GS-1340-W6, Amendment 02, 04/12/2017
Amendment 02 contains the following:
I. Answer to question from potential offeror.
I. Question and Answer – Answer by GSA provided in red.
1. In the DES-DPS_100% submittal, page 57 note #5, it indicates that the existing Motor Control Center (MCC) must be replaced. The drawings GSA DEA PDS Bridging documents also show to remove the existing MCC and install a new MCC in the new electrical room. Is it possible to have specifications on this new MCC?
Answer: No specifications for the Motor Control Center (MCC) are developed. The documentation in the bridging documents is schematic in nature and will be the responsibility of the DB contractor's Electrical Engineer of Record to perform load calculations, size and capacity for the new MCC per the latest edition of the National Electrical Code and GSA PBS P100 standards.