About this file

This is a Request for Qualifications and Request for Fee Proposals issued by the Board of Regents of the University System of Georgia on behalf of Georgia Institute of Technology for Design-Build services on Project No. BR-30-2602 GTRI 1906 - 430 South Hawks Project. The project involves comprehensive renovation of approximately 27,000 square feet across three stories and a penthouse of an existing brick building at Georgia Tech's Atlanta campus. Work includes renovation of Levels G, 1, and 2, the penthouse, and roof, with construction of new secure spaces meeting ICD-705 standards, replacement of existing elevators and restrooms, infill of high bay space to create a new data center, installation of fire alarm systems, and security infrastructure including cameras, access control systems, and cabling. The project delivery method is Design-Build, with the Design Builder responsible for all design and construction services including preconstruction phases and construction administration. Statements of Qualifications were due May 22, 2026, with finalist notification expected May 29 through June 1, 2026. A mandatory pre-proposal site visit for finalists is scheduled for June 4, 2026 at 10:00 AM, limited to four personnel per team. Fee proposals from finalists are due June 23, 2026, with finalist interviews scheduled for June 24, 2026. The project should be operational by December 2028.

The Guaranteed Maximum Price is estimated at $33,700,000, with preliminary stated cost limitation of $30,600,000. Minimum qualifications for responding firms include current bonding capacity equal to the preliminary cost limitation, valid Georgia General Contractor's license, current liability insurance, business registration in Georgia, a current ratio of 1.0 or higher, and an Experience Modification Rating of 1.2 or less. Firms must submit documentation asserting compliance with these minimums and provide sworn certifications. No incumbent contractor information is identified. The project imposes security restrictions requiring all workers to be U.S. citizens with original birth certificates or passports, with no electronic devices permitted within construction boundaries. Only the highest-ranked firm's fee proposal will be opened, constituting a starting point for contract negotiations. The Owner reserves the right to reject any proposals and to negotiate terms with subsequent ranked firms if agreement cannot be reached with the highest-ranked firm.

View the file

Other files

File Type Posted
Egnyte Upload Instructions.pdf PDF
Exhibit F _ Project Cost Matrix.xlsx XLSX spreadsheet
Exhibit G _ Proposer_s Disclosure Statement.doc DOC document
Exhibit C _ DB Fee Proposal.docx DOCX document
Exhibit B _ Contractor Affidavit.docx DOCX document
Exhibit A _ Certification Form.docx DOCX document
Exhibit D _ Precon Cost and Expenses.xlsx XLSX spreadsheet
Exhibit E _ General Conditions Breakdown.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Board of Regents of the University System of Georgia

Request for Qualifications (Step I) and

Request for Fee Proposals & Interviews

(Step II)

To Provide

Design-Build Services

(DB)

for

Project No. BR-30-2602

GTRI 1906 - 430 South Hawks Project

Georgia Institute of Technology Atlanta, Georgia

Solicitation Issue Date: April, 30, 2026 Qualifications Packages Due: May, 22, 2026

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 1

TABLE OF CONTENTS

STEP I – REQUEST FOR QUALIFICATIONS (RFQ)

1. GENERAL PROJECT INFORMATION

2. DESIGN-BUILD SERVICES REQUIREMENTS

3. QUALIFICATIONS REVIEW PROCESS

4. SCHEDULE OF EVENTS (STEP I)

5. SUBMITTAL OF QUESTIONS AND REQUESTS FOR CLARIFICATIONS

6. INSTRUCTIONS FOR PREPARING STATEMENTS OF QUALIFICATIONS

7. SUBMITTAL OF STATEMENTS OF QUALIFICATIONS

8. FINALIST NOTIFICATION

STEP II – REQUEST FOR FEE PROPOSALS (from Qualified Finalists) & INTERVIEWS

1. SCHEDULE OF EVENTS (STEP II)

2. PRE-PROPOSAL SITE VISIT

3. SELECTION PROCESS

4. SUBMITTAL OF FEE PROPOSALS

5. PRESENTATION / INTERVIEW INFORMATION

6. ADDITIONAL TERMS AND CONDITIONS

EXHIBITS

a. Exhibit A – Certification Form

b. Exhibit B – Contractor Affidavit and Certificate of Compliance

c. Exhibit C – DB Fee Proposal

d. Exhibit D – Preconstruction Cost & Expenses Breakdown

e. Exhibit E – General Conditions Breakdown

f. Exhibit F – Project Cost Matrix

g. Exhibit G – Proposer’s Disclosure Statement

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 2

STEP I

REQUEST FOR QUALIFICATIONS

IMPORTANT: Read the document carefully, the selection requirements have changed!

Design Build Services

Project No. BR-30-2602 “GTRI 1906 - 430 South Hawks Project”

Georgia Institute of Technology Atlanta, Georgia

The Board of Regents of the University System of Georgia (“BOR”) As (“Owner”), on behalf of the Georgia Institute of Technology (“GIT”), is soliciting statements of qualifications from firms interested in providing design-build services for the construction of a project known as Project No. BR-30-2602 “GTRI 1906 - 430 South Hawks Project”, at Georgia Institute of Technology, Atlanta, Georgia. This Request for Qualifications (RFQ) seeks to identify potential providers of the above-mentioned services. Some firms that respond to this RFQ, who are determined by the Owner to be especially qualified, may be deemed eligible and may be invited to interview and offer proposals for these services. All respondents to this RFQ are subject to instructions communicated in this document and are cautioned to completely review the entire RFQ and follow instructions carefully. BOR reserves the right to reject any or all statements of qualifications or proposals, and to waive technicalities and informalities at their discretion.

