Attachment 2_Project Specifications Manual 6 March 2015.pdf

PDF 3 MB Posted

Attached to
General Construction for Perimeter Security Improvements Project Federal contract opportunity
Solicitation number
GS11P16MKC7003
Issued by
General Services Administration Public Buildings Service National Capital Region

About this file

Not Listed

View the file

Other files for this federal contract opportunity

Other files attached to General Construction for Perimeter Security Improvements Project, newest first.
File Type Posted
Amendment_5_to_GS11P16MKC7003.pdf PDF
Amendment_4_to_GS11P16MKC7003.pdf PDF
Site_Visit__1_Sign_In_sheet.pdf PDF
Amendment_3_to_GS11P16MKC7003.pdf PDF
Amendment_2_to_GS11P16MKC7003.pdf PDF
Revised_Spec_Section_321413_(Unit_Paving)_dated_3_June_2016.pdf PDF
Revised_DWG_DETAILS_L503_dated_3_June_2016.pdf PDF
GC_Past_Performance_Reference_Form.pdf PDF
Amendment_1_to_GS11P16MKC7003.pdf PDF
Revised_Spec_Section_334100_(Storm_Piping)_dated_3_June_2016.pdf PDF
The_Solicitation_dated_9June16_Revised.pdf PDF
Attachment_1_-_Statement_of_Work_dated_9_June_2016.pdf PDF
Attachment 8_USMSContractor Security clearance request.pdf PDF
Attachment_11_EnvironmentalAssessment_Jan_2012.pdf PDF
GSA527-15.pdf PDF
Attachment 7_Davis Bacon Wage Rate VA160083.pdf PDF
Attachment 12B_Traffic Impact Study.pdf PDF
Attachment_1_Statement_of_Work.pdf PDF
Attachment 9_Geotechnical Engineering Report 3 March 2015.pdf PDF
Attachment_3__Final_Drawing_Mylar_Submission.pdf PDF
Attachment_12B_Traffic_Impact_Study.pdf PDF
Pricing_Sheet.pdf PDF
Attachment_6B_C D-Waste-Monthly-Report.PerimeterSecurity_(1).xlsx XLSX spreadsheet
Attachment 6B_C D-Waste-Monthly-Report.PerimeterSecurity —
Attachment_5_Safety__and_Health_Specification_Section_01546.pdf PDF
The_Agreement_Small_Business_Set-Aside_GC_FINAL.pdf PDF
Attachment 6A_C D-Waste-Monthly-Report.PerimeterSecurity —
Attachment 2_Project Specifications Manual 6 March 2015.pdf PDF
Attachment_2_Project_Specifications_Manual_6_March_2015.pdf PDF
Attachment_10_ALTA-ACSM_Final_Survey_06-24-15_(1).pdf PDF
Attachment_6A_C D-Waste-Monthly-Report.PerimeterSecurity_(2).xlsx XLSX spreadsheet
Attachment 10_ALTA-ACSM Final Survey 06-24-15 —
C301_GC_Reps_ _Certs.pdf PDF
Attachment 12A_Traffic Impact Study Jan 2012.pdf PDF
Attachment_7_Davis_Bacon_Wage_Rate_VA160083.pdf PDF
Attachment 12A_Traffic Impact Study Jan 2012.pdf PDF
Attachment 11_EnvironmentalAssessment Jan 2012.pdf PDF
Attachment 8_USMSContractor Security clearance request.pdf PDF
Attachment 3_ Final Drawing Mylar Submission.pdf PDF
Attachment 5_Safety and Health Specification Section 01546.pdf PDF
Attachment 1_Statement of Work.pdf PDF
Attachment 10_ALTA-ACSM Final Survey 06-24-15 —
Attachment 6B_C D-Waste-Monthly-Report.PerimeterSecurity —
Attachment 7_Davis Bacon Wage Rate VA160083.pdf PDF
SF1442_Form_(GS-11-P-16-MK-C-7003).pdf PDF
C301_GC_Reps_ _Certs.pdf PDF
SF_24-98.pdf PDF
Pricing_Sheet.pdf PDF
The_Solicitation_Small_Business_Set_Aside_GC_LPTA__FINAL.pdf PDF
Attachment 6A_C D-Waste-Monthly-Report.PerimeterSecurity —
Show all 50

