270 DS IDIQ Est R5_BLANK 111910 Issued.pdf

PDF 129 KB Posted

Attached to
WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS DOCKSIDE REPAIRS
Solicitation number
HSCG80-10-R-P45GK4
Issued by

About this file

Schedule of Supplies/Services Summary Sheet and Pricing Sheets

View the file

Other files

File Type Posted
AMEND A0009 PAGE 2.doc DOC document
270 DS IDIQ SPEC R4 111910 Issued.pdf PDF
Amend A0009.pdf PDF
Amend A0008.pdf PDF
270 DS IDIQ Est R4_Blank 110410 Issued.pdf PDF
Amend A0007.pdf PDF
270 DS IDIQ SPEC R3 110410 Issued.pdf PDF
Amend A0006.pdf PDF
270 DS IDIQ Est R3_Blank 102110.pdf PDF
Amend A0005.pdf PDF
270 DS IDIQ Est R3_Blank 102110.pdf PDF
Amend A0004.pdf PDF
AMEND A0003 PAGE 2.doc DOC document
270 IDIQ DS CUTTER CONTACTS.pdf PDF
270 DS IDIQ SPEC R2 092410 —
Amend A0003.pdf PDF
SOSS.pdf PDF
AMEND 0002.pdf PDF
AMEND A0001.pdf PDF
HSCG80-10-R-P45GK4 SOLICITATION.doc DOC document
SF33.pdf PDF
270 DS IDIQ SPEC R1 Issue TEF 072910.doc DOC document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM DESCRIPTION UNIT YR 1 ITEM

QTY

YR 2 ITEM

QTY

YR 3 ITEM

QTY

YR 4 ITEM

QTY

YR 5 ITEM

QTY

1 Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1 1 1 1 1

2 Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 1 1 1 1 1

3 Chain Lockers, Inspect JOB 1 1 1 1 1

4 Sea Water Piping, Renew 1 LF - - - - -

4.1 1"-2-3/4" O.D. 1 LF 1 1 1 1 1

4 2 3" - 4-3/4" O D 1 LF 1 1 1 1 1

US COAST GUARD WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS

SCHEDULE OF SUPPLIES & SERVICES (SOS&S)

DOCKSIDE AVAILABILITY IDIQ - SUMMARY

This is an IDIQ contract pursuant to Federal Acquisition Regulation (FAR) 16.504 and 52.216-22. The minimum quantity guaranteed to be ordered is $250,000 over the duration of the contract, and the maximum quantity is $8,000,000, also over the duration of the contract. The duration of the contract includes any option periods, if options to extend the term of the contract are exercised.