1. GENERAL PROJECT INFORMATION

Project Background The Georgia Tech Research Institute (GTRI) is the nonprofit, applied research division of the Georgia Institute of Technology (Georgia Tech). Founded in 1934 as the Engineering Experiment Station, GTRI has grown to more than 2,400 employees supporting eight laboratories in over 20 locations around the country. It performs more than $500 million of problem-solving research annually for government and industry. Georgia Tech and GTRI combine the best of both applied and basic research to solve the innovation equation on behalf of clients. This combination provides unsurpassed expertise, technical solutions, and new levels of capability for our armed forces, our federal and state sponsors, our industry partners, and those with whom we collaborate worldwide.

GTRI is primarily located within three (3) major hubs around Atlanta. Within these facilities, GTRI has space that has been approved by the US Government as meeting the requirements for Sensitive Compartmented Information Facility (SCIF), Special Access Program Facility (SAPF) and Closed Facility. This type of space is critical for GTRI’s ability to meet the program requirements of our sponsors and government contracts.

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 3

Per the National Industrial Security Program Operating Manual, dated February 2006, GTRI is contractually obligated to follow: “Contractors shall protect all classified information to which they have access or custody. A contractor performing work within the confines of a Federal installation shall safeguard classified information according to the procedures of the host installation or agency.”

It is the responsibility of GTRI to protect all classified material within their custody at all times. GTRI meets this national security requirement in many ways. The primary method for safeguarding information is via the controlled space within our facilities. GTRI is experiencing an increase in research that is required to be performed in accredited facilities. GTRI has exceeded its available space that meets these secure requirements in the 10th Street Hub.

Project Description The 430 South Building is an existing three stories brick building with a penthouse. The project will be a comprehensive renovation of approximately 27,000 SF encompassing the plan east portion of Level G, all of Level 1, all of Level 2, all of the Penthouse, and the roof.

This renovation will be providing new secure spaces constructed in accordance with the ICD-705 construction standards for secure facilities. Construction will take place on all three levels of the building; the previously renovated secure space on the ground floor will remain as-is and will be occupied during construction. Renovation will include existing elevator and restroom replacement/modernization.

Construction will also include in-fill of existing high bay space to create additional square footage on the first floor for a new data center which supports the entire GTRI network. Existing data center must remain operational until transition to the new data center. The expanded and modernized data center will include modern electrical infrastructure including electrical and HVAC systems.

A new fire alarm system will be installed. The Design Build Contractor is responsible for designing and installing security cabling and equipment (Cameras/UL50/Access Control/Pink Noise). Conduit and low voltage cabling will be in the project scope. AV design and conduit infrastructure for audio-visual cabling is included in the scope, however wiring and AV devices will be by an Owner provided vendor. Project also may include some facade improvements as well as sitework and landscaping.

Sustainable Approach The Owner is not considering LEED Certification of this facility; however, the project will incorporate the requirements of the Energy Efficiency & Sustainable Construction Act (SB 130) (O.C.G.A. 50-8-

18) and may include other sustainable concepts where feasible to do so.

Project Delivery Method This project will utilize Design/Build as the project delivery method, and, as a minimum, will employ the services of a team that includes the Design Professional, General Contractor or Construction Manager. Georgia Institute of Technology will employ a 3rd Party Commissioning Agent.

Project Budget The Guaranteed Maximum Price is estimated at $33,700,000. The preliminary stated cost limitation (SCL) or construction cost of the Project is estimated at $30,600,000. The final SCL may be revised by the Owner due to final programmatic requirements, funding availability or other circumstances.

Project Schedule The Design Builder’s (DB) services are anticipated to commence by August 2026 with construction documents anticipated for completion in February 2027. Design deliverables and construction may be phased in order to accommodate government approvals. Based on a previous study, the first phase is expected to be the high bay structural, demolition, and roofing. The second phase is expected to be the data center. Following phases will be different ICD-705 areas depending on their

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 4 government approval. Assumptions on approval timelines should be 6 months for government approval. The shortlisted firms will be provided with the study and can examine the project requirements and provide input on the most effective phasing approach. Project should be accredited and operational by December 2028.

2. DESIGN-BUILD SERVICES REQUIREMENTS

The Design-Builder shall provide all design and construction services necessary for the Project. The Design-Build services shall include a Preconstruction/Design Phase, and a Construction Phase.

During the Design Phase, the Design-Builder shall provide design documents through its Design Professional. During the Preconstruction Phase, the Design-Builder will provide cost estimates and cost evaluation, value engineering recommendations, design analysis, constructability reviews and technical input on methods of construction, materials, details, and bidding formats and types of separate bidding packages. The Design-Builder shall provide assistance in studying various system design options.

