270 A B CLASS (WMEC) DOCKSIDE REPAIRS - SCHEDULE OF SUPPLIES AND SERVICES PRICING SHEETS (BASE YEAR 2011 YEAR 2012 YEAR 2013 YEAR 2014 YEAR 2015)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AMEND A0009 PAGE 2.doc | DOC document | |
| 270 DS IDIQ SPEC R4 111910 Issued.pdf | ||
| Amend A0009.pdf | ||
| 270 DS IDIQ Est R5_BLANK 111910 Issued.pdf | ||
| Amend A0008.pdf | ||
| Amend A0007.pdf | ||
| 270 DS IDIQ SPEC R3 110410 Issued.pdf | ||
| 270 DS IDIQ Est R4_Blank 110410 Issued.pdf | ||
| Amend A0006.pdf | ||
| 270 DS IDIQ Est R3_Blank 102110.pdf | ||
| Amend A0005.pdf | ||
| Amend A0004.pdf | ||
| 270 DS IDIQ Est R3_Blank 102110.pdf | ||
| AMEND A0003 PAGE 2.doc | DOC document | |
| 270 IDIQ DS CUTTER CONTACTS.pdf | ||
| 270 DS IDIQ SPEC R2 092410 | — | |
| Amend A0003.pdf | ||
| AMEND 0002.pdf | ||
| AMEND A0001.pdf | ||
| SF33.pdf | ||
| 270 DS IDIQ SPEC R1 Issue TEF 072910.doc | DOC document | |
| HSCG80-10-R-P45GK4 SOLICITATION.doc | DOC document |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM DESCRIPTION UNIT PRICE UNIT QTY
BASE YEAR
EXTENDED PRICE
(FY'11)
1-O Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 25
2-O Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 40
3-D Chain Lockers, Inspect JOB 4
4-O Sea Water Piping, Renew 1 LF 1
5-D Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 4
6-D Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 4
7-D Vent Ducts (Engine Room), Commercial Cleaning JOB 4
8-D Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 4
9-D Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 4
10-O Chill Water Piping, Renew 1 LF 16
11-O Feed/Jacket Water Piping, Renew 1 LF 16
12-O Potable Water Piping, Renew 1 LF 16
13-D Potable Water Pneumatic Tank, Clean and Inspect JOB 4
14-O Fuel Piping, Renew 1 LF 4
15-D Fin Stabilizers, General Maintenance JOB 4
SCHEDULE OF SUPPLIES & SERVICES (SOS&S)
270 DOCKSIDE AVAILABILITY IDIQ - 2011, BASE YEAR
(4 Availabilities Projected for 2011)
16-D Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 4
17-D Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 4
18-D Warping Capstan, Perform Level 2 Maintenance JOB 4
19-D Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 4
20-D Helo Talon Grid, Inspect and Test JOB 4
21-D Grey Water Holding Tanks, Clean and Inspect JOB 4
22-D Sewage Collection and Holding Tanks, Clean and Inspect JOB 4
23-O Work Item Deleted - Job - -
24-D Grey Water Piping, Clean and Flush 10 LF 4
25-O Sewage Piping, Renew 1 LF 4
26-D Sewage Piping, Clean and Flush 10 LF 4
27-O Tanks (Ballast), Preserve “100%” - - - -
27-O Ballast, 3-B-0-W EA 1
27-O Ballast, 4-75-1-W EA 1
27-O Ballast, 4-75-2-W EA 1
27-O Ballast, 4-103-1-W EA 1
27-O Ballast, 4-103-2-W EA 1
270 DS IDIQ Est R2_BLANK 09241013
27-O Ballast,4-169-0-W EA 1
27-O Ballast, 4-228-1-W EA 1
27-O Ballast, 4-228-2-W EA 1
27-O Ballast, 4-242-0-W EA 1
28-O Tank (Dirty Oil and Waste), Preserve “100%” JOB 1
29-O Tanks (Potable Water), Preserve “100%” - - - -
29-O Potable Water, 4-78-1-W EA 1
29-O Potable Water, 4-78-2-W EA 1
29-O Potable Water, 4-94-1-W EA 1