General Construction for Perimeter Security Improvements Project has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT - FOR OFFICIAL USE ONLY

Do not remove this notice – Properly destroy or return documents when no longer needed

Project Manual

Final Submission

March 6, 2015

Albert V. Bryan Courthouse Security Perimeter Improvements

401 Courthouse Square Alexandria, VA

Geier Brown Renfrow Architects, LLC 1029 North Royal Street, Suite 200

Alexandria, Virginia 22314

Attachment 2

Albert V. Bryan U.S. Courthouse Perimeter Security Improvements March 6, 2105

PROPERTY OF THE UNITED STATES GOVERNMENT - FOR OFFICIAL USE ONLY

Do not remove this notice – Properly destroy or return documents when no longer needed

TABLE OF CONTENTS TOC - i Geier Brown Renfrow Architects, LLC Final Submission

Perimeter Security Improvements Albert V. Bryan Courthouse, Alexandria, VA

Project Manual - Table of Contents

SPECIFICATIONS GROUP

General Requirements Subgroup

DIVISION 01 - GENERAL REQUIREMENTS

01 1000 SUMMARY

01 2100 ALLOWANCES

01 2500 SUBSTITUTION PROCEDURES

01 2700 UNIT PRICES

01 2900 PAYMENT PROCEDURES

01 3000 ELECTRONIC PROJECT MANAGEMENT

01 3100 PROJECT MANAGEMENT AND COORDINATION

01 3120 CRITICAL PATH METHOC SCHEDULING FOR SMALL PROJECTS

01 3200 CONSTRUCTION PROGRESS DOCUMENTATION

01 3300 SUBMITTAL PROCEDURES

01 3516 ALTERATION PROJECT PROCEDURES

01 4000 QUALITY REQUIREMENTS

01 4200 REFERENCES

01 5000 TEMPORARY FACILITIES AND CONTROLS

01 5930 SECURITY REGULATIONS

01 5950 SAFETY AND HEALTH

01 6000 PRODUCT REQUIREMENTS

01 7000 EXECUTION REQUIREMENTS

01 7310 CUTTING AND PATCHING

01 7700 CLOSEOUT PROCEDURES

01 7900 DEMONSTRATION AND TRAINING

Facility Construction Subgroup

DIVISION 02 - EXISTING CONDITIONS

02 4119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

03 3000 CAST IN PLACE CONCRETE

03 4500 PRE-CAST ARCHITECTURAL CONCRETE

DIVISION 04 - MASONRY

NOT APPLICABLE

DIVISION 05 - METALS

05 7000 DECORATIVE METAL

PROPERTY OF THE UNITED STATES GOVERNMENT - FOR OFFICIAL USE ONLY

Do not remove this notice – Properly destroy or return documents when no longer needed

TABLE OF CONTENTS TOC - ii Geier Brown Renfrow Architects, LLC Final Submission

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

NOT APPLICABLE

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 8400 FIRE STOPPPING

DIVISION 08 - OPENINGS

NOT APPLICABLE

DIVISION 09 - FINISHES

NOT APPLICABLE

DIVISION 10 - SPECIALTIES

NOT APPLICABLE

DIVISION 11 - EQUIPMENT

NOT APPLICABLE

DIVISION 12 - FURNISHINGS

NOT APPLICABLE

DIVISION 13 - SPECIAL CONSTRUCTION

NOT APPLICABLE

DIVISION 14 - CONVEYING EQUIPMENT

NOT APPLICABLE

Facility Services Subgroup

DIVISION 21 - FIRE SUPPRESSION

NOT APPLICABLE

DIVISION 22 - PLUMBING

NOT APPLICABLE

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

NOT APPLICABLE

DIVISION 25 - INTEGRATED AUTOMATION

NOT APPLICABLE

DIVISION 26 - ELECTRICAL

26 0500 COMMON WORK RESULTS FOR ELECTRICAL

26 0519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 0526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 0533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

