This document outlines an award fee plan for a federal contract to provide launch services. The contract is awarded by the Space and Missile Systems Center to support National Security Space Launch missions through fiscal year 2024. Evaluation criteria include support for government mission assurance, fleet surveillance, and responsiveness to government needs. Performance will be assessed over eight six-month periods, with available award fees of $20 million each. Criteria are grouped into mission assurance, surveillance, and responsiveness categories weighted 60%, 25%, and 15%. Scoring determines fee amounts from 0-100% using excellent, very good, good, satisfactory ratings. Half the earned fee will be withheld if a launch failure occurs.

Award Fee Plan

View the file

Other files for this federal contract opportunity

Other files attached to National Security Space Launch (NSSL) Phase 2 Launch Service Procurement (LSP) Request for Proposal (RFP), newest first.
File Type Posted
0 FA8811-19-R-0002 0002 Phase 2 LSP Amendment 2.pdf PDF
4B Attachment 2 DD254 SAP and SCI Addenda 20 December 2019.pdf PDF
6 Attachment 6 Evaluation Criteria 20 December 2019.pdf PDF
3 Attachment 1 PWS 20 December 2019.pdf PDF
5 Attachment 5 Instructions to Offerors 20 December 2019.pdf PDF
1 NSSL Phase 2 Model Contract 20 December 2019.pdf PDF
2 Exhibit A CDRLs 20 December 2019.pdf PDF
4A Attachment 2 DD254 20 December 2019.pdf PDF
Exhibit_A_CDRLs_23_July_2019.pdf PDF
NSSL_Phase_2_LSP_Model_Contract_28_June_2019.pdf PDF
Attachment_8_Pricing_Tables_23_July_2019.xlsx XLSX spreadsheet
Attachment_1_PWS_23_July_2019.pdf PDF
Attachment_5_Instructions_to_Offerors_23_July_2019.pdf PDF
Phase_2_Amendment_1_SF30_and_Summary_of_Changes.pdf PDF
Attachment_6_Evaluation_Criteria_3_May_19.pdf PDF
Attachment_4_Acceptance_Criteria_3_May_19.pdf PDF
Attachment_11_OCI_Plan_Cover_3_May_19.pdf PDF
Attachment_13_NRO_Phase_2_DD254_3_May_2019.pdf PDF
Attachment_5_Instructions_to_Offerors_3_May_19.pdf PDF
Attachment_2_DD254_3_May_19.pdf PDF
Attachment_9_Payment_Plan_3_May_19.pdf PDF
Attachment_7_Government_Property_Cover_3_May_19.pdf PDF
Attachment_3B_Small_Business_Participation_Commitment_3_May_19.pdf PDF
Attachment_1_PWS_3_May_19.pdf PDF
Attachment_3A_Small_Business_Subcontracting_Plan_Cover_3_May_19.pdf PDF
Attachment_13A_NRO_Phase_2_Requirements_Description_and_CDRLs_3_May19.pdf PDF
Attachment_10A_Cumulative_Mission_Success_Incentive_Plan_3_May_19.pdf PDF
NSSL_Phase_2_Model_Contract_3_May_19.pdf PDF
Attachment_8_Pricing_Tables_3_May_19.xlsx XLSX spreadsheet
Exhibit_A_CDRLs_3_May_19.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 10B:

Award Fee Plan

Contract No. FA8811-19-R-0002

Fee Determination Official

ROBERT BONGIOVI, Colonel, USAF Director Launch Enterprise Systems Directorate

APPROVAL:

PHILIP A GARRANT, Brigadier General, USAF Vice Commander Space and Missile System Center

TABLE OF CONTENTS

1. INTRODUCTION

2. ORGANIZATIONAL RESPONSIBILITIES

3. AWARD FEE PROCESS

4. FEE ALLOCATIONS BY EVALUATION PERIOD

5. AREAS OF EVALUATION/CRITERIA

6. INTERIM FEEDBACK

7. AWARD FEE INTEGRITY

8. AWARD FEE PLAN CHANGE PROCEDURE

9. TERMINATION FOR CONVENIENCE

ANNEX 1: AWARD FEE REVIEW BOARD MEMBERSHIP

ANNEX 2: EVALUATION CRITERIA

ANNEX 3: SAMPLE COMPUTATION OF AWARD FEE EARNED

1. INTRODUCTION

a. This Award Fee Plan describes the process for the Launch Enterprise Systems Directorate (LE) evaluation of the contractor's performance and the basis for presenting an assessment of that performance to the Fee Determination Official (FDO). The specific criteria used to assess contractor performance and to determine the amount of award fee earned are described herein. Award fee deals with those areas under the control of the contractor that are susceptible to qualitative and subjective evaluation.

b. The principal goal of the Award Fee Plan is to provide an incentive for the Contractor to satisfy performance criteria in the following categories: support to Government mission assurance, support to fleet surveillance, and responsiveness to Government need.

c. The award fee earned and payable under this plan is determined by the FDO based upon review of the Contractor's performance against the criteria established in Annex 2. The contractor begins each evaluation period with the potential to earn 100% of the available award fee (see Table 1: Evaluation Periods with Available Award Fee). The award fee amount earned is based upon the FDO rating of the contractor's overall performance during the evaluation period. The earned amount is provided to the contractor through contract modifications. The methodology for determining Award Fee is a unilateral decision made solely at the discretion of the Government.