During the Construction Phase, the Design-Builder shall be responsible for construction of the Project and be responsible for means & methods of construction, safety programs, and quality control. The Design-Builder shall competitively select all construction subcontracts in accordance with the terms of the Design-Build Contract. The Design-Builder’s Design professional shall perform the construction contract administration duties required by the Design-Build Contract. The successful Design-Builder will be required to work collaboratively with the Owner’s consultants.

All workers on the project must be US Citizens and provide either an original birth certificate or passport in order to be on site. No electronic devices including cell phones, tablets, computers, key fobs, or Bluetooth devices will be allowed within the construction boundaries.

3. QUALIFICATIONS REVIEW PROCESS

Selection of the DB will be a multi-step process generally following the steps outlined in the State Construction Manual.

Step I- Qualifications Review is initiated with this RFQ for the purpose of acquiring Statements of Qualifications from prospective DB firms. A selection of finalist firms will be made by a Selection Committee consisting of representatives of the User and BOR. The Selection Committee will receive, and review Statements of Qualifications submitted in response to this RFQ. To be deemed eligible for evaluation, firms must meet the following minimum qualifications:

Minimum Qualifications Required

• The firm or its principals are not currently ineligible, debarred, suspended, or otherwise excluded from bidding or contracting by any state or federal agency, department, or authority.

• Firm must have sufficient bonding capacity for anticipated total cost of work. Provide a letter or other supporting documentation from a bonding company indicating the firm’s capacity to bond the project.

• Firm must have a current Contractor’s Public Liability Insurance policy Refer to Insurance Requirements in the Owner’s Design Build (DB) contract at www.usg.edu/facilities/services/contracts_and_agreements. (The Owner reserves the right to require additional limits and/or coverage for actual contract). Provide your current insurance certificate.

• Firms must have all necessary, valid and current licenses to do business in the State of Georgia.

Provide a copy of your GC license, business license and Georgia Certificate of Existence.

http://www.usg.edu/facilities/services/contracts_and_agreement

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 5

• Firm must demonstrate sufficient cash flow to undertake the project as evidenced by a current ratio (assets/liabilities) of 1.0 or higher.

• The firm must demonstrate a commitment to safety with regard to Worker’s Compensation by having an Experience Modification Rate (EMR) over the past three years of 1.2 or less.

• The firm or its principals have not been terminated for cause or currently in default on any public works contract.

The firms must provide a sworn statement attesting to compliance with the minimum criteria listed above and provide supporting documentation as requested further in the process in accordance with deliverable (A) A-1 below in this RFQ.

The Selection Committee will then evaluate the submittals which have met the above minimum qualifications. Criteria for the evaluation are listed below:

Criteria for Evaluation of Statements of Qualifications

25% Factor: Stability of the firm, including the firm’s corporate history, resources, form of ownership, litigation history, financials, etc.

45% Factor: Firm’s relevant project experience and qualifications, including the demonstrated ability of firm in effective management of construction of facilities comparable in complexity, size, and function, for Owners such as University System of Georgia and other similarly-structured organizations. This includes relevant experience and qualifications of the firm’s proposed Project Team; and the demonstrated proficiency of the firm with projects similar to this Project.

30% Factor: Firm’s suitability to provide services for project, including whether the firm’s size and resources are appropriate in relation to the size and complexity of the project type, any unique qualifications for the project, current and projected workloads, the proximity of office to project location, knowledge of or experience with the local subcontractor market, and any special services or project for project-related concerns.

4. SCHEDULE OF EVENTS (STEP I)

The following Schedule of Events represents the Owner’s best estimate of the schedule that will be followed. All times indicated are prevailing times in Atlanta, Georgia. The Owner reserves the right to adjust the schedule as the Owner deems necessary.

5. SUBMITTAL OF QUESTIONS AND REQUESTS FOR CLARIFICATION

STEP I (RFQ) Estimated Timeline

a. Owner issues public advertisement of RFQ 04/30/26 -----

b. Deadline for written questions/requests for clarification (see section 6). 05/14/26 2:00pm

c. Deadline for submission of Statements of Qualifications 05/22/26 2:00pm

e. Owner completes evaluation, post results, and issues notification to finalist firms

05/29/26

06/01/26

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 6

It is the responsibility of each respondent to examine the entire RFQ and RFP, seek clarification in writing, and review its submittal for accuracy before submitting the document. Questions about any aspect of the RFQ, or the project, shall be submitted in writing (e-mail is preferable) to:

Mr. Michael Boeckl Sr. Project Manager Georgia Institute of Technology Office of Facilities Design & Construction, Room # 363E 151 6th Street NW, Atlanta, GA 30332 Email: Michael.Boeckl@facilities.gatech.edu

The deadlines for submission of questions relating to the RFQ are the times and dates shown in the (Schedule of Events- Section 4). All relevant questions and requests for clarification received by the Institution and the corresponding responses will be posted on the Georgia Procurement Registry at http://ssl.doas.state.ga.us/PRSapp/ as an addendum to the original solicitation for services. From the issue date of this solicitation until a successful proposer is selected and the selection is announced, respondents are not allowed to communicate for any reason with any members or employees of the BOR or the Institution except for submission of questions as instructed in the RFQ, or during the proposer’s conference (if applicable), or as provided by any existing work agreement(s). For violation of his provision, the Owner shall reserve the right to reject the proposal of the offending proposer.