30-O Tanks (Sewage and Vacuum Collection), Preserve “100%” - -
30-O Sewage Tank, 3-82-0-E EA 1
30-O Vacuum Collection Tank, 2-82-0-E EA 1
31-O Tanks (Grey Water Holding), Preserve “100% - - - -
31-O Aft, 3-103-0-E EA 1
31-O FWD, 3.82-0-E EA 1
Seal Water Tank EA 1
32-O Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - - -
Watertight Door, 12" x 18" EA 1
Watertight Door, 18" x 36" EA 1
Watertight Door, 33" x 66" EA 1
Scuttle, Round, 12" Dia. EA 1Scuttle, Round, 12 Dia. EA 1
Scuttle, Round, 14" Dia. EA 1
Scuttle, Round, 18" Dia. EA 1
Scuttle, Round, 21" Dia. EA 1
Scuttle, Round, 24" Dia. EA 1
33-O Watertight Doors and Scuttles (External), Renew - - - -
Watertight Door, 12" x 18" EA 1
Watertight Door, 18" x 36" EA 1
Watertight Door, 33" x 66" EA 1
Scuttle, Round, 12" Dia. EA 1
Scuttle, Round, 14" Dia. EA 1
Scuttle, Round, 18" Dia. EA 1
Scuttle, Round, 21" Dia. EA 1
Scuttle, Round, 24" Dia. EA 1
34-O Piping Insulation, Renew 10 LF 1
35-D Compressed Air Receivers, Clean, Inspect, and Test JOB 4
36-O Tanks (Ballast), Preserve, “Partial” - - - -
36-O Ballast, 3-B-0-W EA 4
270 DS IDIQ Est R2_BLANK 09241023
36-O Ballast, 4-75-1-W EA 4
36-O Ballast, 4-75-2-W EA 4
36-O Ballast, 4-103-1-W EA 4
36-O Ballast, 4-103-2-W EA 4
36-O Ballast,4-169-0-W EA 4
36-O Ballast, 4-228-1-W EA 4
36-O Ballast, 4-228-2-W EA 4
36-O Ballast, 4-242-0-W EA 4
37-O Tank (Dirty Oil and Waste), Preserve, “Partial” Job 4
38-O Tanks (Potable Water), Preserve “Partial” - - - -
38-O Potable Water, 4-78-1-W EA 4
38-O Potable Water, 4-78-2-W EA 4
38-O Potable Water, 4-94-1-W EA 4
39-O Tanks (Sewage Holding), Preserve, “Partial” - - - -
39-O Sewage Tank, 3-82-0-E EA 4
39-O Vacuum Collection Tank, 2-82-0-E EA 4
40-O Tanks (Grey Water Holding), Preserve, “Partial” - - - -
40-O Aft, 3-103-0-E EA 4
40-O FWD, 3.82-0-E EA 4
40-O Seal Water Tank EA 4
A-O Composite Labor Rate HOUR 1,775
B-D GFP Report NSP EA 4 NSP
Total Price of Definite Items Total Price of Option Items Total Price of Definite and Option Items
270 DS IDIQ Est R2_BLANK 09241033
YR 1 - BASE 2011
ITEM DESCRIPTION UNIT PRICE UNIT QTY EXTENDED PRICE
(FY'12)
1-O Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 12
2-O Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 20
3-D Chain Lockers, Inspect JOB 2
4-O Sea Water Piping, Renew 1 LF 1
5-D Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 2
6-D Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 2
7-D Vent Ducts (Engine Room), Commercial Cleaning JOB 2
8-D Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 2
9-D Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 2
10-O Chill Water Piping, Renew 1 LF 8
11-O Feed/Jacket Water Piping, Renew 1 LF 8
12-O Potable Water Piping, Renew 1 LF 8
13-D Potable Water Pneumatic Tank, Clean and Inspect JOB 2
14-O Fuel Piping, Renew 1 LF 2
SCHEDULE OF SUPPLIES & SERVICES (SOS&S)
270 DOCKSIDE AVAILABILITY IDIQ - 2012, YEAR 2
(2 Availabilities Projected for 2012)
15-D Fin Stabilizers, General Maintenance JOB 2
16-D Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 2