PROPERTY OF THE UNITED STATES GOVERNMENT - FOR OFFICIAL USE ONLY

Do not remove this notice – Properly destroy or return documents when no longer needed

TABLE OF CONTENTS TOC - iii Geier Brown Renfrow Architects, LLC Final Submission

26 0543 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

26 0544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

DIVISION 26 – ELECTRICAL – Continued.

26 0572 PROTECTIVE DEVICE SHORT CIRCUIT, COORDINATION, AND ARC FLASH

STUDY

26 2416 PANEL BOARDS

26 2813 FUSES

26 2816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

26 8000 MISCELLANEOUS ELECTRICAL EQUIPMENT

26 9000 ELECTRICAL TESTING

26 9500 SUBMITTAL AND DOCUMENTATION REQUIREMENTS FOR ELECTRICAL

SYSTEMS

DIVISION 27 - COMMUNICATIONS

NOT APPLICABLE

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

NOT APPLICABLE

Site and Infrastructure Subgroup

DIVISION 31 - EARTHWORK

31 1000 SITE CLEARING

31 2000 EARTH MOVING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 1216 ASPHALT PAVING

32 1313 CONCRETE PAVING

32 1413 UNIT PAVING

32 8400 IRRIGATION

32 9113.19 PLANTING SOIL

32 9200 TURF AND GRASSES

32 9300 PLANTS

DIVISION 33 - UTILITIES

33 4100 STORM PIPING

DIVISION 34 - TRANSPORTATION

34 7113 VEHICLE BARRIERS

34 7513.13 ACTIVE VEHICLE BARRIERS

END OF TABLE OF CONTENTS

Albert V. Bryan U.S. Courthouse Perimeter Security Improvements March 6, 2015

Do not remove this notice – Properly destroy or return documents when no longer needed

Summary 011000 - 1 Geier Brown Renfrow Architects, LLC Final Submission

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work under separate contracts.

4. Access to site.

5. Coordination with occupants.

6. Work restrictions.

7. Specification and drawing conventions.

8. Miscellaneous provisions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: Albert V. Bryan Sr. Courthouse, Perimeter Security Improvements Project.

1. Project Location: 401 Courthouse Square, Alexandria, VA 22314.

B. Owner: The United States of America.

1. Owner's Representative: As noted in Solicitation.

2. Security Vendor Coordinator: PJ Carter, USMS, pj.carter@usdoj.gov, 202.353.9116.

C. Architect: Geier Brown Renfrow Architects, LLC.

1. Address: 1029 North Royal Street, Suite 200, Alexandria, Virginia 22314 mailto:pj.carter@usdoj.gov

Summary 011000 - 2

2. Telephone: 703.836.9775

3. Contact: John E Wittmann, AIA

D. Architect's Consultants: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents:

1. Structural Engineer: McMullan & Associates, Inc.

2. MEP Engineer: GHT Limited.

3. Civil Engineer: AMT, LLC

4. Landscape Architect: Carvahlo & Good, PLLC

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Removal of existing temporary security elements and replacement with permanent perimeter security measures; work includes related selective demolition, structural, plumbing, electrical, site utilities, paving and landscaping.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

a. Contract form will be as noted in Soliciation.

1.5 WORK UNDER SEPARATE CONTRACTS

A. Concurrent Work: Owner has awarded and will assign to Contractor separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. Security System Interface: To Tyco Integrated Security for connection and interface of new security system components to existing building security system.