6. INSTRUCTIONS FOR PREPARING STATEMENTS OF QUALIFICATIONS

Interested firms shall submit/upload one (1) electronic copy in .pdf format of the complete qualifications package to a BOR ftp site. Submittals must be prepared in a manner that fits a standard 8 ½” x 11” paper format when printed. Responses are limited to using a minimum of an 11-point font.

The entire response shall not exceed 50 single sided pages or 25 double sided pages, including exhibits, affidavits or other enclosure information that may be included in an appendix. All pages count regardless of content. Submittals that include qualifications of more than one firm shall not exceed page limits. Submittals that exceed the page limit will be deemed non-responsive and will not be considered by the Selection Committee.

STATEMENT OF QUALIFICATIONS

(DELIVERABLES “A”, “B”, “C” and “D” FOR ALL FIRMS)

A. Stability A1- Provide basic company information:

a. Company’s legal name, address, name of primary contact, telephone number, e-mail address, and company website (if available). If the firm has multiple offices, the qualification statement shall include information about the parent company and branch office separately.

b. Identify office from which project will be managed and this office’s proximity to the project site.

c. Indicate the year the local office was established and the number of persons staffing the local office and their disciplines.

d. Provide form of ownership (LLC, Corporation, Partnership, etc.) including state of residency or incorporation, and the year the company was established.

e. Provide general information about the firm's establishment, personnel resources, including disciplines and numbers and classifications of employees, and locations and staffing of offices that will be directly involved with this Project.

mailto:Michael.Boeckl@facilities.gatech.edu http://ssl.doas.state.ga.us/PRSapp/

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 7

f. List the firm’s annual revenue, for the parent office and the local office separately, if applicable, for the past 5 years.

A2- Describe your experience with ANY litigation with Owners and/or Architects. State basis of litigation (nonpayment, breach of contract, etc.).

A3- State whether the firm, or a member thereof, has ever been removed from a contract or failed to complete a contract as assigned? If so, provide explanation.

A4- The firm, in order to be deemed eligible for further evaluation, must provide supporting documentation asserting that the firm meets the minimum qualifications required for this project.

a. Certify that your firm or its principals are not currently ineligible, debarred, suspended, or otherwise excluded from bidding or contracting by any state or federal agency, department, or authority.

b. Certify that your firm has sufficient bonding capacity for anticipated total cost of work. Surety and insurance companies must be in the current Department of Treasury’s Listing of Approved Sureties (Department Circular 570). All insurance and bonds will be obtained through a company licensed by the Georgia Insurance Commissioner to transact the business of insurance in the State of Georgia for the applicable line of insurance in the State of Georgia for the applicable line of insurance. All insurers (or qualified self-insurers or group self-insureds, a specific excess insurer providing statutory limits) with an A.M. Best Financial Strength rating of “A- “or better with an A.M. Best Financial Size Category of Class V or larger. Provide a letter or other supporting documentation from your firm’s surety indicating the firm has a bonding capacity, equal to or greater than, the preliminary stated cost limitation (SCL) contained herein.

c. Certify your firm’s ability to meet or exceed the established insurance coverage requirements. A copy of the Certificate of Liability Insurance form is located at https://www.usg.edu/facilities/assets/facilities/documents/COI_-_new.pdf. (The Owner reserves the right to require additional limits and/or coverage for actual contract). Provide your firm’s current insurance certificate.

d. Certify your firm has a valid and current Georgia General Contractor’s License and must be registered to do business in the State of Georgia. Provide a valid copy of your Georgia General Contractor license, and a Georgia Certificate of Existence or other documentation stating your firm has registered with the Georgia Secretary of State and is authorized to do business in Georgia.

e. Certify your firm has sufficient cash flow to undertake the project as evidenced by a current ratio (assets/liabilities) of 1.0 or higher. Provide no more than a one-page statement evidencing your current ratio.

f. Certify your firm demonstrates a commitment to safety with regard to Worker’s Compensation by having a current Experience Modification Rating (EMR) of 1.2 or less. Provide evidence from your firm’s carrier on their letterhead of your firm’s

EMR.

A5- Complete the “Certification Form” (Exhibit A) and submit a scanned notarized copy with the firm’s Statement of Qualifications.

A6- Complete and submit the “Contractor Affidavit” (Exhibit B) and submit with the firm’s

Statement of Qualifications in compliance with the Georgia Security and Immigration Compliance Act.

GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT(S)

“Contractor” in the following Affidavits shall mean “General Contractor”/ ”Contractor” for the purpose of compliance with O.C.G.A. § 13-10-91, (b).

For the purpose of completing the attached Affidavits, please insert the following:

https://www.usg.edu/facilities/assets/facilities/documents/COI_-_new.pdf

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 8

• “Name of Public Employer” shall mean “Board of Regents of the University System of Georgia, Owner, for the use and benefit of Georgia Institute of Technology.

• “Name of Project” shall mean “BR-30-2602 GTRI 1906 - 430 South Hawks Project”.

Failure to submit this form with Statement of Qualifications will result in the firm being eliminated from consideration for this project.

A7- Complete the “Proposer’s Disclosure Statement” (Exhibit G) and submit with the firm’s

Statement of Qualifications.