4.2 3" - 4-3/4" O.D. 1 LF 1 1 1 1 1

4.3 5" - 7-3/4" O.D. 1 LF 1 1 1 1 1

4.4 8" - 10" O.D. 1 LF 1 1 1 1 1

5 Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1 1 1 1 1

6 Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1 1 1 1 1

7 Vent Ducts (Engine Room), Commercial Cleaning JOB 1 1 1 1 1

8 Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1 1 1 1 1

9 Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1 1 1 1 1

10 Chill Water Piping, Renew 1 LF - - - - -

10.1 1"-2-3/4" O.D. 1 LF 1 1 1 1 1

10.2 3" - 4-3/4" O.D. 1 LF 1 1 1 1 1

10.3 5" - 7-3/4" O.D. 1 LF 1 1 1 1 1

11 Feed/Jacket Water Piping, Renew 1 LF - - - - -

11.1 1"-2-3/4" O.D. 1 LF 1 1 1 1 1

11.2 3" - 4-3/4" O.D. 1 LF 1 1 1 1 1

11.3 5" - 7-3/4" O.D. 1 LF 1 1 1 1 1

12 Potable Water Piping, Renew 1 LF - - - - -

270 DS IDIQ Est R5_BLANK 111910 Issued Page 1

12.1 1"-2-3/4" O.D. 1 LF 1 1 1 1 1

12.2 3" - 4-3/4" O.D. 1 LF 1 1 1 1 1

12.3 5" - 7-3/4" O.D. 1 LF 1 1 1 1 1

13 Potable Water Pneumatic Tank, Clean and Inspect JOB 1 1 1 1 1

14 Fuel Piping, Renew 1 LF - - - - -

14.1 1"-2-3/4" O.D. 1 LF 1 1 1 1 1

14.2 3" - 4-3/4" O.D. 1 LF 1 1 1 1 1

14.3 5" - 7-3/4" O.D. 1 LF 1 1 1 1 1

15 Fin Stabilizers, General Maintenance JOB 1 1 1 1 1

16 Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1 1 1 1 1

17 Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1 1 1 1 1

181 Warping Capstan, Perform Level 2 Maintenance JOB 1 1 1 1 1

19 Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1 1 1 1 1

20 Helo Talon Grid, Inspect and Test JOB 1 1 1 1 1

21 Grey Water Holding Tanks, Clean and Inspect JOB 1 1 1 1 1

22 Sewage Collection and Holding Tanks, Clean and Inspect JOB 1 1 1 1 1

23 Work Item Deleted Job 1 1 1 1 1

24 Grey Water Piping, Clean and Flush 10 LF 1 1 1 1 1

25 Sewage Piping, Renew 1 LF - - - - -25 Sewage Piping, Renew 1 LF - - - - -

25.1 1"-2-3/4" O.D. 1 LF 1 1 1 1 1

25.2 3" - 4-3/4" O.D. 1 LF 1 1 1 1 1

25.3 5" - 7-3/4" O.D. 1 LF 1 1 1 1 1

26 Sewage Piping, Clean and Flush 10 LF 1 1 1 1 1

27 Tanks (Ballast), Preserve “100%” EA - - - - -

27.1 Ballast, 3-B-0-W EA 1 1 1 1 1

27.2 Ballast, 4-75-1-W EA 1 1 1 1 1

27.3 Ballast, 4-75-2-W EA 1 1 1 1 1

27.4 Ballast, 4-103-1-W EA 1 1 1 1 1

27.5 Ballast, 4-103-2-W EA 1 1 1 1 1

27.6 Ballast,4-169-0-W EA 1 1 1 1 1

27.7 Ballast, 4-228-1-W EA 1 1 1 1 1

27.8 Ballast, 4-228-2-W EA 1 1 1 1 1

27.9 Ballast, 4-242-0-W EA 1 1 1 1 1

28 Tank (Dirty Oil and Waste), Preserve “100%” JOB 1 1 1 1 1

29 Tanks (Potable Water), Preserve “100%” - - - - - -

270 DS IDIQ Est R5_BLANK 111910 Issued Page 2

29.1 Potable Water, 4-78-1-W EA 1 1 1 1 1

29.2 Potable Water, 4-78-2-W EA 1 1 1 1 1

29.3 Potable Water, 4-94-1-W EA 1 1 1 1 1

30 Tanks (Sewage and Vacuum Collection), Preserve “100%” - - - - - -

30.1 Sewage Tank, 3-82-0-E EA 1 1 1 1 1

30.2 Vacuum Collection Tank, 2-82-0-E EA 1 1 1 1 1

31 Tanks (Grey Water Holding), Preserve “100% - 1 1 1 1 1

31.1 Aft, 3-103-0-E EA 1 1 1 1 1

31.2 FWD, 3.82-0-E EA 1 1 1 1 1

31.3 Seal Water Tank EA 1 1 1 1 1

32 Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - - - - -

32.1 Watertight Door, 12" x 18" EA 1 1 1 1 1

32.2 Watertight Door, 18" x 36" EA 1 1 1 1 1

32.3 Watertight Door, 33" x 66" EA 1 1 1 1 1

32.4 Scuttle, Round, 12" Dia. EA 1 1 1 1 1

32.5 Scuttle, Round, 14" Dia. EA 1 1 1 1 1

32.6 Scuttle, Round, 18" Dia. EA 1 1 1 1 1

32.7 Scuttle, Round, 21" Dia. EA 1 1 1 1 1

32.8 Scuttle, Round, 24" Dia. EA 1 1 1 1 132.8 Scuttle, Round, 24 Dia. EA 1 1 1 1 1

33 Watertight Doors and Scuttles (External), Renew - - - - - -

33.1 Watertight Door, 12" x 18" EA 1 1 1 1 1

33.2 Watertight Door, 18" x 36" EA 1 1 1 1 1

33.3 Watertight Door, 33" x 66" EA 1 1 1 1 1

33.4 Scuttle, Round, 12" Dia. EA 1 1 1 1 1

33.5 Scuttle, Round, 14" Dia. EA 1 1 1 1 1

33.6 Scuttle, Round, 18" Dia. EA 1 1 1 1 1

33.7 Scuttle, Round, 21" Dia. EA 1 1 1 1 1

33.8 Scuttle, Round, 24" Dia. EA 1 1 1 1 1

34 Piping Insulation, Renew - - - - - -

34.1 For interior gas, steam, hot water (jacket water only), and oil piping systems: - 1 1 1 1 1

34.2 3/4" - 2" O.D. pipe dia. 10 LF 1 1 1 1 1

34.3 2-1/4" - 4" O.D. pipe dia. 10 LF 1 1 1 1 1

34.4 4-1/4" - 6" O.D. pipe dia. 10 LF 1 1 1 1 1

34.5 For interior refrigerant (LP side only), hot water, cold water, and chill water piping s stems:

34.6 3/4" - 2" O.D. pipe dia. 10 LF 1 1 1 1 1

270 DS IDIQ Est R5_BLANK 111910 Issued Page 3

34.7 2-1/4" - 4" O.D. pipe dia. 10 LF 1 1 1 1 1

34.8 4-1/4" - 6" O.D. pipe dia. 10 LF 1 1 1 1 1

35 Compressed Air Receivers, Clean, Inspect, and Test JOB 1 1 1 1 1

36 Tanks (Ballast), Preserve, "Partial" - - - - - -

36.1 Ballast, 3-B-0-W EA 1 1 1 1 1

36.2 Ballast, 4-75-1-W EA 1 1 1 1 1

36.3 Ballast, 4-75-2-W EA 1 1 1 1 1

36.4 Ballast, 4-103-1-W EA 1 1 1 1 1

36.5 Ballast, 4-103-2-W EA 1 1 1 1 1

36.6 Ballast,4-169-0-W EA 1 1 1 1 1

36.7 Ballast, 4-228-1-W EA 1 1 1 1 1

36.8 Ballast, 4-228-2-W EA 1 1 1 1 1

36.9 Ballast, 4-242-0-W EA 1 1 1 1 1

37 Tank (Dirty Oil and Waste), Preserve, “Partial” Job 1 1 1 1 1

38 Tanks (Potable Water), Preserve “Partial” - - - - - -

38.1 Potable Water, 4-78-1-W EA 1 1 1 1 1

38.2 Potable Water, 4-78-2-W EA 1 1 1 1 1

38.3 Potable Water, 4-94-1-W EA 1 1 1 1 1

39 Tanks (Sewage Holding), Preserve, “Partial” - - - - - -39 Tanks (Sewage Holding), Preserve, Partial - - - - - -

39.1 Sewage Tank, 3-82-0-E EA 1 1 1 1 1

39.2 Vacuum Collection Tank, 2-82-0-E EA 1 1 1 1 1

40 Tanks (Grey Water Holding), Preserve, “Partial” - - - - - -

40.1 Aft, 3-103-0-E EA 1 1 1 1 1

40.2 FWD, 3.82-0-E EA 1 1 1 1 1

40.3 Seal Water Tank EA 1 1 1 1 1

41 Tanks (Ballast), Clean and Inspect - - - - - -

41.1 3-B-0-W EA 1 1 1 1 1

41.2 4-75-1-W EA 1 1 1 1 1

41.3 4-75-2-W EA 1 1 1 1 1

41.4 4-103-1-W EA 1 1 1 1 1

41.5 4-103-2-W EA 1 1 1 1 1

41.6 4-169-0-W EA 1 1 1 1 1

41.7 4-228-1-W EA 1 1 1 1 1

41.8 4-228-2-W EA 1 1 1 1 1

41.9 4-242-0-W EA 1 1 1 1 1

270 DS IDIQ Est R5_BLANK 111910 Issued Page 4

42 Tanks (Dirty Oil and Waste), Clean and Inspect - - - - - -

42.1 4-165-1-F EA 1 1 1 1 1

42.2 4-169-1-F EA 1 1 1 1 1

43 Tanks (Lube Oil), Clean and Inspect EA 1 1 1 1 1

44 Tanks (MP Fuel Service), Clean and Inspect - - - - - -

44.1 2-228-1-F EA 1 1 1 1 1

44.2 4-165-3-F EA 1 1 1 1 1

44.3 4-165-4-F EA 1 1 1 1 1

45 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - - - - - -

45.1 4-26-1-F EA 1 1 1 1 1

45.2 4-26-2-F EA 1 1 1 1 1

45.3 4-47-1-F EA 1 1 1 1 1

45.4 4-47-2-F EA 1 1 1 1 1

45.5 4-82-0-F EA 1 1 1 1 1

45.6 4-82-1-F EA 1 1 1 1 1

45.7 4-82-2-F EA 1 1 1 1 1

45.8 4-96-0-F EA 1 1 1 1 1

45.9 4-103-0-F EA 1 1 1 1 1

45.10 4-165-2-F EA 1 1 1 1 145.10 4-165-2-F EA 1 1 1 1 1

45.11 4-207-0-F EA 1 1 1 1 1

45.12 4-207-1-F EA 1 1 1 1 1

45.13 4-207-2-F EA 1 1 1 1 1

46 Tanks (MP Fuel), Preserve "100%" - - - - - -

46.1 2-228-1-F EA 1 1 1 1 1

46.2 4-26-1-F EA 1 1 1 1 1

46.3 4-26-2-F EA 1 1 1 1 1

46.4 4-47-1-F EA 1 1 1 1 1

46.5 4-47-2-F EA 1 1 1 1 1

46.6 4-82-0-F EA 1 1 1 1 1

46.7 4-82-1-F EA 1 1 1 1 1

46.8 4-82-2-F EA 1 1 1 1 1

46.9 4-96-0-F EA 1 1 1 1 1

46.10 4-103-0-F EA 1 1 1 1 1

46.11 4-165-2-F EA 1 1 1 1 1

46.12 4-165-3-F EA 1 1 1 1 1

270 DS IDIQ Est R5_BLANK 111910 Issued Page 5

46.13 4-165-4-F EA 1 1 1 1 1

46.14 4-207-0-F EA 1 1 1 1 1

46.15 4-207-1-F EA 1 1 1 1 1

46.16 4-207-2-F EA 1 1 1 1 1

47 Tanks (Hydraulic Oil), Clean and Inspect EA 1 1 1 1 1

48 Tanks (Aviation Fuel Service), Clean and Inspect - - - - - -

48.1 3-190-1-J EA 1 1 1 1 1

48.2 3-190-2-J EA 1 1 1 1 1

49 Tanks (Aviation Fuel Service), Preserve"100%" - - - - - -

49.1 3-190-1-J EA 1 1 1 1 1

49.2 3-190-2-J EA 1 1 1 1 1

50 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect - - - - - -

50.1 4-186-1-J EA 1 1 1 1 1

50.2 4-186-2-J EA 1 1 1 1 1

50.3 4-190-1-J EA 1 1 1 1 1

50.4 4-190-2-J EA 1 1 1 1 1

51 Tanks (Aviation Fuel Stowage and Overflow), Preserve "100%" - - - - - -

51.1 4-186-1-J EA 1 1 1 1 1

51.2 4-186-2-J EA 1 1 1 1 151.2 4-186-2-J EA 1 1 1 1 1

51.3 4-190-1-J EA 1 1 1 1 1

51.4 4-190-2-J EA 1 1 1 1 1

52 Insulation, Ventillation Ducting, Renew - - - - - -

52.1 Thermal Blanket Insulation - 1" 10 SQ-FT 1 1 1 1 1

52.2 Thermal Blanket Insulation - 2" 10 SQ-FT 1 1 1 1 1

52.3 Thermal Board Insulation - 1" 10 SQ-FT 1 1 1 1 1

52.4 Thermal Board Insulation - 2" 10 SQ-FT 1 1 1 1 1

52.5 Acoustic Blanket Insulation - 2" 10 SQ-FT 1 1 1 1 1

52.6 Acoustic Board Insulation - 1" 10 SQ-FT 1 1 1 1 1

52.7 Acoustic Board Insulation - 2" 10 SQ-FT 1 1 1 1 1

53 Insulation, Bulkhead / Overhead, Renew - - - - - -

53.1 Bulkhead / Overhead Surfaces: Non-beam covering - - - - - -

53.2 Thermal Blanket Insulation - 1" 10 SQ-FT 1 1 1 1 1

53.3 Thermal Blanket Insulation - 2" 10 SQ-FT 1 1 1 1 1

53.4 Thermal Board Insulation - 1" 10 SQ-FT 1 1 1 1 1

53.5 Thermal Board Insulation - 2" 10 SQ-FT 1 1 1 1 1

270 DS IDIQ Est R5_BLANK 111910 Issued Page 6

53.6 Acoustic Blanket Insulation - 2" 10 SQ-FT 1 1 1 1 1

53.7 Acoustic Board Insulation - 1" 10 SQ-FT 1 1 1 1 1

53.8 Acoustic Board Insulation - 2" 10 SQ-FT 1 1 1 1 1

53.9 Bulkhead / Overhead Surfaces: Beam Coverings - - - - - -

53.10 Thermal Blanket Insulation - 1" 10 SQ-FT 1 1 1 1 1

53.11 Thermal Blanket Insulation - 2" 10 SQ-FT 1 1 1 1 1

53.12 Acoustic Blanket Insulation - 2" 10 SQ-FT 1 1 1 1 1

54 Insulation, MDE Exhaust Blankets, Fabricate and Install 10 SQ-FT 1 1 1 1 1

A-O Composite Labor Rate HOUR 1 1 1 1 1

270 DS IDIQ Est R5_BLANK 111910 Issued Page 7

ITEM DESCRIPTION UNIT PRICE UNIT ITEM QTY BASE YEAR EXTENDED

PRICE (FY'11)