1.6 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep driveways parking garage, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and

Summary 011000 - 3 emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

2. Access to the Loading Dock may be arranged through the COR for the purposes of loading/unloading tools, equipment, and materials.

a. The Loading Dock is open from 08:00 am to 04:00 pm each regular work day for receipt of deliveries.

1) All deliveries to the Loading Dock must be scheduled in advance and must be coordinated with GSA Building Manager at least 72 hours in advance.

2) Access to loading dock and/or staging area that needs to occur after normal working hours, during the weekends and/or on Holidays will require at least one (1) week advance notice.

3) The Loading Dock is only be accessible from Mill Road and will require vehicle inspection.

b. The Contractor shall be responsible for personally receiving deliveries on site at the building, and shall reconcile bills of lading for deliveries of contractor-furnished materials for the contracted project. Government personnel, including A.V. Bryan U.S. Courthouse Loading Dock personnel, will not be responsible for reconciling bills of lading for contractor-furnished materials delivered to the building for a Contractor.

c. The Contractor shall furnish a Contractor point-of-contact to vendors for receipt of material deliveries. The Contractor shall not provide the names of Government personnel to vendors as the point-of-contact for deliveries.

d. The Contractor shall be responsible for scheduling and tracking the deliveries of all contractor-furnished materials for the project. The Contractor shall remove delivered materials from the Loading Dock as expeditiously as possible..

e. Prior to accessing the Loading Dock, all vehicles are inspected by the Guard Service. The Guard Service will inspect the passenger compartment, engine compartment, all trunks, load beds, trailers, and the underside of all vehicles.

Contractors should anticipate delays caused by vehicle inspections. These measures are being taken as per requirement of the Department of Homeland Security, Federal Protective Service.

3. On-Site Storage: On-site storage will be limited to what can be staged in construction area. The Contractor will be responsible for providing secure offsite storage for materials as required to complete the project prior to work commencing.

Summary 011000 - 4

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.7 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than one week in advance of activities that will affect Owner's operations.

1.8 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 08:30 a.m. to 05:00 p.m., Monday through Friday, unless otherwise indicated.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than one week in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Comply with requirements of authorities having jurisdiction and coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than one week in advance of proposed disruptive operations.

2. Obtain Owner's written permission before proceeding with disruptive operations.

E. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

Summary 011000 - 5

F. Employee Identification: Comply with requirements in SECTION 015930 - SECURITY

REGULATIONS.

G. Employee Screening: Comply with requirements in SECTION 015930 - SECURITY

REGULATIONS.

1.9 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

Allowances 012100 - 1

SECTION 012100 - ALLOWANCES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract, including Federal Acquisition Regulations (FAR) and General Services Administration Acquisition Regulations (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

1. Certain items are described in the Contract Documents as allowance items. The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. The Contracting Officer will issue Modifications to incorporate allowance items in the Work after actual products and systems have been determined.

B. Types of allowance items may include the following :

1. Lump-sum allowance items.

2. Unit-price allowance items.

3. Quantity allowance items.

1.3 SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise the contracting officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowances must be included in all schedule submissions

1.4 ACTION SUBMITTALS

A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.

Allowances 012100 - 2

1.5 INFORMATIONAL SUBMITTALS

A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.

B. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

1.6 COORDINATION

A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.

B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the contracting officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiving and handling at Project site, labor, installation, overhead, and profit.

1. If requested by the contracting officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by Contracting officer. Deliver unused material to Contracting officer's storage space as directed.

1.7 ADJUSTMENT OF ALLOWANCE ITEMS

A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.

B. Contracting officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance item promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.

Allowances 012100 - 3

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

3.3 SCHEDULE OF ALLOWANCE ITEMS

A. Allowance Item No. 01 - Quantity Allowance for Salvage of Existing Pavers: Include salvage of 4,000 sf of existing brick pavers for reinstallation.