B. Experience and Qualifications B1- Describe your firm’s proposed design-build team and include an organizational chart of the team. Please designate the specific individuals who will fill the key roles on your team and provide the percentage of time committed during the design, preconstruction phase and time committed on site during construction. Provide a resume for each individual.

Resumes should include information regarding similar projects completed. Firms should list all positions/persons that DB expects to serve on the design-build team or whose time will be charged to the project. This will include, but is not limited to:

a. Superintendent (s)

b. Project Manager

c. Design Professional

d. Project Executive/Director

e. Preconstruction Lead

f. Other project management/support staff providing basic services.

B2 Provide information on the construction firm’s experience on projects of similar size, function, and complexity (similar type of construction as the incumbent project). Describe no more than five (5) and no less than three (3) projects, in order of most relevant to least relevant, which demonstrate the firm's capabilities to perform the project at hand. For each project, the following information should be provided:

a. Project name, location and dates during which services were performed.

b. List the individuals who served as the Project Executive/Director, Project Manager, Superintendent, Design Professional and Cost Estimator on the projects. Please note whether these individuals are still employed with your firm and if they will be assigned to this project.

c. Brief description of project and physical description including delivery method, project duration, contract value, square footage, structural system/components, site area, unique project components or equipment. Include photographs.

d. Describe similarities in the construction of the highlighted project to our project being advertised including ICD-705 requirements, data center construction, and construction in occupied facilities. Include the relevancy of the similarities and experience with the highlighted project to the project being advertised.

e. Described services performed by your firm and (if multiple offices) the location of the office involved.

f. Respective Owner’s stated satisfaction in construction and service of your firm.

Provide any Owner-written letters of reference/recommendation about the firm’s performance on the project.

g. Owner/User/Architect contact information.

B3 Identify your proposed Design professional and provide basic company information:

Company name, address, name of primary contact, the year the company was established, telephone number, e-mail address, and company website (if available).

Identify office from which the project will be managed. Indicate the year the local office

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 9 was established and the number of persons staffing that office and their disciplines.

Provide form of ownership (LLC, Corporation, Partnership, etc), including state of residency or incorporation, and number of years in business.

B4 Provide information on the Design professional firm’s experience on projects of similar size, function, and complexity (similar type of construction as the incumbent project).

Describe no more than five (5) and no less than three (3) projects, in order of most relevant to least relevant, which demonstrate the firm's capabilities to perform the project at hand.

For each project, the following information should be provided:

a. Project name, location and dates during which services were performed.

b. List of the individuals who served as the Project Executive/Director, and Project Architect. Please note whether these individuals are still employed with your firm and if they will be assigned to this project.

c. Brief description of project and physical description (delivery method, contract value square footage, number of stories, site area, unique project components or equipment. Include photographs.

d. Describe similarities in the design and construction of the highlighted project to the project being advertised including ICD-705 requirements, data center design, and construction in occupied facilities. Include the relevancy of the similarities and experience with the highlighted project to the project being advertised.

e. Services performed by the firm and (if multiple offices) the location of the office involved.

f. Respective Owner’s stated satisfaction in construction and service of your firm.

Provide any Owner-written letters of reference/recommendation about the firm’s performance on the project.

g. Owner/User/Architect contact information.

C. General Management Approach

C1- General approach to the schedule management before and during design & construction.

C2- Provide a brief summary of your cost management plan for controlling costs while maintaining the project schedule.

C3- Provide a brief summary of your procurement process for ensuring adequate skilled workforce and proper subcontractor engagement.

C4- Provide a brief summary of your quality assurance plan. Describe your firm’s approach for validating compliance with construction documents.

D. Statement of Suitability

D1- Provide any information that may serve to differentiate your firm from other firms regarding suitability for the project. Suitability may include, but is not limited to, the firm’s fit to the project and/or needs of the Owner, any special or unique qualifications for the project, current and projected workloads, the proximity of office to project location, and any techniques or methodologies offered by the firm that may be particularly suitable for this project type.

D2- Indicate the proximity of the Project Site to the firm’s office that will be managing the Project. Describe your firm’s knowledge of or experience with the local subcontractor market. Provide information on any special services such as BIM capabilities, LEED Certification, offered by the firm that may be relevant and available for this project.

7. SUBMITTAL OF STATEMENTS OF QUALIFICATIONS

The Qualifications shall be uploaded as a one (1) complete package in .pdf format onto the BOR / Egnyte ftp site. Please do not submit individual documents or sections separately. The file shall be titled in the format below:

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 10

EXAMPLE: (BOR-Project No. BR-30-2602-DB, ABC Company, Qualifications)

See the document titled “Upload Instructions” on the Georgia Procurement Registry site along with this RFQ/RFP for detailed instructions regarding the upload of your submittal.

The total page count of the submittal must not exceed 50 single sided pages or 25 double sided pages. All pages count toward the total number of pages regardless of content. Qualification submittals that exceed the page limit will be deemed non-responsive and will not be considered by the selection committee.

If difficulty is encountered during upload, contact Josette Decatur-Hampton at (404) 962-3172 or josette.decatur-hampton@usg.edu for assistance or confirmation that the file was received. Firms are encouraged to verify their upload was successful at least 45 minutes prior to the deadline.

