure on 3 each CD’s will be used for evaluation purposes only.)
NOTE: All photos taken under one Task Order may be combined on one CD.)
180000 DIVING SERVICES
180001 position of old structure, attending retrieval process for found structure and cut of any metal pile extending above the mud line.
1 EA
180002 Diving services to investigate underwater condition of underwater portion of structure. Provide written report of dive findings.
190000 FIELD ENGINEERING
190001
VERTICAL and HORIZONTAL methods.
191000 MARINE MAMMAL MONITORING
191001
Monumental Dam to Lewiston, ID): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
191002
Geographical Area 2 (Columbia River from McNary Dam to Richland, WA and Snake River up to Lower Monumental Dam): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
191003
Geographical Area 3 (Columbia River from John Day Dam to McNary Dam): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
191004
Geographical Area 4 (Columbia River from Bonneville Dam to Joh Day Dam): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
191005
Geographical Area 5 (Columbia River from Lewis and Clark Bridge to Bonneville Dam and Willamette River up to, and including, Multnomah Channel and Wilsonville, OR): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
191006
Geographical Area 6 (Columbia River from Lewis and Clark Bridge to Pacific Ocean including structures within a 10NM radius west of western most point of northern entrance jetty)): Mobilization of a boat, operator and a biological monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
191007
Onsite Monitoring Services/per day: Includes labor, equipment and supplies for the biologist and team to perform monitoring services on the ATON site for one 8-hour day. Applies to Geographical Areas 1, 2, 3, 4, 5, and 6.
1 DY
191008
Standby for Marine Mammal(s): Includes labor and equipment for the construction crew to standby while waiting for a marine mammal to vacate the construction area.
192000 EELGRASS SURVEY
192001 waters north of Yaquina Head, OR, including inlets, bays, and waterways.): Mobilization of a boat, operator and an eelgrass monitor as well as the necessary reporting for one ATON structure within/per body of
192002
Geographical Area 2 (South of Yaquina Head, OR to the waters north of Coquille Point, OR, including all inlets, bays, and waterways.): Mobilization of a boat, operator and an eelgrass monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
192003
Geographical Area 3 (South of Coquille Point, OR to the waters north of the California-Oregon border, including all inlets, bays, and waterways.): Mobilization of a boat, operator and an eelgrass monitor as well as the necessary reporting for one ATON structure within/per body of water.
1 EA
192004
Onsite Monitoring Services/per day: Includes labor, equipment and supplies for the biologist and team to perform eelgrass surveys on the ATON site for one 8-
Total Option Year One $ ______________________
200001
Option Year 2: Provide all labor, materials, equipment, transportation, and supervision for the Term Pile contract in the Columbia River, WA and OR and the
Base Period from April 1, 2018 to March 31, 2019.
210000 IMPROPER CHARACTERISTIC TASK ORDER
211000 MOBILIZATION / DEMOBILIZATION:
211001
No. 1. 1 per Task Order.
1 EA
211002 Demobilize for Improper Characteristic Task Order in Area No. 1. 1 Per Task Order.
1 EA
211003 Mobilize for Improper Characteristic Task Order in Area No. 2. 1 Per Task Order.
1 EA
211004 Demobilize for Improper Characteristic Task Order in Area No. 2. 1 Per Task Order.
1 EA
211005 Mobilize for Improper Characteristic Task Order in Area No. 3. 1 Per Task Order.
1 EA
211006 Demobilize for Improper Characteristic Task Order in Area No. 3. 1 Per Task Order.
1 EA
211007 Mobilize for Improper Characteristic Task Order in Area No. 4. 1 Per Task Order.
1 EA
211008 Demobilize for Improper Characteristic Task Order in Area No. 4. 1 Per Task Order.
1 EA
211009 Mobilize for Improper Characteristic Task Order in Area No. 5. 1 Per Task Order.
1 EA
211010 Demobilize for Improper Characteristic Task Order in Area No. 5. 1 Per Task Order.
211011
No. 6. 1 Per Task Order.
1 EA
211012 Demobilize for Improper Characteristic Task Order in Area No. 6. 1 Per Task Order.
1 EA
211013
Mobilize and Demobilize from one site in Area No. 1 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
211014
Mobilize and Demobilize from one site in Area No. 2 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
211015
Mobilize and Demobilize from one site in Area No. 3 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
211016
Mobilize and Demobilize from one site in Area No. 4 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
211017
Mobilize and Demobilize from one site in Area No.5 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
1 EA
211018
Mobilize and Demobilize from one site in Area No. 6 for land construction of line items in sections 012500 Removals Shore Construction and 013500 Shore Construction
212000 REMOVALS – IN WATER CONSTRUCTION
212001 including platform assembly, ladder extensions.
Remove and return all ATON hardware, platform, and ladders if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 01 and ATON
212002 including platform assembly, ladder extensions.
Remove and return all ATON hardware, platform, and ladders if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 03 and ATON STD 04.
1 EA
212003
Remove damaged four (4) steel pipe pile structure including pile platform assembly, ladder extensions and sectional lower assembly. Remove return and all ATON hardware, pile platform, ladders and sectional tower parts if reusable. Contractor shall dispose of all other materials. See drawings ATON STD 06 and ATON STD 08.
1 EA
212004
Remove damaged wood pile channel marking structure consisting of one (1) or multiple driven pile members, including platform assembly, ladders and bindings.
Remove and return all ATON hardware and metal platform, if used and reusable. Contractor shall dispose of all other materials.
1 EA
212005
Remove damaged wood pile range structure consisting of multiple driven pile members, including platform assembly, ladders and bindings. Remove and return all ATON hardware. Contractor shall dispose of all other materials.
1 EA
212006
Remove damaged wood pile range structure consisting of multiple driven pile members a platform assembly, sectional steel tower, ladders and bindings. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials.
1 EA
212007
Remove pedestal assembly from either a break wall or submerged obstruction, consisting of a steel pipe and platform. Remove and return all ATON hardware.
Contractor shall dispose of all other materials.
1 EA
212008 Remove and dispose of one NON ATON piling using vibratory method
212500 Removals - Shore Construction
212501 driven pile members a platform assembly, sectional steel tower, ladders and bindings. Remove and return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other
212502
Return all ATON hardware and reusable sectional tower components. Contractor shall dispose of all other materials. See drawings ATON STD 08.
1 EA
212503 Remove concrete foundation up to 6 Cubic Yards.
Contractor shall dispose of all other materials.
1 EA
212…