1. Coordinate quantity allowance adjustment with unit price requirements in Section 012700 – Unit Prices.

END OF SECTION 012100

Substitution Procedures 012500 - 1

SECTION 012500 - SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 012100 "Allowances" for products selected under an allowance.

2. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.

1.4 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use CSI Form 13.1A.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

Substitution Procedures 012500 - 2

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. COR's Action: If necessary, COR will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. COR will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if COR does not issue a decision on use of a proposed substitution within time allocated.

Substitution Procedures 012500 - 3

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: COR and Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Requested substitution provides sustainable design characteristics that specified product provided.

c. Requested substitution is equal to or exceeds the requirements of the specified product.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Not allowed.

Substitution Procedures 012500 - 4

END OF SECTION 012500

Unit Prices 012700 - 1

SECTION 012700 - UNIT PRICES

1.1 A. Unit price is defined in the Agreement.

1.2 PROCEDURES

A. Measurement: Method of measurement for each unit price is specified in the section applicable to the work.

B. Verification: The Government reserves the right to reject the Contractor's measurement of work in place that involves use of an established unit price, and to have this work measured at the Government's expense by an independent surveyor.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 UNIT PRICE ITEM SCHEDULE

A. Unit Price Item No. 1: Salvaged Brick Pavers in lieu of new Brick Pavers.

1. Description: Identify unit cost credit for salvaged brick pavers in excess of quantity allowance identified in Section 012100 – Allowances.

2. Measurement: Square feet of brick pavers.

B. Unit Price Item No. 1: New Brick Pavers in lieu of salvaged Brick Pavers.

1. Description: Identify unit cost to furnish new brick pavers in lieu of salvaged brick pavers per quantity allowance identified in Section 012100 – Allowances.

2. Measurement: Square feet of brick pavers

END OF SECTION 012700

Payment Procedures 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and to process Requests for Payment.

1.2 DEFINITIONS

A. Schedule of Values: A detailed written statement (masterformat/uniformat) furnished by the Contractor outlining the portions of the contract sum, which allocates values (price & percentage) for the various parts of the work and used as the basis for payment application and reviewing progress payments.

The Agreement provides further details.

B. Request for Payment: A contractor’s invoice and request for progress payment with substantiating information consistent with approved schedule of values.

1.3 SCHEDULE OF VALUES

1. Coordination: Submit completed Schedule of Values no later than 14 calendar days prior to scheduled date of initial Requests for Payment.

2. Schedules for Phased Work: Where the work is separated into phases, provide Schedules showing values correlated with each phase using the standard format referenced below.

A. Format and Content: Contractor shall be responsible to complete the GSA Schedule of Values Workbook and compile the values into electronic Project Management (ePM) System. Contractor will enter values into workbook prior to ePM input and provide associated electronic baseline copy to contracting officer for record. Contractor will follow guidelines in the Schedule of Values workbook to support ePM upload.

1. Identification: Complete the following Project Identification fields in the Schedule of Values:

a. Project Name

b. Project Number

c. Project Location, City, State

d. Base Contract Number

e. Task Order Number

f. Modification Number

g. GSA Project Manager

h. Contractor's Name and contact information

i. Date of submittal

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Requests for Payment and progress reports.

a. Work activity – (by division or specific work activity)

Payment Procedures 012900 - 2

b. Dollar value of each specific work activity – both with an amount in dollars and whole cents, and as a percentage of the Contract Sum to nearest one-hundredth percent.

Adjust the amounts to total to the Contract Sum and the percentages to total 100 percent.

c. Each item in the schedule of values and Requests for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

(i.e. no stand alone item for Overhead, and Profit)

d. Modifications that affect value.

e. Update affected work branches and subordinate line items and

f. resubmit the schedule of values before the next Request for Payment when

Modifications result in a change in the Contract Sum

g. Line item for mobilization and de-mobilization

h. Line item for close out (% to be negotiated with GSA COR)

3. Each item in the Schedule of Values and Requests for Payment shall be complete. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at the government's option.