(Experience with the ftp site indicates that uploads do not always receive the confirmation statement that the file was successfully uploaded. Typically, files ranging in size from 3 – 10 mb, should not take more than one or two minutes to complete the upload).

Statements of Qualifications must be electronically received by the Owner prior to the deadline indicated in the Schedule of Events (Section 4 of RFQ). Printed copies will not be accepted. A list of firms submitting responsive Statements of Qualifications will be published on the Board of Regents’ Real Estate and Facilities website at http://www.usg.edu/facilities/external_partners/construction_professional_selections.

It is the responsibility of the Proposers to examine the entire Request, seek clarification in writing, and review their qualifications for accuracy before submitting a response. Once the deadline has passed, all submittals will be final.

All expenses for preparing and submitting responses are the sole cost of the party submitting the response. The Owner is not obligated to any party to reimburse such expenses. All submittals upon receipt become the property of the Owner. Labeling information provided in submittals “proprietary” or “confidential” or any other designation of restricted use will not protect the information from public view. Subject to the provisions of the Open Records Act, the details of the proposal documents will remain confidential until final award.

8. FINALIST NOTIFICATION

Once the Selection Committee has completed the evaluation of the Statements of Qualifications, the finalist firms will be notified in writing. The shortlisted firms will also appear on the Board of Regents’ Office of Real Estate and Facilities website at https://www.usg.edu/facilities/external_partners/construction_professional_selections and posted at the DB RFQ solicitation on Georgia Procurement Registry.

mailto:josette.decatur-hampton@usg.edu http://www.usg.edu/facilities/external_partners/construction_professional_selections https://www.usg.edu/facilities/external_partners/construction_professional_selections

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 11

STEP II

REQUEST FOR FEE PROPOSALS & INTERVIEWS

(From Qualified Finalists)

Step II- DB Selection, will be initiated by the invitation to the qualified finalists to submit Fee Proposals as instructed in the Request for Qualifications (RFQ). Finalist will be those firms determined by the Selection Committee to be especially qualified to perform as the Design Build services for this Project in accordance with the qualifications therein. The Owner will issue a notice to finalists to participate in an oral presentation/interview. The successful DB firm will be determined from the interviews and proposals received.

1. SCHEDULE OF EVENTS (STEP II)

The following Schedule of Events represents the Owner’s best estimate of the schedule that will be followed. All times indicated are prevailing times in Atlanta. The Owner reserves the right to adjust the schedule as the Owner deems necessary.

2. PRE-PROPOSAL SITE VISIT

A pre-proposal site visit will be conducted by the Owner, and attendance of finalist firms is mandatory.

The date for the conference and site visit will be as listed above. The site visitors will convene at a time and location to be determined and communicated in the Notice to Finalists. Site visit will be limited to 4 personnel per team and everybody must have a photo ID in order to access the facility.

Additional information, possibly including some plans and drawings, may be available at the site visit for finalist review. The Owner reserves the right to disqualify a proposer from the selection process due to a failure by a proposer to arrive for the site visit by the scheduled time. Failure to attend a mandatory site visit will automatically result in disqualification from the selection process.

3. SELECTION PROCESS

Step II- DB Selection will be initiated by the invitation to the qualified finalists by the Selection Committee (determined in Step I from evaluation of Statements of Qualifications) to submit Project Proposals as instructed in this RFP. Finalist interviews will also be conducted by the Owner. The successful DB will be determined from the evaluation of proposals received and interviews.

STEP II (RFP) Estimated Timeline Event Projected

Date Projected

Time

a. Owner issues notice to finalist firms to propose as instructed in RFP 06/01/26 ----------

b. Owner conducts Mandatory Pre-Proposal Site Visit for finalists 06/04/26 10:00 AM

c. Deadline for Site Visit written questions/requests for clarification 06/08/26 2:00 PM

d. Deadline for submission of Fee Proposals 06/23/26 2:00 PM

e. Owner interviews finalist firms 06/24/26 TBA

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 12

Criteria for the evaluation of Finalist Interviews:

50% Factor: Relevant Experience and Qualifications of the Proposed Project Team, including experience of the design professional, project manager and superintendent working together on past similar projects; experience of the team working together with the selected Program Manager (if applicable); team’s experience with projects of similar facility size, type, and complexity. The Owner may use references from stakeholders of the Owner’s choosing from previous projects of the finalists, among other information as necessary.

25% Factor: Proposed Management Plan: The firm’s approach to those Project issues presented in the interview.

25% Factor: Team Communications/Project Solutions: Committee’s overall impression of the firm and the overall impression of key team members and their ability to effectively answer project questions and provide solutions during the interview.

4. SUBMITTAL OF FEE PROPOSALS

Fee Proposals will be solicited from the finalists invited to interview. Firms must use the “DB Fee Proposal”, “Preconstruction Cost & Expenses Breakdown”, General Conditions Breakdown” and “Project Cost Matrix” forms (included as an Exhibits C, D, E & F to this RFQ/RFP) and submit one (1) password protected file electronically. Consult with your IT department if you need assistance with this process. Do not include any project proposal information.

