Exhibit E _ General Conditions Breakdown.xlsx
XLSX spreadsheet 28 KB Posted
- Solicitation number
- PE-47200-RFQ-2026-000000125
- Issued by
- Fulton County, Georgia
About this file
This is a Construction Overhead Cost Breakdown form (Exhibit E) for a state or local construction contract with a General Maximum Price (GMP) of $46 million. The document provides a detailed line-item template for contractors to itemize construction overhead expenses across multiple categories including site supervision and management, site office expenses, safety and security, bonds and insurance, and miscellaneous project costs. The form requires bidders to fill in applicable costs for labor, materials, and subcontractor expenses, with explicit instructions that any attempts to recategorize items as "Fee," "Cost of Work," or "By Others" will result in a non-responsive proposal. The overhead cost categories encompass staffing positions such as senior project managers, project superintendents, engineers, and support personnel; office infrastructure and utilities; safety equipment and services; insurance and bonding requirements; and temporary facilities and equipment necessary for project execution.
The projected fee for the $46 million GMP is $1,231,000, which represents the baseline for the grand total of general conditions and fee. All cost line items in the submitted template show $0 values, indicating this is a blank form awaiting contractor completion. The breakdown structure separates labor costs, material costs, and subcontractor costs into distinct columns with subtotals for each category, allowing for transparent cost accounting. Notable items marked as "Included" (such as workers' compensation insurance, office supplies, computer equipment, and building permits) indicate these costs should be incorporated into other line items rather than listed separately, while items marked "NA" or "By Architect" are excluded from the contractor's overhead responsibility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Egnyte Upload Instructions.pdf | ||
| Exhibit F _ Project Cost Matrix.xlsx | XLSX spreadsheet | |
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document | |
| Exhibit C _ DB Fee Proposal.docx | DOCX document | |
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| Exhibit A _ Certification Form.docx | DOCX document | |
| Exhibit D _ Precon Cost and Expenses.xlsx | XLSX spreadsheet | |
| _GIT BR_30_2602 DB GTRI 1906_final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attach. B - Const. OH Cost)
| EXHIBIT E | |||||||||||||||||||||
| Fill-in all applicable costs, any attempts to recategorize any of these items as "Fee", "Cost of Work", or "By Others" will be treated as a non-responsive proposal. | |||||||||||||||||||||
| CONSTRUCTION OVERHEAD COST BREAKDOWN | |||||||||||||||||||||
| Description | Qty | Unit | Labor* | Mat'l** | Sub | Labor Subtotal | Mat'l Subtotal | Sub Subtotal | Total | Notes | Qty | Unit | Labor* | Mat'l** | Sub | Labor Subtotal | Mat'l Subtotal | Sub Subtotal | Total | Notes | |
| Site Supervision & Management: | |||||||||||||||||||||
| 1 | Senior Project Mgr. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 2 | Project Mgr. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 3 | Project Supt. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 4 | Asst. Project Supt. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 5 | Area Supt. | mos | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 6 | Secretary | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 7 | Project Engineer | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 8 | Engineer or Eng. Company | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 9 | Cost Control | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 10 | Safety Engineer | mos | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 11 | Scheduling | mos | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 12 | Purchasing | mos | $0 | $0 | $0 | $0 | 0 | $30,000 | |||||||||||||
| 13 | Project Accountant | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 14 | 0 | $0 | |||||||||||||||||||
| 15 | Incl. | ||||||||||||||||||||
| Subtotal | $0 | $0 | $0 | 0 | $0 | ||||||||||||||||
| $30,000 | |||||||||||||||||||||
| Site Office Expense: | |||||||||||||||||||||
| 18 | Job Office Trailer Rent | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 19 | Office Jobsite Build Out | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 20 | Office Jobsite Set-up | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 21 | Temp. Const. Trailer/Storage | ea | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 22 | Office Furniture | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 23 | Office Machines/Equip. | mos | $0 | $0 | $0 | $0 | Incl. Below | ||||||||||||||
| 24 | Copy Machines/Maintenance | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 25 | Office Supplies | mos | $0 | $0 | $0 | $0 | Incl. Above | ||||||||||||||
| 26 | Janitor/San. Supplies | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 27 | Postage & Shipping | mos | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 28 | First Aid/Med. Treat. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 29 | Telephone System | ls | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 30 | Phone Installation | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 31 | Phone Charges | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 32 | Phone Charges-Long Dist. | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 33 | Radio Communications | ea | $0 | $0 | $0 | $0 | By Arch. | ||||||||||||||
| 34 | Radio Maintenance | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 35 | Computer-PCS | mos | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 36 | Computers | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 37 | Software | allow | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 38 | MIS Charges | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 39 | Temp. Electric-Office | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 40 | Security-Office | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 41 | Water - Field Office | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 42 | |||||||||||||||||||||
| 43 | 0 | $0 | |||||||||||||||||||
| Subtotal | $0 | ||||||||||||||||||||
| $0 | |||||||||||||||||||||
| Safety & Security: | |||||||||||||||||||||
| 43 | Safety Incentives | ls | $0 | $0 | $0 | $0 | |||||||||||||||
| 44 | Watchman/Guard Ser. | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 45 | Traffic Control | ls | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 46 | Safety Equipment | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 47 | Rainwear/Hardhats, etc. | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 48 | Drug Testing | ea | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 49 | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 50 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||||
| Subtotal | $0 | ||||||||||||||||||||
| $0 | |||||||||||||||||||||
| Bonds & Insurance: | |||||||||||||||||||||
| 51 | Perform. & Payment Bonds | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 52 | Workers Comp. Insurance | mos | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 53 | Liability Insurance | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 54 | Fed. & State Unemployment | mos | $0 | $0 | $0 | $0 | $0 | 0 | $0 | ||||||||||||
| 55 | FICA | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 56 | Builders Risk Insurance | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 57 | |||||||||||||||||||||
| 58 | |||||||||||||||||||||
| Subtotal | $0 | ||||||||||||||||||||
| $0 | |||||||||||||||||||||
| Miscellaneous | |||||||||||||||||||||
| 59 | Off-Site Parking | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 60 | Ceremony Expense | ls | $0 | $0 | $0 | $0 | |||||||||||||||
| 61 | Vehicle for On-Site Project Manager | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 62 | Vehicle for On-Site Superintendent | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 63 | Vehicle Repairs/Maintenance | ls | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 64 | Water - Coolers | mos | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 65 | Water Barrels | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 66 | Ice Machine | mos | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 67 | Ice and/or Cups | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 68 | Temporary Toilets Install | ea | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 69 | Temporary Toilets | mos | $0 | $0 | $0 | $0 | $0 | 0 | $0 | ||||||||||||
| 70 | Cold Weather Protection | ls | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 71 | Temp. Heat for Bldg. | ls | $0 | $0 | $0 | $0 | $0 | 0 | $0 | ||||||||||||
| 72 | Job Signs | ea | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 73 | Progress Photos | ea | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 74 | Extra Plans & Specs. | ea | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 75 | Blueprint/Photostat. | allow | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 76 | Temp. Electric -Building | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 77 | Building Permit | ls | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 78 | Plan Check Fees | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 79 | NA | ||||||||||||||||||||
| 80 | NA | ||||||||||||||||||||
| Subtotal | $0 |
| TOTAL ALL CONSTRUCTION OVERHEAD COSTS: | $0 | ||
| 108 | Projected Fee (Based on $46 Million GMP) | ||
| $1,231,000 | |||
| 109 | Grand Total GCs & Fee | $0 | |
| ERROR:#REF! |