Questions & Answers 004

GS05P16SID7002

Question 1: If we are allowed to have both chillers down to conduct the eddy current at the same time we can get a cheaper price from the subcontractor. If we conduct this test during the winter months, would we be allowed to have both chillers down at the same time?

Answer 1: Yes, the preference is that the contractor conducts these tests during the winter months