Fee proposals must be received electronically by the Owner prior to the deadline indicated in the Schedule of Events (Section 1 of the Step II). See the document titled “Upload Instructions” on the Georgia Procurement Registry site along with this RFQ for detailed instructions regarding the upload of your document.

The file shall be titled in the format below:

EXAMPLE: (BOR-Project No. BR-30-2602-DB, ABC Company, Fee Proposal)

No fee proposal will be opened until one firm has been judged to be the highest ranked firm. Following the interviews, the highest ranked firm will be contacted to provide the document password. Only the fee proposal from the highest ranked firm will be opened. Please understand that this proposal constitutes a starting point for negotiation toward an eventual agreement on fees.

5. PRESENTATION/ INTERVIEW INFORMATION

Interview Format

Firms selected to make presentations shall be notified by the Invitation to Interview letter issued by the Selection Committee Manager. The Invitation to Interview letter shall designate a place and time for the interview session. The time allotted to each firm to present and be interviewed

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 13 will be in accordance with the State Construction Manual. The Invitation letter will specify the manner in which the presentations will be conducted.

• The interview will last a total of 50 minutes (30 minutes for the presentation, 20 minutes reserved for questions and answers). Teams will have 5 minutes prior to your interview to get your presentation set up. The Selection Committee will consist of representatives of the institution and the Board of Regents Office of Real Estate and Facilities.

• Electronic presentations, such as PowerPoint presentations are also allowed.

• BOR will typically have a screen and projector available in the interview room, and possibly a laptop computer. Nevertheless, presenters must be prepared with their own projector, flash drive and laptop computer in case unforeseen technical difficulties are encountered.

• The presentation may involve flip charts or boards along with the oral presentation.

• All members of the Selection Committee will be present during all the presentations.

• Firms are not allowed to address any questions to anyone other than the designated contact prior to the interview.

Interview Requirements The primary intent of the formal interview process is to provide the Selection Committee with in-depth and clarifying information about the firm. Information provided should assist the Selection Committee in making an informed decision as to the proposer best suited for the work. All key personnel should be present at the interview.

Firms should focus their presentations on their plan for managing the following construction issues:

• Your design approach.

• Your approach to the Preconstruction process including document review.

• Your subcontractor engagement and bidding process.

• Budgeting, estimating and cost management process

• Your scheduling process and any concerns with the stated project duration.

• Approach to constructing the project including any specific plans for phasing plans for the project, quality, the site plan, or other project issues.

• ICD 705 Construction, Data Center Construction, Occupied Building Construction

• Unique characteristics or services the firm offers.

Please bring a copy of your interview presentation on a thumb-drive to leave with the DB Selection Committee.

Firms are discouraged from reviewing general company history and past experience as submitted in Statements of Qualifications or Project Proposals unless this information is particularly relevant to the presentation. All key personnel should be present at the interview including at a minimum, the lead designer, project superintendent, project manager, and project executive.

Final Selection Upon completion of the evaluation and interview process by the Selection Committee, the firms will be ranked in descending order of recommendation. Negotiations will then be initiated with the best-qualified firm to finalize the terms and conditions of the contract. In the event a satisfactory fee agreement cannot be reached with the highest ranking firm, the Owner will formally terminate the negotiations in writing and enter into negotiations in turn with the second highest ranking firm and so on until a mutual agreement is established and the Owner awards an architectural services contract.

Refer to the BOR website for the most current version of Design Build Contract Between Design- Builder and Owner: https://www.usg.edu/facilities/services/contracts_and_agreements https://www.usg.edu/facilities/services/contracts_and_agreements https://www.usg.edu/facilities/services/contracts_and_agreements

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 14

6. ADDITIONAL TERMS AND CONDITIONS

Restriction of Communication From the issue date of this (RFQ) solicitation until a successful proposer is selected and the selection is announced, proposers are not allowed to communicate about this solicitation or this Project for any reason with any members of the Selection Committee, the Institution, or BOR, except for submission of questions as instructed in the RFQ/RFP, or during the proposer's conference (if applicable), or as provided by any existing work agreement(s). For violation of this provision, the Owner reserves the right to reject the proposal of the offending proposer.

Submittal Costs and Confidentiality All expenses for preparing and submitting responses are the sole cost of the party submitting the response. The Owner is not obligated to any party to reimburse such expenses. All submittals upon receipt become the property of the Owner. Labeling information provided in submittals “proprietary” or “confidential”, or any other designation of restricted use will not protect the information from public view. Subject to the provisions of the Open Records Act, the details of the proposal documents will remain confidential until final award.

Award Conditions This request is not an offer to contract or a solicitation of bids. This request and any statement of qualifications or proposal submitted in response, regardless of whether the proposal is determined to be the best proposal, is not binding upon the Owner and does not obligate the Owner to procure or contract for any services. Neither the Owner nor any party submitting a response will be bound unless and until a written contract mutually accepted by both parties is negotiated as to its terms and conditions and is signed by the Owner and a party containing such terms and conditions as are negotiated between those parties. The Owner reserves the right to waive non-compliance with any requirements of this Request for Proposal and to reject any or all proposals submitted in responses.

Upon receipt and review of responses, the Owner will determine the party(s) and proposal that in the sole judgment of the Owner is in the best interest of the Owner (if any is so determined), with respect to the evaluation criteria stated herein. The Owner then intends to conduct negotiations with such party(s) to determine if a mutually acceptable contract may be reached.

