HQ085021R0001 Attachment 6 - Tranche 0 Launch Services Notional Payment Plan.pdf
PDF 45 KB Posted
- Attached to
- SDA Tranche 0 Launch Services
- Solicitation number
- HQ085021R0001
- Issued by
-
Space Development Agency
About this file
This attachment to a solicitation outlines a notional payment plan for launch services to deliver twenty-eight satellite vehicles to orbit by March 2023. The Space Development Agency seeks a launch services contractor to provide delivery on orbit through multiple launches, with the first launch occurring in September 2022. Payments will be made upon completion of milestones including hardware purchases, integration activities, launch readiness reviews, and post-launch reports. The notional plan includes nine payment milestones from contract award through final launch acceptance, ranging from 3-35% of the total fixed price. The final 10% will be paid after the constellation is on orbit as specified. In the event of a launch failure, the contract price will be reduced by the full amount for the applicable launch milestones.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Space Development Agency
Tranche 0 Launch Services Contract
Solicitation No. HQ085021R0001
Attachment 6
Notional Payment Plan
BASIS OF PAYMENT
The launch service shall be paid based on payment milestones. Table 1 outlines a notional payment plan and will be updated once the payment plan has been finalized between the awarded vendor and the Government. Each milestone represents an event or action necessary to successful performance. The payment amounts are broken out as specified percentages for the bottom-line firm fixed price (FFP) associated with the required tasks to meet the SOW requirements. Each payable milestone event will be included in the final Contract as a separately priced Contract Line Item Number (CLIN). These payable milestones shall not be “progress payments based on cost” as described in FAR 52.232-16, but instead reflect the completion of the top level critical performance based milestones traced back to the tasks found in Attachment 1 – Statement Of Work and allows for a successful delivery-to-orbit of all Space Vehicles. Offerors should include proposed changes to the payment schedule within their proposal cost/price volume.
Once payment plan has been finalized between the awarded vendor and the Government, in order to initiate the payment process, the Contractor shall notify the Government upon completion of each milestone. The Government’s Contracting Officer (CO) will determine whether a milestone has been successfully met based on the inputs from Space Development Agency team.
To the maximum extent possible within fifteen (15) business days after the Government has received the Contractor’s notification of completion, the CO will provide concurrence of milestone completion or justification on why the milestone has not been met and specify the issues and/or corrective actions required.
The Contractor shall not receive greater than 90% of the total contract price until after acceptance of the launch services and payloads have reached the required orbit specified in the SOW. If multiple launches are executed, the successful completion of the initial launch milestone will earn 7% and successful completion of the final launch milestone will earn 5%. Given that defects in service for the launch milestone(s) are not suitable for correction by re-performance, the CO has determined that, pursuant to FAR 52.246-4(e), the appropriate relief for the Government in the event(s) of launch failure is to reduce the contract price by the amount of the full Milestone #8 and/or Milestone #9 (as applicable), which reflects the reduced value of the services performed.
Table 1: Milestone Payment Plan
Payment # Timeline Event/Criteria % of Total Price
1 Contract Award
- Initiate Early Integration Studies 3%
2 Initial Launch L-11 months
- Long-lead hardware purchases
- Early integration results
- Interface Control Document
20%
3 L-9 months - LV As-Built Configuration List (Initial Launch)
- Flight hardware interface checks (Initial Launch)
35%
4 L-6 months - LV As-Built Configuration List (Subsequent Launch)
- Flight hardware interface checks (Subsequent Launch)
18%
5 L-3 months - Launch Campaign Readiness Review (Initial Launch)
5%
6 L-2 months - Pre-shipment review (Initial Launch) 5%
7 L-0 months - Launch Campaign Readiness Review (Subsequent Launch)
2%
8 L+30 days - Mission Orbital Parameter Accuracy Verification (Initial Launch)
- Government Acceptance of Launch Service (Initial Launch)
- Post-Launch Report
7%
9 Final Launch L+30 days
- Mission Orbital Parameter Accuracy Verification (Final Launch)
- Government Acceptance of Launch Service (Final Launch)
- Post-Launch Report
5%