HSCG80-13-Q-P45218-Amendment_1.pdf
PDF 215 KB Posted
- Attached to
- USCGC ACTIVE (WMEC-618) Routine Dockside Repairs
- Solicitation number
- HSCG80-13-R-P45218
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_5.pdf | ||
| Amendment_4.pdf | ||
| Amendment_3-HSCG80-13-R-P45218.pdf | ||
| Amendment_2.pdf | ||
| RFP_HSCG80-13-R-P45218.pdf | ||
| SOW-RFP_HSCG80-13-R-P45218.pdf | ||
| Attachment_2-Past_Perf_Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 7540-01-152-8070
STANDARD FORM 30 (REV. 10-83) PREVIOUS EDITION UNUSABLE
Prescribed by GSA, FAR (48 CFR) 53.243
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 1
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Amendment 0001 02/07/2013
6. ISSUED BY CODE 84 7. ADMINISTERED BY (If other than Item 6) CODE 84
Department of Homeland Security
United States Coast Guard
USCG Surface Forces Logistics Center
300 East Main Street, Suite 550
Norfolk, VA 23510-9112
Same as Item 6
POC: Amy McLiverty (757) 628-4125
E-mail: Amy.L.McLiverty@uscg.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
HSCG80-13-R-P45218
X 9B. DATED (SEE ITEM 11)
12/03/2012
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for Receipt of Offers is extended / is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning one copy(s) of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE
RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc)
SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not / is required to sign this document and return _1__ copy(s) to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0001 is issued to:
1) Correct the date listed on page 16 of 39, for FAR Clause 52.212-5—Contract Terms and Conditions Required to
Implement Statutes or Executive Orders—Commercial Items. The date is January 2013.
2) Update the evaluation criteria information in Factor 1-Past Performance listed in FAR Provision 52.212-2
Evaluation-Commercial Items (JAN 1999)-Variation. Please review Factor 1-Past Performance on page 26 of
39.
3) Please find replacement pages attached.
The Closing Date remains 12:00 pm EST on 19 February 2013.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY:
(Signature of person authorized to sign) (Signature of Contracting Officer)
HSCG80-13-R-P45218 Page 16 of 39
USCGC ACTIVE (WMEC-618)
DOCKSIDE REPAIRS
CONTRACT DEFICIENCY REPORT
The Contracting Officer or Contracting Officer‘s Technical Representative (COTR) may issue a Contract
Deficiency Report (CDR), SFLC Form 005. The Contractor shall respond in writing within 24 hours of receipt, unless otherwise approved by the Contracting Officer, to the COTR. The COTR will comment on the
Contractor's response and will forward the Deficiency Report and comments to the Contracting Officer, with a copy to the Contractor and Availability Program Manager. The Contracting Officer will render a final determination and provide it to the Contractor and COTR in writing.
(End of FAR 52.212-4 Addendum)
52.212-5 -- Contract Terms and Conditions Required to Implement Statutes or Executive
Orders -- Commercial Items. (JAN 2013)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.222-50, Combating Trafficking in Persons (FEB 2009) (22 U.S.C. 7104(g)).
____ Alternate I (AUG 2007) of 52.222-50 (22 U.S.C. 7104(g)).
(2) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(3) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the contracting officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.]
_X_ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct
1995) (41 U.S.C. 253g and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Apr 2010) (Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub L. 111-5) (Applies to contracts funded by the American Recovery and
Reinvestment Act of 2009).
_X_ (4) 52.204-10, Reporting Executive compensation and First-Tier Subcontract Awards (Aug 2012) (Pub.
L. 109-282) (31 U.S.C. 6101 note).
___ (5) 52.204-11, American Recovery and Reinvestment Act—Reporting Requirements (Jul 2010) (Pub. L.
111-5).
_X_ (6) 52.209-6, Protecting the Government‘ Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Dec 2010) (31 U.S.C. 6101 note).
___ (7) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Feb 2012)
(41 U.S.C. 2313).
___ (8) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (May 2012) (section 738 of Division C of Public Law 112-74, section 740 of Division C of Pub. L. 111-117, section 743 of Division D of Pub. L. 111-8, and section 745 of Division D of Pub. L. 110-161).
___ (9) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
___ (10) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Jan 2011)
(if the offeror elects to waive the preference, it shall so indicate in its offer)(15 U.S.C. 657a).
___ (11) [Reserved] _X_ (12) (i) 52.219-6, Notice of Total Small Business Aside (Nov 2011) (15 U.S.C. 644).
___ (ii) Alternate I (Nov 2011).
___ (iii) Alternate II (Nov 2011).
ALMcliverty Highlight
HSCG80-13-R-P45218 Page 26 of 39
USCGC ACTIVE (WMEC-618)
DOCKSIDE REPAIRS
(a) Submission of certified cost or pricing data is not required
(b) If the contracting officer cannot determine price reasonableness either in the initial solicitation or in any change to the contract after award, the contracting officer will require submission information in sufficient detail in order to make such determination.
The information may be as follows:
REQUEST FOR INFORMAL COST BREAKDOWN
In addition to placing your offer in the appropriate place in Schedule of supplies and
Prices, it is requested that you provide a breakdown of your costs, to include but not be limited to, those items identified in the sample format below:
Trade, (i.e. laborers, rigger, etc.)
Breakdown of labor grades by trade category
Manhours per trade, per labor grade
Cost/hour/trade
Supplies/materials (description & cost of each)
Sub-total
Pension Plans
Overhead at a rate of ______%
Profit at a rate of ________%
Total for item _____________
FAR 52.212-2 EVALUATION-COMMERCIAL ITEMS (JAN 1999) - VARIATION
QUOTES SHALL BE EVALUATED USING THE FOLLOWING CRITERIA:
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the
Government, price and other factors considered. The two (2) following factors shall be used to evaluate offers:
FACTOR 1-PAST PERFORMANCE:
The offeror shall identify at least two (2) relevant (construction, overhaul, repair and alteration of ships) and current federal, state or local government or private contracts performed during the last three (3) years. An offeror without a record of relevant past performance will not be evaluated favorably or unfavorably on past performance. For each contract, list:
a. Contract number and customer point of contact (including two (2) points of contact
With telephone numbers)
b. Dollar value of the contract (Original and Final)
c. Type of service performed and whether Prime or subcontractor
ALMcliverty Highlight
File details come from the government source that posted it. Updated .