17-D Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 2
18-D Warping Capstan, Perform Level 2 Maintenance JOB 2
19-D Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 2
20-D Helo Talon Grid, Inspect and Test JOB 2
21-D Grey Water Holding Tanks, Clean and Inspect JOB 2
22-D Sewage Collection and Holding Tanks, Clean and Inspect JOB 2
23-O Work Item Deleted - Job - -
24-D Grey Water Piping, Clean and Flush 10 LF 2
25-O Sewage Piping, Renew 1 LF 2
26-D Sewage Piping, Clean and Flush 10 LF 4
27-O Tanks (Ballast), Preserve “100%” - -
27-O Ballast, 3-B-0-W EA 1
27-O Ballast, 4-75-1-W EA 1
27-O Ballast, 4-75-2-W EA 1
27-O Ballast, 4-103-1-W EA 1
27-O Ballast, 4-228-2-W EA 1
27-O Ballast, 4-242-0-W EA 1
28-O Tank (Dirty Oil and Waste), Preserve “100%” JOB 1
29-O Tanks (Potable Water), Preserve “100%” - -
29-O Potable Water, 4-78-1-W EA 1
29-O Potable Water, 4-78-2-W EA 1
29-O Potable Water, 4-94-1-W EA 1
30-O Tanks (Sewage and Vacuum Collection), Preserve “100%” - -
30-O Sewage Tank, 3-82-0-E EA 1
30-O Vacuum Collection Tank, 2-82-0-E EA 1
31-O Tanks (Grey Water Holding), Preserve “100% - -
31-O Aft, 3-103-0-E EA 1
31-O FWD, 3.82-0-E EA 1
Seal Water Tank EA 1
32-O Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - -
Watertight Door 12" x 18" EA 1Watertight Door, 12 x 18 EA 1
Watertight Door, 18" x 36" EA 1
Watertight Door, 33" x 66" EA 1
Scuttle, Round, 12" Dia. EA 1
Scuttle, Round, 14" Dia. EA 1
Scuttle, Round, 18" Dia. EA 1
Scuttle, Round, 21" Dia. EA 1
Scuttle, Round, 24" Dia. EA 1
33-O Watertight Doors and Scuttles (External), Renew - - -
Watertight Door, 12" x 18" EA 1
34-O Piping Insulation, Renew 10 LF 2
35-D Compressed Air Receivers, Clean, Inspect, and Test JOB 2
36-O Tanks (Ballast), Preserve, “Partial” - -
36-O Ballast, 3-B-0-W EA 2
36-O Ballast, 4-75-1-W EA 2
36-O Ballast, 4-75-2-W EA 2
36-O Ballast, 4-103-1-W EA 2
36-O Ballast, 4-103-2-W EA 2
36-O Ballast,4-169-0-W EA 2
36-O Ballast, 4-228-1-W EA 2
36-O Ballast, 4-228-2-W EA 2
36-O Ballast, 4-242-0-W EA 2
37-O Tank (Dirty Oil and Waste), Preserve, “Partial” Job 2
38-O Tanks (Potable Water), Preserve “Partial” - -
38-O Potable Water, 4-78-1-W EA 2
38-O Potable Water, 4-78-2-W EA 2
38-O Potable Water, 4-94-1-W EA 2
39-O Tanks (Sewage Holding), Preserve, “Partial” - -
39-O Sewage Tank, 3-82-0-E EA 2
39-O Vacuum Collection Tank, 2-82-0-E EA 2, 40-O Tanks (Grey Water Holding), Preserve, “Partial” - -
40-O Aft, 3-103-0-E EA 2
40-O FWD, 3.82-0-E EA 2
40-O Seal Water Tank EA 2
A-O Composite Labor Rate HOUR 650
B-D GFP Report NSP EA 2 NSP
Total Price of Definite Items Total Price of Option Items
YR 2 - 2012
(FY'13)
1-O Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1
2-O Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 8
3-D Chain Lockers, Inspect JOB 1
4-O Sea Water Piping, Renew 1 LF 3
5-D Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1
6-D Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1
7-D Vent Ducts (Engine Room), Commercial Cleaning JOB 1
8-D Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1
9-D Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1