1 Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1

2 Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 1

3 Chain Lockers, Inspect JOB 1

4 Sea Water Piping, Renew - - - -

4.1 1"-2-3/4" O.D. 1 LF 1

4.2 3" - 4-3/4" O.D. 1 LF 1

4.3 5" - 7-3/4" O.D. 1 LF 1

4.4 8" - 10" O.D. 1 LF 1

5 Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1

6 Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1

7 Vent Ducts (Engine Room), Commercial Cleaning JOB 1

8 Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1

9 Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1

10 Chill Water Piping, Renew - - - -

10.1 1"-2-3/4" O.D. 1 LF 1

10.2 3" - 4-3/4" O.D. 1 LF 1

10.3 5" - 7-3/4" O.D. 1 LF 1

11 Feed/Jacket Water Piping, Renew - - - -

11.1 1"-2-3/4" O.D. 1 LF 1

11.2 3" - 4-3/4" O.D. 1 LF 1

11.3 5" - 7-3/4" O.D. 1 LF 1

12 Potable Water Piping, Renew - - - -

12 1 1"-2-3/4" O D 1 LF 1

SCHEDULE OF SUPPLIES & SERVICES (SOS&S)

270 DOCKSIDE AVAILABILITY IDIQ - 2011, BASE YEAR

(4 Availabilities Projected for 2011)

US COAST GUARD WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS

12.1 1"-2-3/4" O.D. 1 LF 1

12.2 3" - 4-3/4" O.D. 1 LF 1

12.3 5" - 7-3/4" O.D. 1 LF 1

13 Potable Water Pneumatic Tank, Clean and Inspect JOB 1

14 Fuel Piping, Renew - - - -

14.1 1"-2-3/4" O.D. 1 LF 1

14.2 3" - 4-3/4" O.D. 1 LF 1

14.3 5" - 7-3/4" O.D. 1 LF 1

15 Fin Stabilizers, General Maintenance JOB 1

16 Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1

17 Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1

18 Warping Capstan, Perform Level 2 Maintenance JOB 1

19 Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1

20 Helo Talon Grid, Inspect and Test JOB 1

21 Grey Water Holding Tanks, Clean and Inspect JOB 1

22 Sewage Collection and Holding Tanks, Clean and Inspect JOB 1

23 Work Item Deleted - Job 1 -

24 Grey Water Piping, Clean and Flush 10 LF 1

25 Sewage Piping, Renew - - - -

25.1 1"-2-3/4" O.D. 1 LF 1

25.2 3" - 4-3/4" O.D. 1 LF 1

25.3 5" - 7-3/4" O.D. 1 LF 1

26 Sewage Piping, Clean and Flush 10 LF 1

27 Tanks (Ballast), Preserve “100%” - - - -

27.1 Ballast, 3-B-0-W EA 1

27.2 Ballast, 4-75-1-W EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued14

27.3 Ballast, 4-75-2-W EA 1

27.4 Ballast, 4-103-1-W EA 1

27.5 Ballast, 4-103-2-W EA 1

27.6 Ballast,4-169-0-W EA 1

27.7 Ballast, 4-228-1-W EA 1

27.8 Ballast, 4-228-2-W EA 1

27.9 Ballast, 4-242-0-W EA 1

28 Tank (Dirty Oil and Waste), Preserve “100%” JOB 1

29 Tanks (Potable Water), Preserve “100%” - - - -

29.1 Potable Water, 4-78-1-W EA 1

29.1 Potable Water, 4-78-2-W EA 1

29.3 Potable Water, 4-94-1-W EA 1

30 Tanks (Sewage and Vacuum Collection), Preserve “100%” - -

30.1 Sewage Tank, 3-82-0-E EA 1

30.2 Vacuum Collection Tank, 2-82-0-E EA 1

31 Tanks (Grey Water Holding), Preserve “100% - - 1 -

31.1 Aft, 3-103-0-E EA 1

31.2 FWD, 3.82-0-E EA 1

31.3 Seal Water Tank EA 1

32 Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - - -

32.1 Watertight Door, 12" x 18" EA 1

32.2 Watertight Door, 18" x 36" EA 1

32.3 Watertight Door, 33" x 66" EA 1

32.4 Scuttle, Round, 12" Dia. EA 1

32.5 Scuttle, Round, 14" Dia. EA 1

32.6 Scuttle, Round, 18" Dia. EA 1

32.7 Scuttle, Round, 21" Dia. EA 1

32.8 Scuttle, Round, 24" Dia. EA 1

33 Watertight Doors and Scuttles (External), Renew - - - -

33.1 Watertight Door, 12" x 18" EA 1

33 2 Watertight Door 18" x 36" EA 133.2 Watertight Door, 18" x 36" EA 1

33.3 Watertight Door, 33" x 66" EA 1

33.4 Scuttle, Round, 12" Dia. EA 1

33.5 Scuttle, Round, 14" Dia. EA 1

33.6 Scuttle, Round, 18" Dia. EA 1

33.7 Scuttle, Round, 21" Dia. EA 1

33.8 Scuttle, Round, 24" Dia. EA 1

34 Piping Insulation, Renew - - - -

34.1 For interior gas, steam, hot water (jacket water only), and oil piping systems: - - 1 -

34.2 3/4" - 2" O.D. pipe dia. 10 LF 1

34.3 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.4 4-1/4" - 6" O.D. pipe dia. 10 LF 1

34.5 For interior refrigerant (LP side only), hot water, cold water, and chill water piping systems:

34.6 3/4" - 2" O.D. pipe dia. 10 LF 1

34.7 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.8 4-1/4" - 6" O.D. pipe dia. 10 LF 1

35 Compressed Air Receivers, Clean, Inspect, and Test JOB 1

36 Tanks (Ballast), Preserve, “Partial” - - - -

36.1 Ballast, 3-B-0-W EA 1

36.2 Ballast, 4-75-1-W EA 1

36.3 Ballast, 4-75-2-W EA 1

36.4 Ballast, 4-103-1-W EA 1

36.5 Ballast, 4-103-2-W EA 1

36.6 Ballast,4-169-0-W EA 1

36.7 Ballast, 4-228-1-W EA 1

36.8 Ballast, 4-228-2-W EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued24

36.9 Ballast, 4-242-0-W EA 1

37 Tank (Dirty Oil and Waste), Preserve, “Partial” Job 1

38 Tanks (Potable Water), Preserve “Partial” - - - -

38.1 Potable Water, 4-78-1-W EA 1

38.2 Potable Water, 4-78-2-W EA 1

38.3 Potable Water, 4-94-1-W EA 1

39 Tanks (Sewage Holding), Preserve, “Partial” - - - -

39.1 Sewage Tank, 3-82-0-E EA 1

39.2 Vacuum Collection Tank, 2-82-0-E EA 1

40 Tanks (Grey Water Holding), Preserve, “Partial” - - - -

40.1 Aft, 3-103-0-E EA 1

40.2 FWD, 3.82-0-E EA 1

40.3 Seal Water Tank EA 1

41 Tanks (Ballast), Clean and Inspect - - - -

41.1 3-B-0-W EA 1

41.2 4-75-1-W EA 1

41.3 4-75-2-W EA 1

41.4 4-103-1-W EA 1

41.5 4-103-2-W EA 1

41.6 4-169-0-W EA 1

41.7 4-228-1-W EA 1

41.8 4-228-2-W EA 1

41.9 4-242-0-W EA 1

42 Tanks (Dirty Oil and Waste), Clean and Inspect - - - -

42.1 4-165-1-F EA 1

42.2 4-169-1-F EA 1

43 Tanks (Lube Oil), Clean and Inspect EA 1

44 Tanks (MP Fuel Service), Clean and Inspect - - - -

44.1 2-228-1-F EA 1

44.2 4-165-3-F EA 1

44 3 4-165-4-F EA 144.3 4-165-4-F EA 1

45 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - - - -

45.1 4-26-1-F EA 1

45.2 4-26-2-F EA 1

45.3 4-47-1-F EA 1

45.4 4-47-2-F EA 1

45.5 4-82-0-F EA 1

45.6 4-82-1-F EA 1

45.7 4-82-2-F EA 1

45.8 4-96-0-F EA 1

45.9 4-103-0-F EA 1

45.10 4-165-2-F EA 1

45.11 4-207-0-F EA 1

45.12 4-207-1-F EA 1

45.13 4-207-2-F EA 1

46 Tanks (MP Fuel), Preserve "100%" - - - -

46.1 2-228-1-F EA 1

46.2 4-26-1-F EA 1

46.3 4-26-2-F EA 1

46.4 4-47-1-F EA 1

46.5 4-47-2-F EA 1

46.6 4-82-0-F EA 1

46.7 4-82-1-F EA 1

46.8 4-82-2-F EA 1

46.9 4-96-0-F EA 1

46.10 4-103-0-F EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued34

46.11 4-165-2-F EA 1

46.12 4-165-3-F EA 1

46.13 4-165-4-F EA 1

46.14 4-207-0-F EA 1

46.15 4-207-1-F EA 1

46.16 4-207-2-F EA 1

47 Tanks (Hydraulic Oil), Clean and Inspect EA 1

48 Tanks (Aviation Fuel Service), Clean and Inspect - - - -

48.1 3-190-1-J EA 1

48.2 3-190-2-J EA 1

49 Tanks (Aviation Fuel Service), Preserve"100%" - - - -

49.1 3-190-1-J EA 1

49.2 3-190-2-J EA 1

50 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect - - - -

50.1 4-186-1-J EA 1

50.2 4-186-2-J EA 1

50.3 4-190-1-J EA 1

50.4 4-190-2-J EA 1

51 Tanks (Aviation Fuel Stowage and Overflow), Preserve "100%" - - - -

51.1 4-186-1-J EA 1

51.2 4-186-2-J EA 1

51.3 4-190-1-J EA 1

51.4 4-190-2-J EA 1

52 Insulation, Ventillation Ducting, Renew - - - -

52.1 Thermal Blanket Insulation - 1" 10 SQ-FT 1

52.2 Thermal Blanket Insulation - 2" 10 SQ-FT 1

52.3 Thermal Board Insulation - 1" 10 SQ-FT 1

52.4 Thermal Board Insulation - 2" 10 SQ-FT 1

52.5 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52.6 Acoustic Board Insulation - 1" 10 SQ-FT 1