4. Revise and update workbook in ePM with all items affecting scope, schedule or cost and resubmit within 14 calendar days as coordinated with project manager or contracting officer.

Contractor shall provide a final as-built schedule at project completion. Update affected work branches and subordinate line items and resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

1.4 REQUESTS FOR PAYMENT

A. Requirements for Requests for Payment are in Section III, Terms and Conditions of the Agreement.

B. Each Request for Payment following the initial Request for Payment shall be consistent with previous Requests.

1. Initial Request for Payment, Request for Payment at time of Substantial Completion, and final Request for Payment involve additional requirements.

C. Payment Request Times: Submit Request for Payment to GSA by the last business day of the month. The period covered by each Request for Payment is one month, ending on the last day of the month.

1. Submit one paper draft copy (aka pencil copy) of Request for Payment to the CO or enter in ePM along with construction progress report seven days prior to due date for review by GSA.

Provide documentation evidencing the cost of work performed to be included in the Request for Payment. Resolve questions resulting from GSA review of draft Request for Payment and construction progress report prior to submitting Request for Payment.

D. Request Preparation: All payments must be executed by a person authorized to legally bind the Contractor.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts for work completed following effective date of previous Request for Payment, whether or not payment has been received. Include only amounts for work completed as of effective date of current Request for Payment.

3. Include amounts of Modifications issued before last day of construction period covered by Request.

Payment Procedures 012900 - 3

E. Stored Materials: Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices.

Match amount requested with amounts indicated on documentation.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of effective date of previous Request for Payment.

b. Value of previously stored materials put in place after effective date of previous Request for Payment and on or before effective date of current Request for Payment.

c. Value of materials stored since effective date of previous Request for Payment and remaining stored as of effective date of current Request for Payment.

F. Initial Request for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Request for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule per Agreement (startup if not final).

4. Products list (preliminary if not final).

5. Sustainable design submittal for project materials cost data.

6. Sustainable design action plans.

7. Schedule of unit prices.

8. Submittal schedule (preliminary if not final).

9. List of Contractor's staff assignments.

10. List of Contractor's principal consultants.

11. Copies of building permits.

12. Copies of authorizations and licenses from authorities having jurisdiction for performance of the

Work.

13. Initial progress report.

14. Report of preconstruction conference.

G. Request for Payment at Substantial Completion: After GSA issues the Notice of Substantial Completion, submit a Request for Payment less previous payments made for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This Request shall reflect Notices of Substantial Completion issued previously for GSA occupancy of designated portions of the Work.

H. Final Payment Request: The Agreement provides further details

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012900

ELECTRONIC PROJECT MANAGEMENT 013000 - 1

SECTION 013000 - ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM

1.1 PURPOSE

A. The Contractor shall use GSA’s web-based electronic Project Management (ePM) system, which is a fully configured version of Meridian Systems’ Proliance Construction Management Software. Click on this link for the ePM minimum requirements:

https://insite.gsa.gov/portal/category/517870

1.2 DEFINITION

A. ePM is a web-based project management tool which provides GSA’s Public Buildings Service with an automated workflow, collaboration, document management and project management solution to help manage GSA design and construction projects. ePM is integrated with GSA’s gBUILD (Green Building Upgrade Information Lifecycle Database ) to share project creation and data storage information.

1.3 PROJECT COLLABORATION AND DOCUMENTATION

A. General

1. The Contractor shall effectively manage the ePM database including maintaining adequate staffing levels and ensuring that personnel attend the mandatory GSA-provided training sessions.

2. The Contractor shall use ePM to upload, store, capture, preserve, record, maintain, update, and route all project-related documentation to comply with GSA's Document Security Requirements. Classified material is not permitted to be stored in this system.

3. The Contractor shall use the workflow processes contained within ePM to submit and receive approval for all project deliverables.

