Amendment_4.pdf
PDF 50 KB Posted
- Attached to
- USCGC ACTIVE (WMEC-618) Routine Dockside Repairs Federal contract opportunity
- Solicitation number
- HSCG80-13-R-P45218
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_5.pdf | ||
| Amendment_3-HSCG80-13-R-P45218.pdf | ||
| Amendment_2.pdf | ||
| HSCG80-13-Q-P45218-Amendment_1.pdf | ||
| RFP_HSCG80-13-R-P45218.pdf | ||
| Attachment_2-Past_Perf_Questionnaire.pdf | ||
| SOW-RFP_HSCG80-13-R-P45218.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 7540-01-152-8070
STANDARD FORM 30 (REV. 10-83) PREVIOUS EDITION UNUSABLE
Prescribed by GSA, FAR (48 CFR) 53.243
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 1
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Amendment 0004 02/14/2013
6. ISSUED BY CODE 84 7. ADMINISTERED BY (If other than Item 6) CODE 84
Department of Homeland Security
United States Coast Guard
USCG Surface Forces Logistics Center
300 East Main Street, Suite 550
Norfolk, VA 23510-9112
Same as Item 6
POC: Amy McLiverty (757) 628-4125
E-mail: Amy.L.McLiverty@uscg.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
HSCG80-13-R-P45218
X 9B. DATED (SEE ITEM 11)
02/04/2013
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for Receipt of Offers is extended / is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning one copy(s) of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE
RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc)
SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not / is required to sign this document and return ___ copy(s) to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0004 is issued to:
1) Post Questions and Answers received as a result of the solicitation.
The Closing Date remains 12:00 pm EST on 19 February 2013.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY:
(Signature of person authorized to sign) (Signature of Contracting Officer)
Q&A/HSCG80-13-R-P45218
1) Specification Item No.: 12
WORK ITEM 12: Padeyes, Inspect and Test Paragraph No.: 3.2.1 Surface preservation
Question:
Supplied drawing shows all padeyes in interior of vessel. The specification instructs contractor to follow COMDTINT M10360.3 which reads, surface preparation by SP-10. Because sandblasting to SP-10 will contaminate the interior of vessel will the government consider SP-3 or SP-11 an acceptable surface preparation?
Answer: A mechanical preparation to bare metal with SP-11 would be acceptable.
2) Specification Item No.: 14
WORK ITEM 14: Control Air Dryer, Upgrade Paragraph No.: 3.2.4 Electrical System connections
Question:
Is the Government instructing the contractor to completely rewire the ER controls? Or just disconnect the existing and reconnect on the new unit?
Answer: The E/R controls are in place, the unit itself needs the swap, and there is no extensive rewiring required.
Question:
Is the Control Air light existing? If contractor is to supply and install, where does it get installed?
Answer: Yes, the light does exist.