52 7 Acoustic Board Insulation - 2" 10 SQ-FT 152.7 Acoustic Board Insulation - 2" 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew - - - -

53.1 Bulkhead / Overhead Surfaces: Non-beam covering - - - -

53.2 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.3 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.4 Thermal Board Insulation - 1" 10 SQ-FT 1

53.5 Thermal Board Insulation - 2" 10 SQ-FT 1

53.6 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

53.7 Acoustic Board Insulation - 1" 10 SQ-FT 1

53.8 Acoustic Board Insulation - 2" 10 SQ-FT 1

53.9 Bulkhead / Overhead Surfaces: Beam Coverings - - - -

53.10 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.11 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.12 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

54 Insulation, MDE Exhaust Blankets, Fabricate and Install 10 SQ-FT 1

A-O Composite Labor Rate HOUR 1

B-D GFP Report NSP EA 1 NSP

Total Price

270 DS IDIQ Est R5_BLANK 111910 Issued44

ITEM DESCRIPTION UNIT PRICE UNIT ITEM QTY EXTENDED PRICE

(FY'12)

1 Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1

2 Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 1

3 Chain Lockers, Inspect JOB 1

4 Sea Water Piping, Renew - - - -

4.1 1"-2-3/4" O.D. 1 LF 1

4.2 3" - 4-3/4" O.D. 1 LF 1

4.3 5" - 7-3/4" O.D. 1 LF 1

4.4 8" - 10" O.D. 1 LF 1

5 Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1

6 Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1

7 Vent Ducts (Engine Room), Commercial Cleaning JOB 1

8 Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1

9 Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1

10 Chill Water Piping, Renew - - - -

10.1 1"-2-3/4" O.D. 1 LF 1

10.2 3" - 4-3/4" O.D. 1 LF 1

10.3 5" - 7-3/4" O.D. 1 LF 1

11 Feed/Jacket Water Piping, Renew - - - -

11.1 1"-2-3/4" O.D. 1 LF 1

11.2 3" - 4-3/4" O.D. 1 LF 1

11.3 5" - 7-3/4" O.D. 1 LF 1

12 Potable Water Piping, Renew - - - -

12.1 1"-2-3/4" O.D. 1 LF 1

SCHEDULE OF SUPPLIES & SERVICES (SOS&S)

270 DOCKSIDE AVAILABILITY IDIQ - 2012, YEAR 2

(2 Availabilities Projected for 2012)

US COAST GUARD WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS

270 DS IDIQ Est R5_BLANK 111910 Issued

12.2 3" - 4-3/4" O.D. 1 LF 1

12.3 5" - 7-3/4" O.D. 1 LF 1

13 Potable Water Pneumatic Tank, Clean and Inspect JOB 1

14 Fuel Piping, Renew - - - -

14.1 1"-2-3/4" O.D. 1 LF 1

14.2 3" - 4-3/4" O.D. 1 LF 1

14.3 5" - 7-3/4" O.D. 1 LF 1

15 Fin Stabilizers, General Maintenance JOB 1

16 Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1

17 Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1

18 Warping Capstan, Perform Level 2 Maintenance JOB 1

19 Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1

20 Helo Talon Grid, Inspect and Test JOB 1

21 Grey Water Holding Tanks, Clean and Inspect JOB 1

22 Sewage Collection and Holding Tanks, Clean and Inspect JOB 1

23 Work Item Deleted - Job 1 -

24 Grey Water Piping, Clean and Flush 10 LF 1

25 Sewage Piping, Renew - - - -

25.1 1"-2-3/4" O.D. 1 LF 1

25.2 3" - 4-3/4" O.D. 1 LF 1

25.3 5" - 7-3/4" O.D. 1 LF 1

26 Sewage Piping, Clean and Flush 10 LF 1

27 Tanks (Ballast), Preserve “100%” - -

27.1 Ballast, 3-B-0-W EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

27.5 Ballast, 4-103-2-W EA 1

27.6 Ballast,4-169-0-W EA 1

27.7 Ballast, 4-228-1-W EA 1

27.8 Ballast, 4-228-2-W EA 1

27.9 Ballast, 4-242-0-W EA 1

28 Tank (Dirty Oil and Waste), Preserve “100%” JOB 1

29 Tanks (Potable Water), Preserve “100%” - -

29.1 Potable Water, 4-78-1-W EA 1

29.1 Potable Water, 4-78-2-W EA 1

29.3 Potable Water, 4-94-1-W EA 1

30 Tanks (Sewage and Vacuum Collection), Preserve “100%” - -

30.1 Sewage Tank, 3-82-0-E EA 1

30.2 Vacuum Collection Tank, 2-82-0-E EA 1

31 Tanks (Grey Water Holding), Preserve “100% - 1

31.1 Aft, 3-103-0-E EA 1

31.2 FWD, 3.82-0-E EA 1

31.3 Seal Water Tank EA 1

32 Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - -

32.1 Watertight Door, 12" x 18" EA 1

32.2 Watertight Door, 18" x 36" EA 1

32.3 Watertight Door, 33" x 66" EA 1

32.4 Scuttle, Round, 12" Dia. EA 1

32.5 Scuttle, Round, 14" Dia. EA 1

32.6 Scuttle, Round, 18" Dia. EA 1

32.7 Scuttle, Round, 21" Dia. EA 1

32.8 Scuttle, Round, 24" Dia. EA 1

33 Watertight Doors and Scuttles (External), Renew - - -

33.1 Watertight Door, 12" x 18" EA 1

33 2 Watertight Door 18" x 36" EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

33.2 Watertight Door, 18" x 36" EA 1

33.3 Watertight Door, 33" x 66" EA 1

33.4 Scuttle, Round, 12" Dia. EA 1

33.5 Scuttle, Round, 14" Dia. EA 1

33.6 Scuttle, Round, 18" Dia. EA 1

33.7 Scuttle, Round, 21" Dia. EA 1

33.8 Scuttle, Round, 24" Dia. EA 1

34 Piping Insulation, Renew - - - -

34.1 For interior gas, steam, hot water (jacket water only), and oil piping systems: - - 1 -

34.2 3/4" - 2" O.D. pipe dia. 10 LF 1

34.3 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.4 4-1/4" - 6" O.D. pipe dia. 10 LF 1

34.5 For interior refrigerant (LP side only), hot water, cold water, and chill water piping systems:

34.6 3/4" - 2" O.D. pipe dia. 10 LF 1

34.7 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.8 4-1/4" - 6" O.D. pipe dia. 10 LF 1