4. The Contractor shall continuously monitor and review ePM to ensure the Contractor data is current through completion of the Close-out Phase of Construction.

5. The Contractor is required to store documents from their subcontractors and vendors in ePM. If a subcontractor or vendor does not obtain an ePM license, the contractor will be responsible for uploading and processing documents in ePM on their behalf.

https://insite.gsa.gov/portal/category/517870

ELECTRONIC PROJECT MANAGEMENT 013000 - 2

B. Contents of ePM.

1. The Contractor shall use ePM as the electronic filing cabinet for all project-related correspondence and submittals. The Contract Documents specify certain documentation that the Contractor shall provide during performance of the Contract. For the avoidance of doubt, and unless specifically stated otherwise in the Contract Documents, in addition to any documentation that the Contractor submits to GSA as set forth in the Contract Documents. The current ePM Minimum Requirements can be found at:

http://www.gsa.gov/epm.

1.4 SCHEDULING REQUIREMENTS

1. The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule and is compatible with Meridian Proliance.®

1.5 EQUIPMENT AND TRAINING

A. Equipment

1. GSA will not furnish any equipment related to accessing ePM. ePM is web-accessible, and can therefore be accessed via any computer with an Internet connection. For up to date ePM desktop requirements: http://www.gsa.gov/epm.

B. ePM Training

1. GSA will provide no cost training to familiarize team members with the ePM system. The

GSA Project Manager will ensure that appropriate personnel should attend training and what roles they will be set up within the system based on their project responsibilities.

C. ePM Support

1. GSA will provide ePM system administration and end user support, for the duration of the project.

1.6 PERSONNEL REQUIREMENTS

A. An HSPD-12 security clearance is required to access ePM. Project Team members without an HSPD-12 clearance will need to work with the GSA Project Manager to initiate the clearance process, and request a temporary waiver for ePM access until clearance can be confirmed. A waiver means that once the individual’s HSPD-12 clearance is confirmed, an ePM username and password will be provided. For up to date GSA http://www.gsa.gov/epm http://www.gsa.gov/epm

ELECTRONIC PROJECT MANAGEMENT 013000 - 3

HSPD-12 information: www.gsa.gov/hspd12. Obtaining clearances vary in length and may take time to receive them.

1.7 DATA OWNERSHIP

A. GSA shall retain ownership of all data entered into the system and shall administer all information contained therein. And distribution of any system data shall be made upon request.

1.8 DOCUMENT SECURITY

A. ePM security access levels ensure that sensitive documents can only be accessed by the appropriate personnel. It is the contractor’s responsibility to ensure their employees, subcontractors and vendors have the appropriate level of security to ensure document security.

1.9 REFERENCES

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013000

Project Management And Coordination 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Coordination drawings.

3. Conservation.

4. Administrative and supervisory personnel.

5. Conferences and meetings.

6. Utility service interruptions.

7. Cleaning and protection.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space.

Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

3. Minimize roof penetrations.

B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work.

Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Security packages and systems by others (i.e. U.S. Marshals Service (USMS), Federal

Protective Service (FPS), tenants, etc.)

4. Audio Visual (AV) and technology requirements and packages for tenants and/or end users.

5. Telecommunication, data, internet and other tele-work systems for GSA, tenants and/or end users.

Project Management And Coordination 013100 - 2

6. Delivery and processing of submittals.

7. Progress meetings.

8. Project closeout activities.

9. Startup and adjustment of systems.

1.3 COORDINATION DRAWINGS

A. Prepare coordination drawings and/or BIM model and data where coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum use of the space for efficient installation of different components.

1. Show the relationship of components from the separate shop drawings. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems

2. Indicate required installation sequences.

3. Indicate minimum access space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

4. Show locations and sizes of all access doors on vertical and horizontal surfaces throughout the facility.

5. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.

6. Comply with shop drawing requirements for sheet size and submittal methods specified in

Division 1 Section "Submittal Procedures."