10-O Chill Water Piping, Renew 1 LF 1
11-O Feed/Jacket Water Piping, Renew 1 LF 1
12-O Potable Water Piping, Renew 1 LF 1
13-D Potable Water Pneumatic Tank, Clean and Inspect JOB 1
14-O Fuel Piping, Renew 1 LF 1
270 DOCKSIDE AVAILABILITY IDIQ - 2013, YEAR 3
(1 Availabilities Projected for 2013)
15-D Fin Stabilizers, General Maintenance JOB 1
16-D Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1
17-D Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1
18-D Warping Capstan, Perform Level 2 Maintenance JOB 1
19-D Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1
20-D Helo Talon Grid, Inspect and Test JOB 1
21-D Grey Water Holding Tanks, Clean and Inspect JOB 1
22-D Sewage Collection and Holding Tanks, Clean and Inspect JOB 1
24-D Grey Water Piping, Clean and Flush 10 LF 1
25-O Sewage Piping, Renew 1 LF 1
26-D Sewage Piping, Clean and Flush 10 LF 1
27-O Tanks (Ballast), Preserve “100%” - - - -
29-O Tanks (Potable Water), Preserve “100%” - - - -
31-O Tanks (Grey Water Holding), Preserve “100% - - - -
Renew - - - -
33-O Watertight Doors and Scuttles (External), Renew - - - -
34-O Piping Insulation, Renew 10 LF 1
35-D Compressed Air Receivers, Clean, Inspect, and Test JOB 1
36-O Tanks (Ballast), Preserve, “Partial” - - - -
36-O Ballast, 3-B-0-W EA 1
36-O Ballast, 4-75-1-W EA 1
36-O Ballast, 4-75-2-W EA 1
36-O Ballast, 4-103-1-W EA 1
36-O Ballast, 4-103-2-W EA 1
36-O Ballast,4-169-0-W EA 1
36-O Ballast, 4-228-1-W EA 1
36-O Ballast, 4-228-2-W EA 1
36-O Ballast, 4-242-0-W EA 1
37-O Tank (Dirty Oil and Waste), Preserve, “Partial” Job 1
38-O Tanks (Potable Water), Preserve “Partial” - - - -
38-O Potable Water, 4-78-1-W EA 1
38-O Potable Water, 4-78-2-W EA 1
38-O Potable Water, 4-94-1-W EA 1
39-O Tanks (Sewage Holding), Preserve, “Partial” - - - -
39-O Sewage Tank, 3-82-0-E EA 1
39-O Vacuum Collection Tank, 2-82-0-E EA 1, 40-O Tanks (Grey Water Holding), Preserve, “Partial” - - - -
40-O Aft, 3-103-0-E EA 1
40-O FWD, 3.82-0-E EA 1
40-O Seal Water Tank EA 1
A-O Composite Labor Rate HOUR 342
B-D GFP Report NSP EA 1 NSP
YR 3 - 2013
(FY'14)
1-O Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 20
2-O Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 30
3-D Chain Lockers, Inspect JOB 3
5-D Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 3
6-D Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 3
7-D Vent Ducts (Engine Room), Commercial Cleaning JOB 3
8-D Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 3
9-D Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 3
10-O Chill Water Piping, Renew 1 LF 12
11-O Feed/Jacket Water Piping, Renew 1 LF 12
12-O Potable Water Piping, Renew 1 LF 12
13-D Potable Water Pneumatic Tank, Clean and Inspect JOB 3
14-O Fuel Piping, Renew 1 LF 3
270 DOCKSIDE AVAILABILITY IDIQ - 2014, YEAR 4
(3 Availabilities Projected for 2014)
15-D Fin Stabilizers, General Maintenance JOB 3
16-D Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 3
17-D Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 3
18-D Warping Capstan, Perform Level 2 Maintenance JOB 3