35 Compressed Air Receivers, Clean, Inspect, and Test JOB 1

36 Tanks (Ballast), Preserve, “Partial” - -

36.1 Ballast, 3-B-0-W EA 1

36.2 Ballast, 4-75-1-W EA 1

36.3 Ballast, 4-75-2-W EA 1

36.4 Ballast, 4-103-1-W EA 1

36.5 Ballast, 4-103-2-W EA 1

36.6 Ballast,4-169-0-W EA 1

36.7 Ballast, 4-228-1-W EA 1

38 Tanks (Potable Water), Preserve “Partial” - -

38.1 Potable Water, 4-78-1-W EA 1

38.2 Potable Water, 4-78-2-W EA 1

38.3 Potable Water, 4-94-1-W EA 1

39 Tanks (Sewage Holding), Preserve, “Partial” - -

39.1 Sewage Tank, 3-82-0-E EA 1

39.2 Vacuum Collection Tank, 2-82-0-E EA 1

40 Tanks (Grey Water Holding), Preserve, “Partial” - -

40.1 Aft, 3-103-0-E EA 1

40.2 FWD, 3.82-0-E EA 1

40.3 Seal Water Tank EA 1

41 Tanks (Ballast), Clean and Inspect - - - -

41.1 3-B-0-W EA 1

41.2 4-75-1-W EA 1

41.3 4-75-2-W EA 1

41.4 4-103-1-W EA 1

41.5 4-103-2-W EA 1

41.6 4-169-0-W EA 1

41.7 4-228-1-W EA 1

41.8 4-228-2-W EA 1

41.9 4-242-0-W EA 1

42 Tanks (Dirty Oil and Waste), Clean and Inspect - - - -

42.1 4-165-1-F EA 1

42.2 4-169-1-F EA 1

43 Tanks (Lube Oil), Clean and Inspect EA 1

44 Tanks (MP Fuel Service), Clean and Inspect - - - -

44.1 2-228-1-F EA 1

44.2 4-165-3-F EA 1

44 3 4-165-4-F EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

44.3 4-165-4-F EA 1

45 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - - - -

45.1 4-26-1-F EA 1

45.2 4-26-2-F EA 1

45.3 4-47-1-F EA 1

45.4 4-47-2-F EA 1

45.5 4-82-0-F EA 1

45.6 4-82-1-F EA 1

45.7 4-82-2-F EA 1

45.8 4-96-0-F EA 1

45.9 4-103-0-F EA 1

45.10 4-165-2-F EA 1

45.11 4-207-0-F EA 1

45.12 4-207-1-F EA 1

45.13 4-207-2-F EA 1

46 Tanks (MP Fuel), Preserve "100%" - - - -

46.1 2-228-1-F EA 1

46.2 4-26-1-F EA 1

46.3 4-26-2-F EA 1

46.4 4-47-1-F EA 1

46.5 4-47-2-F EA 1

46.6 4-82-0-F EA 1

46.7 4-82-1-F EA 1

46.8 4-82-2-F EA 1

46.9 4-96-0-F EA 1

46.13 4-165-4-F EA 1

46.14 4-207-0-F EA 1

46.15 4-207-1-F EA 1

46.16 4-207-2-F EA 1

47 Tanks (Hydraulic Oil), Clean and Inspect EA 1

48 Tanks (Aviation Fuel Service), Clean and Inspect - - - -

48.1 3-190-1-J EA 1

48.2 3-190-2-J EA 1

49 Tanks (Aviation Fuel Service), Preserve"100%" - - - -

49.1 3-190-1-J EA 1

49.2 3-190-2-J EA 1

50 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect - - - -

50.1 4-186-1-J EA 1

50.2 4-186-2-J EA 1

50.3 4-190-1-J EA 1

50.4 4-190-2-J EA 1

51 Tanks (Aviation Fuel Stowage and Overflow), Preserve "100%" - - - -

51.1 4-186-1-J EA 1

51.2 4-186-2-J EA 1

51.3 4-190-1-J EA 1

51.4 4-190-2-J EA 1

52 Insulation, Ventillation Ducting, Renew - - - -

52.1 Thermal Blanket Insulation - 1" 10 SQ-FT 1

52.2 Thermal Blanket Insulation - 2" 10 SQ-FT 1

52.3 Thermal Board Insulation - 1" 10 SQ-FT 1

52.4 Thermal Board Insulation - 2" 10 SQ-FT 1

52.5 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52.6 Acoustic Board Insulation - 1" 10 SQ-FT 1

52 7 Acoustic Board Insulation - 2" 10 SQ-FT 1

270 DS IDIQ Est R5_BLANK 111910 Issued

52.7 Acoustic Board Insulation - 2" 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew - - - -

53.1 Bulkhead / Overhead Surfaces: Non-beam covering - - - -

53.2 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.3 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.4 Thermal Board Insulation - 1" 10 SQ-FT 1

53.5 Thermal Board Insulation - 2" 10 SQ-FT 1

53.6 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

53.7 Acoustic Board Insulation - 1" 10 SQ-FT 1

53.8 Acoustic Board Insulation - 2" 10 SQ-FT 1

53.9 Bulkhead / Overhead Surfaces: Beam Coverings - - - -

53.10 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.11 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.12 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

A-O Composite Labor Rate HOUR 1

B-D GFP Report NSP EA 1 NSP

(FY'13)

1 Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1

2 Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 1

3 Chain Lockers, Inspect JOB 1

4 Sea Water Piping, Renew - - - -

4.1 1"-2-3/4" O.D. 1 LF 1

4.2 3" - 4-3/4" O.D. 1 LF 1

4.3 5" - 7-3/4" O.D. 1 LF 1

4.4 8" - 10" O.D. 1 LF 1

5 Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1

6 Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1

7 Vent Ducts (Engine Room), Commercial Cleaning JOB 1

8 Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1

9 Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1

10 Chill Water Piping, Renew - - - -

10.1 1"-2-3/4" O.D. 1 LF 1

10.2 3" - 4-3/4" O.D. 1 LF 1

10.3 5" - 7-3/4" O.D. 1 LF 1

11 Feed/Jacket Water Piping, Renew - - - -

11.1 1"-2-3/4" O.D. 1 LF 1

11.2 3" - 4-3/4" O.D. 1 LF 1

11.3 5" - 7-3/4" O.D. 1 LF 1

12 Potable Water Piping, Renew - - - -

12.1 1"-2-3/4" O.D. 1 LF 1

SCHEDULE OF SUPPLIES & SERVICES (SOS&S)

270 DOCKSIDE AVAILABILITY IDIQ - 2013, YEAR 3

(1 Availabilities Projected for 2013)

US COAST GUARD WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS

270 DS IDIQ Est R5_BLANK 111910 Issued

12.2 3" - 4-3/4" O.D. 1 LF 1

12.3 5" - 7-3/4" O.D. 1 LF 1

13 Potable Water Pneumatic Tank, Clean and Inspect JOB 1

14 Fuel Piping, Renew - - - -

14.1 1"-2-3/4" O.D. 1 LF 1

14.2 3" - 4-3/4" O.D. 1 LF 1

14.3 5" - 7-3/4" O.D. 1 LF 1

15 Fin Stabilizers, General Maintenance JOB 1

16 Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1

17 Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1

18 Warping Capstan, Perform Level 2 Maintenance JOB 1

19 Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1

20 Helo Talon Grid, Inspect and Test JOB 1

21 Grey Water Holding Tanks, Clean and Inspect JOB 1

22 Sewage Collection and Holding Tanks, Clean and Inspect JOB 1

23 Work Item Deleted - Job 1 -

24 Grey Water Piping, Clean and Flush 10 LF 1

25 Sewage Piping, Renew - - - -

25.1 1"-2-3/4" O.D. 1 LF 1

25.2 3" - 4-3/4" O.D. 1 LF 1

25.3 5" - 7-3/4" O.D. 1 LF 1

26 Sewage Piping, Clean and Flush 10 LF 1

27 Tanks (Ballast), Preserve “100%” - - - -

27.1 Ballast, 3-B-0-W EA 1

27.5 Ballast, 4-103-2-W EA 1

27.6 Ballast,4-169-0-W EA 1

27.7 Ballast, 4-228-1-W EA 1

27.8 Ballast, 4-228-2-W EA 1

27.9 Ballast, 4-242-0-W EA 1

28 Tank (Dirty Oil and Waste), Preserve “100%” JOB 1

29 Tanks (Potable Water), Preserve “100%” - - - -

29.1 Potable Water, 4-78-1-W EA 1

29.1 Potable Water, 4-78-2-W EA 1

29.3 Potable Water, 4-94-1-W EA 1

30 Tanks (Sewage and Vacuum Collection), Preserve “100%” - -

30.1 Sewage Tank, 3-82-0-E EA 1

30.2 Vacuum Collection Tank, 2-82-0-E EA 1

31 Tanks (Grey Water Holding), Preserve “100% - - 1 -

31.1 Aft, 3-103-0-E EA 1

31.2 FWD, 3.82-0-E EA 1

31.3 Seal Water Tank EA 1

32 Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - - -

32.1 Watertight Door, 12" x 18" EA 1

32.2 Watertight Door, 18" x 36" EA 1

32.3 Watertight Door, 33" x 66" EA 1

32.4 Scuttle, Round, 12" Dia. EA 1

32.5 Scuttle, Round, 14" Dia. EA 1

32.6 Scuttle, Round, 18" Dia. EA 1

32.7 Scuttle, Round, 21" Dia. EA 1

32.8 Scuttle, Round, 24" Dia. EA 1

33 Watertight Doors and Scuttles (External), Renew - - - -

33.1 Watertight Door, 12" x 18" EA 1

33 2 Watertight Door 18" x 36" EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

33.2 Watertight Door, 18" x 36" EA 1

33.3 Watertight Door, 33" x 66" EA 1

33.4 Scuttle, Round, 12" Dia. EA 1

33.5 Scuttle, Round, 14" Dia. EA 1

33.6 Scuttle, Round, 18" Dia. EA 1

33.7 Scuttle, Round, 21" Dia. EA 1

33.8 Scuttle, Round, 24" Dia. EA 1

34 Piping Insulation, Renew - - - -

34.1 For interior gas, steam, hot water (jacket water only), and oil piping systems: - - 1 -

34.2 3/4" - 2" O.D. pipe dia. 10 LF 1

34.3 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.4 4-1/4" - 6" O.D. pipe dia. 10 LF 1

34.5 For interior refrigerant (LP side only), hot water, cold water, and chill water piping systems:

34.6 3/4" - 2" O.D. pipe dia. 10 LF 1

34.7 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.8 4-1/4" - 6" O.D. pipe dia. 10 LF 1