B. Refer to Divisions 23, and 26 Plumbing, Heating Ventilating and Air Conditioning, and Electrical for specific coordination drawing requirements for mechanical and electrical installations.

C. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.

D. Work installed prior to approval of coordination drawings shall be at the Contractor’s risk.

Subsequent relocations required to avoid interferences shall be made without additional expense to the Government. In case interference develops, the Government will decide which work shall be relocated, regardless of which was installed first.

E. Digital Data Files of Coordination Drawings: Prepare coordination digital data files in accordance with the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings.

2. File Submittal Format: Same digital data software program, version, and operating system as the original Drawings and Portable Document Format (PDF).

Project Management And Coordination 013100 - 3

3. GSA will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.

a. GSA makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.

b. Digital Data Software Program: Edit to reflect latest versions and types of software (BIM, Revit, AUTOCAD, etc.) project will be using.

c. Execute a data licensing agreement in a form acceptable to the GSA, if required for Project.

1.4 CONSERVATION

A. Coordinate conservation of energy, water and materials in the conduct of construction operation.

Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.

B. Comply with Green Purchasing Plan requirements.

C. Waste Management Plan: Establish a program to maximize recycling of waste materials.

Program shall include the following:

1. Designation of a waste management coordinator.

2. Identification of recyclable materials.

3. Identification of available local recycling firms and agencies to receive recyclable materials.

4. Establishment of quantity goals for collection of each recyclable material.

5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.

6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.

7. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.

a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.

b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant stakeholder of the project, including the Government.

1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.

B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:

Project Management And Coordination 013100 - 4

1. Scheduling and sequencing of Work.

2. Sharing access to work spaces.

3. Installations.

4. Protection of work.

5. Cutting and patching.

6. Selections for compatibility.

7. Preparation of coordination of drawings.

8. Inspection and tests.

9. Temporary services and facilities.

C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."

D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.

1.6 CONFERENCES AND MEETINGS

A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.

1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:

a. Government.

b. Architect.

c. Major design consultants.

d. Contractor.

e. Major subcontractors.

f. Major suppliers.

g. Other concerned parties.

2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:

a. Tentative construction schedule.

b. Critical work sequencing.

c. Designation of responsible personnel.

d. Procedures for processing field decisions and Change Orders.

e. Procedures for processing Applications for Payment.

f. Distribution of Contract Documents.

g. Submittal of Shop Drawings, Product Data, and Samples.

h. Preparation of Record Documents.

i. Use of the premises.

j. Parking availability.

k. Office, work, and storage areas.

l. Equipment deliveries and priorities.

m. Safety procedures.

n. First aid.

Project Management And Coordination 013100 - 5

o. Security.

p. Housekeeping and progress cleaning.

q. Working hours.

r. Energy and resource efficiency / sustainability

s. Waste management

t. Commissioning

B. Progress Meetings: The Government or designee shall conduct progress meetings at the Project Site at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request.

1. Attendees: In addition to the Contractor's and Government's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.

a. Contractor's Construction Schedule: Review progress since the last progress meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. Provide four week schedule look ahead.

b. Review the present and future needs of each entity present, including but not limited to the following:

1) Interface requirements.

2) Time.

3) Sequences of operations.

4) Status of submittals.

5) Deliveries.

6) Off-site fabrication.

7) Access.

8) Site utilization.

9) Temporary facilities and controls.

10) Hours of work.

11) Hazards and risks.

12) Housekeeping and progress cleaning.

13) Quality and work standards.

14) Change Orders.

15) Documentation of information for payment requests.

16) Updating of Record Documents.

3. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.

Project Management And Coordination 013100 - 6

C. Project Closeout Conference: GSA will schedule and conduct a Project closeout conference, at a time convenient to Contractor, CM and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion

1. Attendees: Authorized representatives of GSA, CM, Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Coordination of final commissioning…