Reciprocal Preference Law Effective July 1, 2010, BOR will comply with all requirements of O.C.G.A. 13-10-3

a. Pursuant to O.C.G.A. 13-10-3, for the purpose of determining residency, a Georgia resident business shall include:

(1) Any business that regularly maintains a place from which business is physically conducted in Georgia for at least one year prior to any bid or proposal

(2) (or) a new business that is domiciled in Georgia which regularly maintains a place from which business is physically conducted in Georgia (provided) that a place of business shall not include a post office box, site trailer or temporary structure.

b. Whenever the state contracts for public works construction, materialmen, contractors, builders, architects, engineers and laborers resident in the State of Georgia are to be granted the same preference over materialmen, contractors, builders, architects, engineers and laborers resident in another state in the same manner, on the same basis, and to the same extent that preference is granted in awarding bids for the same goods or services by such other states.

Joint-Venture Proposals The Owner does not desire to enter into “joint-venture” agreements with multiple firms. In the event two or more firms desire to “team up” it is strongly recommended that one incorporated firm propose

Georgia Institute of Technology, BR-30-2602, GTRI 1906 - 430 South Hawks Project, DB RFQ/RFP 15 and maintain status as the contracted lead firm with the remaining firms participating as major consultants to the lead firm.

Minority and Small Business Enterprise It is the policy of the State of Georgia that minority-owned business enterprises (MBE), woman-owned business enterprises (WBE) and small business enterprises (SBE), have a fair and equal opportunity to participate in the State purchasing process. Therefore, the Owner encourages all MBE, WBE and SBE to compete for contracts to provide goods, services, and construction, and encourages contractors to solicit MBE, WBE and SBE in procuring subcontractors and suppliers. This desire on the part of the Owner is not intended to restrict or limit competitive bidding or to increase the cost of the work. The Owner supports a healthy free market system that seeks to include responsible businesses and provides ample opportunity for business growth and development. Contractors and subcontractors who utilize qualified minority subcontractors may qualify for a Georgia state income tax credits for qualified payments made to minority subcontractors. See Official Code of Georgia Annotated (O.C.G.A.) O.C.G.A. Section 48-7-38. For more information, please contact:

The Governor's Entrepreneur and Small Business Office 75 Fifth Street, Suite 825 Atlanta, Georgia 30308 Phone: 404.962.4071 http://www.georgia.org/Business/SmallBusiness/

Immigration Reform Compliance Requirement

The successful Proposer will be required to certify compliance with the Immigration Reform and Control Act of 1986 (IRCA), D.L. 99-603 and the Georgia Security and Immigration Compliance Act OCGA 13-10-90 et.seq., by meeting or having complied with one of the (2) following provisions and by executing any affidavits required by the rules and regulations issued by the Georgia Department of Labor set forth at Rule 300-10-1-01:

1) The Contractor warrants that Contractor has complied with the Immigration Reform and

Control Act of 1986 and the Georgia Security and Immigration Compliance Act by registering at https://www.vis-dhs.com/EmployerRegistration and verifying information of all new employees;

2) The successful proposer shall comply with the stipulations cited in Security and Immigration Compliance Act OCGA 13-10-91.with respect to the proper federal authorizations regarding the right to work for subcontractors and contractors.

Statement of Agreement With submission of a proposal, the Proposer agrees that he/she has carefully examined the Request for Qualifications (RFQ) & Request for Proposals (RFP), and the Proposer agrees that it is the Proposer’s responsibility to request clarification on any issues in any section of the RFQ/RFP with which the Proposer disagrees or needs clarified. The Proposer also understands that failure to mention these items in the proposal will be interpreted to mean that the Proposer is in full agreement with the terms, conditions, specifications and requirements in the therein.

END

http://www.georgia.org/Business/SmallBusiness/ https://www.vis-dhs.com/EmployerRegistration

Board of Regents of the University
System of Georgia
Request for Qualifications
(Step I)
and
Request for Fee Proposals & Interviews
(Step II)
___________________
To Provide
Design-Build Services
(DB)
Solicitation Issue Date: April, 30, 2026
Qualifications Packages Due: May, 22, 2026
TABLE OF CONTENTS
1. GENERAL PROJECT INFORMATION
3. QUALIFICATIONS REVIEW PROCESS
4. SCHEDULE OF EVENTS (STEP I)
A. Stability
B. Experience and Qualifications
b. List the individuals who served as the Project Executive/Director, Project Manager, Superintendent, Design Professional and Cost Estimator on the projects. Please note whether these individuals are still employed with your firm and if they will be ...
1. SCHEDULE OF EVENTS (STEP II)
6. ADDITIONAL TERMS AND CONDITIONS
Effective July 1, 2010, BOR will comply with all requirements of O.C.G.A. 13-10-3
Immigration Reform Compliance Requirement
The successful Proposer will be required to certify compliance with the Immigration Reform and Control Act of 1986 (IRCA), D.L. 99-603 and the Georgia Security and Immigration Compliance Act OCGA 13-10-90 et.seq., by meeting or having complied with o...

File details come from the government source that posted it. Updated .