35 Compressed Air Receivers, Clean, Inspect, and Test JOB 1

36 Tanks (Ballast), Preserve, “Partial” - - - -

36.1 Ballast, 3-B-0-W EA 1

36.2 Ballast, 4-75-1-W EA 1

36.3 Ballast, 4-75-2-W EA 1

36.4 Ballast, 4-103-1-W EA 1

36.5 Ballast, 4-103-2-W EA 1

36.6 Ballast,4-169-0-W EA 1

36.7 Ballast, 4-228-1-W EA 1

38 Tanks (Potable Water), Preserve “Partial” - - - -

38.1 Potable Water, 4-78-1-W EA 1

38.2 Potable Water, 4-78-2-W EA 1

38.3 Potable Water, 4-94-1-W EA 1

39 Tanks (Sewage Holding), Preserve, “Partial” - - - -

39.1 Sewage Tank, 3-82-0-E EA 1

39.2 Vacuum Collection Tank, 2-82-0-E EA 1

40 Tanks (Grey Water Holding), Preserve, “Partial” - - - -

40.1 Aft, 3-103-0-E EA 1

40.2 FWD, 3.82-0-E EA 1

40.3 Seal Water Tank EA 1

41 Tanks (Ballast), Clean and Inspect - - - -

41.1 3-B-0-W EA 1

41.2 4-75-1-W EA 1

41.3 4-75-2-W EA 1

41.4 4-103-1-W EA 1

41.5 4-103-2-W EA 1

41.6 4-169-0-W EA 1

41.7 4-228-1-W EA 1

41.8 4-228-2-W EA 1

41.9 4-242-0-W EA 1

42 Tanks (Dirty Oil and Waste), Clean and Inspect - - - -

42.1 4-165-1-F EA 1

42.2 4-169-1-F EA 1

43 Tanks (Lube Oil), Clean and Inspect EA 1

44 Tanks (MP Fuel Service), Clean and Inspect - - - -

44.1 2-228-1-F EA 1

44.2 4-165-3-F EA 1

44 3 4-165-4-F EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

44.3 4-165-4-F EA 1

45 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - - - -

45.1 4-26-1-F EA 1

45.2 4-26-2-F EA 1

45.3 4-47-1-F EA 1

45.4 4-47-2-F EA 1

45.5 4-82-0-F EA 1

45.6 4-82-1-F EA 1

45.7 4-82-2-F EA 1

45.8 4-96-0-F EA 1

45.9 4-103-0-F EA 1

45.10 4-165-2-F EA 1

45.11 4-207-0-F EA 1

45.12 4-207-1-F EA 1

45.13 4-207-2-F EA 1

46 Tanks (MP Fuel), Preserve "100%" - - - -

46.1 2-228-1-F EA 1

46.2 4-26-1-F EA 1

46.3 4-26-2-F EA 1

46.4 4-47-1-F EA 1

46.5 4-47-2-F EA 1

46.6 4-82-0-F EA 1

46.7 4-82-1-F EA 1

46.8 4-82-2-F EA 1

46.9 4-96-0-F EA 1

46.13 4-165-4-F EA 1

46.14 4-207-0-F EA 1

46.15 4-207-1-F EA 1

46.16 4-207-2-F EA 1

47 Tanks (Hydraulic Oil), Clean and Inspect EA 1

48 Tanks (Aviation Fuel Service), Clean and Inspect - - - -

48.1 3-190-1-J EA 1

48.2 3-190-2-J EA 1

49 Tanks (Aviation Fuel Service), Preserve"100%" - - - -

49.1 3-190-1-J EA 1

49.2 3-190-2-J EA 1

50 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect - - - -

50.1 4-186-1-J EA 1

50.2 4-186-2-J EA 1

50.3 4-190-1-J EA 1

50.4 4-190-2-J EA 1

51 Tanks (Aviation Fuel Stowage and Overflow), Preserve "100%" - - - -

51.1 4-186-1-J EA 1

51.2 4-186-2-J EA 1

51.3 4-190-1-J EA 1

51.4 4-190-2-J EA 1

52 Insulation, Ventillation Ducting, Renew - - - -

52.1 Thermal Blanket Insulation - 1" 10 SQ-FT 1

52.2 Thermal Blanket Insulation - 2" 10 SQ-FT 1

52.3 Thermal Board Insulation - 1" 10 SQ-FT 1

52.4 Thermal Board Insulation - 2" 10 SQ-FT 1

52.5 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52.6 Acoustic Board Insulation - 1" 10 SQ-FT 1

52 7 Acoustic Board Insulation - 2" 10 SQ-FT 1

270 DS IDIQ Est R5_BLANK 111910 Issued

52.7 Acoustic Board Insulation - 2" 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew - - - -

53.1 Bulkhead / Overhead Surfaces: Non-beam covering - - - -

53.2 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.3 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.4 Thermal Board Insulation - 1" 10 SQ-FT 1

53.5 Thermal Board Insulation - 2" 10 SQ-FT 1

53.6 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

53.7 Acoustic Board Insulation - 1" 10 SQ-FT 1

53.8 Acoustic Board Insulation - 2" 10 SQ-FT 1

53.9 Bulkhead / Overhead Surfaces: Beam Coverings - - - -

53.10 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.11 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.12 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52 Insulation, Ventillation Ducting, Renew 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew 10 SQ-FT 1

54 Insulation, MDE Exhaust Blankets, Fabricate and Install 10 SQ-FT 1

A-O Composite Labor Rate HOUR 1

B-D GFP Report NSP EA 1 NSP

(FY'14)

1 Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1

2 Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 1

3 Chain Lockers, Inspect JOB 1

4 Sea Water Piping, Renew - - - -

4.1 1"-2-3/4" O.D. 1 LF 1

4.2 3" - 4-3/4" O.D. 1 LF 1

4.3 5" - 7-3/4" O.D. 1 LF 1

4.4 8" - 10" O.D. 1 LF 1

5 Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1

6 Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1

7 Vent Ducts (Engine Room), Commercial Cleaning JOB 1

8 Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1

9 Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1

10 Chill Water Piping, Renew - - - -

10.1 1"-2-3/4" O.D. 1 LF 1

10.2 3" - 4-3/4" O.D. 1 LF 1

10.3 5" - 7-3/4" O.D. 1 LF 1

11 Feed/Jacket Water Piping, Renew - - - -

11.1 1"-2-3/4" O.D. 1 LF 1

11.2 3" - 4-3/4" O.D. 1 LF 1

11.3 5" - 7-3/4" O.D. 1 LF 1

12 Potable Water Piping, Renew - - - -

12.1 1"-2-3/4" O.D. 1 LF 1

SCHEDULE OF SUPPLIES & SERVICES (SOS&S)

270 DOCKSIDE AVAILABILITY IDIQ - 2014, YEAR 4

(3 Availabilities Projected for 2014)

US COAST GUARD WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS

270 DS IDIQ Est R5_BLANK 111910 Issued

12.2 3" - 4-3/4" O.D. 1 LF 1

12.3 5" - 7-3/4" O.D. 1 LF 1

13 Potable Water Pneumatic Tank, Clean and Inspect JOB 1

14 Fuel Piping, Renew - - - -

14.1 1"-2-3/4" O.D. 1 LF 1

14.2 3" - 4-3/4" O.D. 1 LF 1

14.3 5" - 7-3/4" O.D. 1 LF 1

15 Fin Stabilizers, General Maintenance JOB 1

16 Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1

17 Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1

18 Warping Capstan, Perform Level 2 Maintenance JOB 1

19 Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1

20 Helo Talon Grid, Inspect and Test JOB 1

21 Grey Water Holding Tanks, Clean and Inspect JOB 1

22 Sewage Collection and Holding Tanks, Clean and Inspect JOB 1

23 Work Item Deleted - Job 1 -

24 Grey Water Piping, Clean and Flush 10 LF 1

25 Sewage Piping, Renew - - - -

25.1 1"-2-3/4" O.D. 1 LF 1

25.2 3" - 4-3/4" O.D. 1 LF 1

25.3 5" - 7-3/4" O.D. 1 LF 1

26 Sewage Piping, Clean and Flush 10 LF 1

27 Tanks (Ballast), Preserve “100%” - - - -

27.1 Ballast, 3-B-0-W EA 1

27.5 Ballast, 4-103-2-W EA 1

27.6 Ballast,4-169-0-W EA 1

27.7 Ballast, 4-228-1-W EA 1

27.8 Ballast, 4-228-2-W EA 1

27.9 Ballast, 4-242-0-W EA 1

28 Tank (Dirty Oil and Waste), Preserve “100%” JOB 1

29 Tanks (Potable Water), Preserve “100%” - - - -

29.1 Potable Water, 4-78-1-W EA 1

29.1 Potable Water, 4-78-2-W EA 1

29.3 Potable Water, 4-94-1-W EA 1

30 Tanks (Sewage and Vacuum Collection), Preserve “100%” - -

30.1 Sewage Tank, 3-82-0-E EA 1

30.2 Vacuum Collection Tank, 2-82-0-E EA 1

31 Tanks (Grey Water Holding), Preserve “100% - - 1 -

31.1 Aft, 3-103-0-E EA 1

31.2 FWD, 3.82-0-E EA 1

31.3 Seal Water Tank EA 1

32 Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - - -

32.1 Watertight Door, 12" x 18" EA 1

32.2 Watertight Door, 18" x 36" EA 1

32.3 Watertight Door, 33" x 66" EA 1

32.4 Scuttle, Round, 12" Dia. EA 1

32.5 Scuttle, Round, 14" Dia. EA 1

32.6 Scuttle, Round, 18" Dia. EA 1

32.7 Scuttle, Round, 21" Dia. EA 1

32.8 Scuttle, Round, 24" Dia. EA 1

33 Watertight Doors and Scuttles (External), Renew - - - -

33.1 Watertight Door, 12" x 18" EA 1

33 2 Watertight Door 18" x 36" EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

33.2 Watertight Door, 18" x 36" EA 1

33.3 Watertight Door, 33" x 66" EA 1

33.4 Scuttle, Round, 12" Dia. EA 1

33.5 Scuttle, Round, 14" Dia. EA 1

33.6 Scuttle, Round, 18" Dia. EA 1

33.7 Scuttle, Round, 21" Dia. EA 1

33.8 Scuttle, Round, 24" Dia. EA 1

34 Piping Insulation, Renew - - - -

34.1 For interior gas, steam, hot water (jacket water only), and oil piping systems: - - 1 -

34.2 3/4" - 2" O.D. pipe dia. 10 LF 1

34.3 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.4 4-1/4" - 6" O.D. pipe dia. 10 LF 1