19-D Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 3
20-D Helo Talon Grid, Inspect and Test JOB 3
21-D Grey Water Holding Tanks, Clean and Inspect JOB 3
22-D Sewage Collection and Holding Tanks, Clean and Inspect JOB 3
24-D Grey Water Piping, Clean and Flush 10 LF 3
25-O Sewage Piping, Renew 1 LF 3
26-D Sewage Piping, Clean and Flush 10 LF 3
35-D Compressed Air Receivers, Clean, Inspect, and Test JOB 3
36-O Ballast, 3-B-0-W EA 3
36-O Ballast, 4-75-1-W EA 3
36-O Ballast, 4-75-2-W EA 3
36-O Ballast, 4-103-1-W EA 3
36-O Ballast, 4-103-2-W EA 3
36-O Ballast,4-169-0-W EA 3
36-O Ballast, 4-228-1-W EA 3
36-O Ballast, 4-228-2-W EA 3
36-O Ballast, 4-242-0-W EA 3
37-O Tank (Dirty Oil and Waste), Preserve, “Partial” Job 3
38-O Potable Water, 4-78-1-W EA 3
38-O Potable Water, 4-78-2-W EA 3
38-O Potable Water, 4-94-1-W EA 3
39-O Sewage Tank, 3-82-0-E EA 3
39-O Vacuum Collection Tank, 2-82-0-E EA 3, 40-O Aft, 3-103-0-E EA 3
40-O FWD, 3.82-0-E EA 3
40-O Seal Water Tank EA 3
A-O Composite Labor Rate HOUR 986
B-D GFP Report NSP EA 3 NSP
YR 4 - 2014
(FY'15)
1-O Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 30
2-O Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 60
3-D Chain Lockers, Inspect JOB 6
5-D Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 6
6-D Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 6
7-D Vent Ducts (Engine Room), Commercial Cleaning JOB 6
8-D Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 6
9-D Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 6
10-O Chill Water Piping, Renew 1 LF 18
11-O Feed/Jacket Water Piping, Renew 1 LF 18
12-O Potable Water Piping, Renew 1 LF 18
13-D Potable Water Pneumatic Tank, Clean and Inspect JOB 6
14-O Fuel Piping, Renew 1 LF 6
270 DOCKSIDE AVAILABILITY IDIQ - 2015, YEAR 5
(6 Availabilities Projected for 2015)
15-D Fin Stabilizers, General Maintenance JOB 6
16-D Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 6
17-D Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 6
18-D Warping Capstan, Perform Level 2 Maintenance JOB 6
19-D Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 6
20-D Helo Talon Grid, Inspect and Test JOB 6
21-D Grey Water Holding Tanks, Clean and Inspect JOB 6
22-D Sewage Collection and Holding Tanks, Clean and Inspect JOB 6
24-D Grey Water Piping, Clean and Flush 10 LF 6
25-O Sewage Piping, Renew 1 LF 6
26-D Sewage Piping, Clean and Flush 10 LF 6
35-D Compressed Air Receivers, Clean, Inspect, and Test JOB 6
36-O Ballast, 3-B-0-W EA 6
36-O Ballast, 4-75-1-W EA 6
36-O Ballast, 4-75-2-W EA 6
36-O Ballast, 4-103-1-W EA 6
36-O Ballast, 4-103-2-W EA 6
36-O Ballast,4-169-0-W EA 6
36-O Ballast, 4-228-1-W EA 6
36-O Ballast, 4-228-2-W EA 6
36-O Ballast, 4-242-0-W EA 6
37-O Tank (Dirty Oil and Waste), Preserve, “Partial” Job 6
38-O Potable Water, 4-78-1-W EA 6
38-O Potable Water, 4-78-2-W EA 6
38-O Potable Water, 4-94-1-W EA 6
39-O Sewage Tank, 3-82-0-E EA 6
39-O Vacuum Collection Tank, 2-82-0-E EA 6, 40-O Aft, 3-103-0-E EA 6
40-O FWD, 3.82-0-E EA 6
40-O Seal Water Tank EA 6
A-O Composite Labor Rate HOUR 2,811
B-D GFP Report NSP EA 6 NSP
YR 5 - 2015