34.5 For interior refrigerant (LP side only), hot water, cold water, and chill water piping systems:

34.6 3/4" - 2" O.D. pipe dia. 10 LF 1

34.7 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.8 4-1/4" - 6" O.D. pipe dia. 10 LF 1

35 Compressed Air Receivers, Clean, Inspect, and Test JOB 1

36 Tanks (Ballast), Preserve, “Partial” - - - -

36.1 Ballast, 3-B-0-W EA 1

36.2 Ballast, 4-75-1-W EA 1

36.3 Ballast, 4-75-2-W EA 1

36.4 Ballast, 4-103-1-W EA 1

36.5 Ballast, 4-103-2-W EA 1

36.6 Ballast,4-169-0-W EA 1

36.7 Ballast, 4-228-1-W EA 1

38 Tanks (Potable Water), Preserve “Partial” - - - -

38.1 Potable Water, 4-78-1-W EA 1

38.2 Potable Water, 4-78-2-W EA 1

38.3 Potable Water, 4-94-1-W EA 1

39 Tanks (Sewage Holding), Preserve, “Partial” - - - -

39.1 Sewage Tank, 3-82-0-E EA 1

39.2 Vacuum Collection Tank, 2-82-0-E EA 1

40 Tanks (Grey Water Holding), Preserve, “Partial” - - - -

40.1 Aft, 3-103-0-E EA 1

40.2 FWD, 3.82-0-E EA 1

40.3 Seal Water Tank EA 1

41 Tanks (Ballast), Clean and Inspect - - - -

41.1 3-B-0-W EA 1

41.2 4-75-1-W EA 1

41.3 4-75-2-W EA 1

41.4 4-103-1-W EA 1

41.5 4-103-2-W EA 1

41.6 4-169-0-W EA 1

41.7 4-228-1-W EA 1

41.8 4-228-2-W EA 1

41.9 4-242-0-W EA 1

42 Tanks (Dirty Oil and Waste), Clean and Inspect - - - -

42.1 4-165-1-F EA 1

42.2 4-169-1-F EA 1

43 Tanks (Lube Oil), Clean and Inspect EA 1

44 Tanks (MP Fuel Service), Clean and Inspect - - - -

44.1 2-228-1-F EA 1

44.2 4-165-3-F EA 1

44 3 4-165-4-F EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

44.3 4-165-4-F EA 1

45 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - - - -

45.1 4-26-1-F EA 1

45.2 4-26-2-F EA 1

45.3 4-47-1-F EA 1

45.4 4-47-2-F EA 1

45.5 4-82-0-F EA 1

45.6 4-82-1-F EA 1

45.7 4-82-2-F EA 1

45.8 4-96-0-F EA 1

45.9 4-103-0-F EA 1

45.10 4-165-2-F EA 1

45.11 4-207-0-F EA 1

45.12 4-207-1-F EA 1

45.13 4-207-2-F EA 1

46 Tanks (MP Fuel), Preserve "100%" - - - -

46.1 2-228-1-F EA 1

46.2 4-26-1-F EA 1

46.3 4-26-2-F EA 1

46.4 4-47-1-F EA 1

46.5 4-47-2-F EA 1

46.6 4-82-0-F EA 1

46.7 4-82-1-F EA 1

46.8 4-82-2-F EA 1

46.9 4-96-0-F EA 1

46.13 4-165-4-F EA 1

46.14 4-207-0-F EA 1

46.15 4-207-1-F EA 1

46.16 4-207-2-F EA 1

47 Tanks (Hydraulic Oil), Clean and Inspect EA 1

48 Tanks (Aviation Fuel Service), Clean and Inspect - - - -

48.1 3-190-1-J EA 1

48.2 3-190-2-J EA 1

49 Tanks (Aviation Fuel Service), Preserve"100%" - - - -

49.1 3-190-1-J EA 1

49.2 3-190-2-J EA 1

50 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect - - - -

50.1 4-186-1-J EA 1

50.2 4-186-2-J EA 1

50.3 4-190-1-J EA 1

50.4 4-190-2-J EA 1

51 Tanks (Aviation Fuel Stowage and Overflow), Preserve "100%" - - - -

51.1 4-186-1-J EA 1

51.2 4-186-2-J EA 1

51.3 4-190-1-J EA 1

51.4 4-190-2-J EA 1

52 Insulation, Ventillation Ducting, Renew - - - -

52.1 Thermal Blanket Insulation - 1" 10 SQ-FT 1

52.2 Thermal Blanket Insulation - 2" 10 SQ-FT 1

52.3 Thermal Board Insulation - 1" 10 SQ-FT 1

52.4 Thermal Board Insulation - 2" 10 SQ-FT 1

52.5 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52.6 Acoustic Board Insulation - 1" 10 SQ-FT 1

52 7 Acoustic Board Insulation - 2" 10 SQ-FT 1

270 DS IDIQ Est R5_BLANK 111910 Issued

52.7 Acoustic Board Insulation - 2" 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew - - - -

53.1 Bulkhead / Overhead Surfaces: Non-beam covering - - - -

53.2 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.3 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.4 Thermal Board Insulation - 1" 10 SQ-FT 1

53.5 Thermal Board Insulation - 2" 10 SQ-FT 1

53.6 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

53.7 Acoustic Board Insulation - 1" 10 SQ-FT 1

53.8 Acoustic Board Insulation - 2" 10 SQ-FT 1

53.9 Bulkhead / Overhead Surfaces: Beam Coverings - - - -

53.10 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.11 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.12 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52 Insulation, Ventillation Ducting, Renew 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew 10 SQ-FT 1

54 Insulation, MDE Exhaust Blankets, Fabricate and Install 10 SQ-FT 1

A-O Composite Labor Rate HOUR 1

B-D GFP Report NSP EA 1 NSP

(FY'15)

1 Hull and Structural Plating – ¼” to ½” Aluminum Plate, Renew 4 SQ FT 1

2 Hull and Structural Plating – ¼” to ½” Steel Plate, Renew 4 SQ FT 1

3 Chain Lockers, Inspect JOB 1

4 Sea Water Piping, Renew - - - -

4.1 1"-2-3/4" O.D. 1 LF 1

4.2 3" - 4-3/4" O.D. 1 LF 1

4.3 5" - 7-3/4" O.D. 1 LF 1

4.4 8" - 10" O.D. 1 LF 1

5 Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean JOB 1

6 Ship Service Diesel Generator (SSDG) Exhaust Piping, Clean JOB 1

7 Vent Ducts (Engine Room), Commercial Cleaning JOB 1

8 Vent Ducts (Galley and Pantry Room - All), Commercial Cleaning JOB 1

9 Vent Ducts (Laundry Exhaust), Commercial Cleaning JOB 1

10 Chill Water Piping, Renew - - - -

10.1 1"-2-3/4" O.D. 1 LF 1

10.2 3" - 4-3/4" O.D. 1 LF 1

10.3 5" - 7-3/4" O.D. 1 LF 1

11 Feed/Jacket Water Piping, Renew - - - -

11.1 1"-2-3/4" O.D. 1 LF 1

11.2 3" - 4-3/4" O.D. 1 LF 1

11.3 5" - 7-3/4" O.D. 1 LF 1

12 Potable Water Piping, Renew - - - -

12.1 1"-2-3/4" O.D. 1 LF 1

SCHEDULE OF SUPPLIES & SERVICES (SOS&S)

270 DOCKSIDE AVAILABILITY IDIQ - 2015, YEAR 5

(6 Availabilities Projected for 2015)

US COAST GUARD WMEC 270 "A&B CLASS" MEDIUM ENDURANCE CUTTERS

270 DS IDIQ Est R5_BLANK 111910 Issued

12.2 3" - 4-3/4" O.D. 1 LF 1

12.3 5" - 7-3/4" O.D. 1 LF 1

13 Potable Water Pneumatic Tank, Clean and Inspect JOB 1

14 Fuel Piping, Renew - - - -

14.1 1"-2-3/4" O.D. 1 LF 1

14.2 3" - 4-3/4" O.D. 1 LF 1

14.3 5" - 7-3/4" O.D. 1 LF 1

15 Fin Stabilizers, General Maintenance JOB 1

16 Commissary Hoist Assembly, Perform Level 2 Maintenance JOB 1

17 Anchor Windlass Assembly, Perform Level 2 Maintenance JOB 1

18 Warping Capstan, Perform Level 2 Maintenance JOB 1

19 Articulating Crane, Hydraulic, Perform Level 2 Maintenance JOB 1

20 Helo Talon Grid, Inspect and Test JOB 1

21 Grey Water Holding Tanks, Clean and Inspect JOB 1

22 Sewage Collection and Holding Tanks, Clean and Inspect JOB 1

23 Work Item Deleted - Job 1 -

24 Grey Water Piping, Clean and Flush 10 LF 1

25 Sewage Piping, Renew - - - -

25.1 1"-2-3/4" O.D. 1 LF 1

25.2 3" - 4-3/4" O.D. 1 LF 1

25.3 5" - 7-3/4" O.D. 1 LF 1

26 Sewage Piping, Clean and Flush 10 LF 1

27 Tanks (Ballast), Preserve “100%” - - - -

27.1 Ballast, 3-B-0-W EA 1

27.5 Ballast, 4-103-2-W EA 1

27.6 Ballast,4-169-0-W EA 1

27.7 Ballast, 4-228-1-W EA 1

27.8 Ballast, 4-228-2-W EA 1

27.9 Ballast, 4-242-0-W EA 1

28 Tank (Dirty Oil and Waste), Preserve “100%” JOB 1

29 Tanks (Potable Water), Preserve “100%” - - - -

29.1 Potable Water, 4-78-1-W EA 1

29.1 Potable Water, 4-78-2-W EA 1

29.3 Potable Water, 4-94-1-W EA 1

30 Tanks (Sewage and Vacuum Collection), Preserve “100%” - -

30.1 Sewage Tank, 3-82-0-E EA 1

30.2 Vacuum Collection Tank, 2-82-0-E EA 1

31 Tanks (Grey Water Holding), Preserve “100% - - 1 -

31.1 Aft, 3-103-0-E EA 1

31.2 FWD, 3.82-0-E EA 1

31.3 Seal Water Tank EA 1

32 Watertight Doors and Scuttles (Internal DC Deck and Below), Renew - - - -

32.1 Watertight Door, 12" x 18" EA 1

32.2 Watertight Door, 18" x 36" EA 1

32.3 Watertight Door, 33" x 66" EA 1

32.4 Scuttle, Round, 12" Dia. EA 1

32.5 Scuttle, Round, 14" Dia. EA 1

32.6 Scuttle, Round, 18" Dia. EA 1

32.7 Scuttle, Round, 21" Dia. EA 1

32.8 Scuttle, Round, 24" Dia. EA 1

33 Watertight Doors and Scuttles (External), Renew - - - -

33.1 Watertight Door, 12" x 18" EA 1

33 2 Watertight Door 18" x 36" EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

33.2 Watertight Door, 18" x 36" EA 1

33.3 Watertight Door, 33" x 66" EA 1

33.4 Scuttle, Round, 12" Dia. EA 1

33.5 Scuttle, Round, 14" Dia. EA 1

33.6 Scuttle, Round, 18" Dia. EA 1

33.7 Scuttle, Round, 21" Dia. EA 1

33.8 Scuttle, Round, 24" Dia. EA 1

34 Piping Insulation, Renew - - - -

34.1 For interior gas, steam, hot water (jacket water only), and oil piping systems: - - 1 -

34.2 3/4" - 2" O.D. pipe dia. 10 LF 1

34.3 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.4 4-1/4" - 6" O.D. pipe dia. 10 LF 1

34.5 For interior refrigerant (LP side only), hot water, cold water, and chill water piping systems:

34.6 3/4" - 2" O.D. pipe dia. 10 LF 1

34.7 2-1/4" - 4" O.D. pipe dia. 10 LF 1

34.8 4-1/4" - 6" O.D. pipe dia. 10 LF 1

35 Compressed Air Receivers, Clean, Inspect, and Test JOB 1

36 Tanks (Ballast), Preserve, “Partial” - - - -

36.1 Ballast, 3-B-0-W EA 1

36.2 Ballast, 4-75-1-W EA 1

36.3 Ballast, 4-75-2-W EA 1

36.4 Ballast, 4-103-1-W EA 1

36.5 Ballast, 4-103-2-W EA 1

36.6 Ballast,4-169-0-W EA 1

36.7 Ballast, 4-228-1-W EA 1

38 Tanks (Potable Water), Preserve “Partial” - - - -

38.1 Potable Water, 4-78-1-W EA 1

38.2 Potable Water, 4-78-2-W EA 1

38.3 Potable Water, 4-94-1-W EA 1

39 Tanks (Sewage Holding), Preserve, “Partial” - - - -

39.1 Sewage Tank, 3-82-0-E EA 1

39.2 Vacuum Collection Tank, 2-82-0-E EA 1

40 Tanks (Grey Water Holding), Preserve, “Partial” - - - -

40.1 Aft, 3-103-0-E EA 1

40.2 FWD, 3.82-0-E EA 1

40.3 Seal Water Tank EA 1

41 Tanks (Ballast), Clean and Inspect - - - -

41.1 3-B-0-W EA 1

41.2 4-75-1-W EA 1

41.3 4-75-2-W EA 1

41.4 4-103-1-W EA 1

41.5 4-103-2-W EA 1

41.6 4-169-0-W EA 1

41.7 4-228-1-W EA 1

41.8 4-228-2-W EA 1

41.9 4-242-0-W EA 1

42 Tanks (Dirty Oil and Waste), Clean and Inspect - - - -

42.1 4-165-1-F EA 1

42.2 4-169-1-F EA 1

43 Tanks (Lube Oil), Clean and Inspect EA 1

44 Tanks (MP Fuel Service), Clean and Inspect - - - -

44.1 2-228-1-F EA 1

44.2 4-165-3-F EA 1

44 3 4-165-4-F EA 1

270 DS IDIQ Est R5_BLANK 111910 Issued

44.3 4-165-4-F EA 1

45 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - - - -

45.1 4-26-1-F EA 1

45.2 4-26-2-F EA 1

45.3 4-47-1-F EA 1

45.4 4-47-2-F EA 1

45.5 4-82-0-F EA 1

45.6 4-82-1-F EA 1

45.7 4-82-2-F EA 1

45.8 4-96-0-F EA 1

45.9 4-103-0-F EA 1

45.10 4-165-2-F EA 1

45.11 4-207-0-F EA 1

45.12 4-207-1-F EA 1

45.13 4-207-2-F EA 1

46 Tanks (MP Fuel), Preserve "100%" - - - -

46.1 2-228-1-F EA 1

46.2 4-26-1-F EA 1

46.3 4-26-2-F EA 1

46.4 4-47-1-F EA 1

46.5 4-47-2-F EA 1

46.6 4-82-0-F EA 1

46.7 4-82-1-F EA 1

46.8 4-82-2-F EA 1

46.9 4-96-0-F EA 1

46.13 4-165-4-F EA 1

46.14 4-207-0-F EA 1

46.15 4-207-1-F EA 1

46.16 4-207-2-F EA 1

47 Tanks (Hydraulic Oil), Clean and Inspect EA 1

48 Tanks (Aviation Fuel Service), Clean and Inspect - - - -

48.1 3-190-1-J EA 1

48.2 3-190-2-J EA 1

49 Tanks (Aviation Fuel Service), Preserve"100%" - - - -

49.1 3-190-1-J EA 1

49.2 3-190-2-J EA 1

50 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect - - - -

50.1 4-186-1-J EA 1

50.2 4-186-2-J EA 1

50.3 4-190-1-J EA 1

50.4 4-190-2-J EA 1

51 Tanks (Aviation Fuel Stowage and Overflow), Preserve "100%" - - - -

51.1 4-186-1-J EA 1

51.2 4-186-2-J EA 1

51.3 4-190-1-J EA 1

51.4 4-190-2-J EA 1

52 Insulation, Ventillation Ducting, Renew - - - -

52.1 Thermal Blanket Insulation - 1" 10 SQ-FT 1

52.2 Thermal Blanket Insulation - 2" 10 SQ-FT 1

52.3 Thermal Board Insulation - 1" 10 SQ-FT 1

52.4 Thermal Board Insulation - 2" 10 SQ-FT 1

52.5 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52.6 Acoustic Board Insulation - 1" 10 SQ-FT 1

52 7 Acoustic Board Insulation - 2" 10 SQ-FT 1

270 DS IDIQ Est R5_BLANK 111910 Issued

52.7 Acoustic Board Insulation - 2" 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew - - - -

53.1 Bulkhead / Overhead Surfaces: Non-beam covering - - - -

53.2 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.3 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.4 Thermal Board Insulation - 1" 10 SQ-FT 1

53.5 Thermal Board Insulation - 2" 10 SQ-FT 1

53.6 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

53.7 Acoustic Board Insulation - 1" 10 SQ-FT 1

53.8 Acoustic Board Insulation - 2" 10 SQ-FT 1

53.9 Bulkhead / Overhead Surfaces: Beam Coverings - - - -

53.10 Thermal Blanket Insulation - 1" 10 SQ-FT 1

53.11 Thermal Blanket Insulation - 2" 10 SQ-FT 1

53.12 Acoustic Blanket Insulation - 2" 10 SQ-FT 1

52 Insulation, Ventillation Ducting, Renew 10 SQ-FT 1

53 Insulation, Bulkhead / Overhead, Renew 10 SQ-FT 1

54 Insulation, MDE Exhaust Blankets, Fabricate and Install 10 SQ-FT 1

A-O Composite Labor Rate HOUR 1

B-D GFP Report NSP EA 1 NSP

270 DS IDIQ Est R5_BLANK 111910 Issued Summary.pdf
Summary
270 DS IDIQ Est R5_BLANK 111910 Issued YR1
YR 1 - BASE 2011
270 DS IDIQ Est R5_BLANK 111910 Issued YR2
YR 2 - 2012
270 DS IDIQ Est R5_BLANK 111910 Issued YR3
YR 3 - 2013
270 DS IDIQ Est R5_BLANK 111910 Issued YR4
YR 4 - 2014
270 DS IDIQ Est R5_BLANK 111910 Issued YR5
YR 5 - 2015