2. ORGANIZATIONAL RESPONSIBILITIES

a. The award fee organization consists of the following: an FDO, the Award Fee Review Board (AFRB) with a chairperson and other membership approved by the FDO, a Procuring Contracting Officer (PCO), a recorder, and Performance Monitors. The members of this AFRB are identified in Annex 1 by their title and position in order to eliminate administrative changes to the plan when an individual member changes. The Performance Monitors are also identified in Annex 1 by their title, position.

b. Fee Determination Official: The LE Director will serve as the FDO. The FDO approves the Award Fee Plan, reviews the AFRB recommendation, considers the contractor self-assessment report and other pertinent data, and unilaterally determines the amount of award fee earned and payable to the contractor for each evaluation period.

c. Award Fee Review Board: The Cognizant Division Chief will serve as the AFRB Chairperson. AFRB members review the Performance Monitors' evaluation of the contractor's performance, review the contractor self-assessment report, other pertinent data and provide briefings as required, and recommend changes to this plan as necessary. Upon consideration of all information obtained from pertinent sources, the AFRB will arrive at a fee recommendation to be presented to the FDO by the AFRB Chairperson.

d. Procuring Contracting Officer: The PCO is the liaison between the contractor and Government personnel. The PCO transmits the FDO's award fee determination letter to the contractor, prepares and distributes the modification awarding the fee authorized by the

FDO after the FDO decision, and maintains appropriate award fee documentation as part of the official contract file.

e. Performance Monitors: Performance Monitors will continually monitor and maintain written records of the contractor's performance in their assigned evaluation area(s) so that a fair and accurate evaluation is obtained. Performance Monitors shall prepare end-of-period evaluation reports. Performance Monitors shall not be members of the AFRB.

f. Recorder: The AFRB recorder is responsible for coordinating the administrative actions of the performance monitors, AFRB, and FDO and accomplishing other actions as required ensuring the smooth operation of the award fee process.

3. AWARD FEE PROCESS

a. The AFRB will convene at the time, date, and place established by the Chairperson, and will consider information submitted by the following sources to make an award fee recommendation to the FDO:

1) Evaluations submitted by designated Performance Monitors.

i. The PM shall share the evaluation with the contractor 25 days prior to the established AFRB date.

ii. The contractor may submit a written response to the Performance Monitors end-of-period evaluation reports within 15 days of receipt. The Contractor's written response shall not exceed ten (10) pages.

2) Assessments or inputs from other sources (e.g., NRO, DCMA, DCAA, GAO, IG and users) as considered appropriate by the AFRB.

i. The PM shall share the assessments or inputs from other sources with the contractor 25 days prior to the established AFRB date.

ii. The contractor may submit a written response to the other sources end-of-period evaluation reports within 15 days of receipt. The Contractor's written response shall not exceed five (5) pages.

3) Optional written contractor self-assessment of performance may be submitted to the AFRB Chairperson through the PCO for each end-of-period evaluation period under consideration. Self-assessments shall be no more than ten pages in length and shall be submitted no later than ten (10) working days following the close of an evaluation period.

b. The Contractor will not be present during the deliberations or voting, as the AFRB is not a forum for arbitration. The participation by contractor personnel is limited to providing data and/or answering questions from AFRB members.

c. The AFRB members, after receiving the presentations of the Performance Monitors' evaluation and point score recommendations and reviewing all available information as appropriate, shall individually vote on each evaluation area by signed ballot (each member shall have only one vote).

d. The AFRB will brief the FDO on the AFRB's recommendations of the award fee amount to be paid to the Contractor and any recommended significant changes to the Award Fee Plan.

e. After the FDO decides an overall rating and the award fee amount for the evaluation period, an FDO determination letter will be sent to the Contractor within thirty (30) calendar days after the end of the evaluation period. The determination letter will inform the Contractor of the earned award fee amount and the major strengths and weaknesses of the Contractor for that evaluation period. When the FDO's determination differs from the AFRB recommendation, the FDO must provide written justification/rationale explaining why the difference and the justification/rationale shall become a part of the official contract file.

f. After the FDO determination letter is sent to the Contractor, the PCO will unilaterally modify the Task Order to award the fee for the earned amount. Contractor receipt of the Task Order will constitute formal notification of the amount of award fee earned as determined by the FDO.

4. FEE ALLOCATIONS BY EVALUATION PERIOD

The award fee earned by the Contractor will be determined at the completion of the evaluation periods shown below. The percentage and dollars shown corresponding to each period is the maximum amount that can be earned during that particular period.

Table 1: Evaluation Periods with Available Award Fee

Evaluation Period Timeframe Available Award Fee

1 Contract Award + 1 year $20,000,000 2 Year 1 End + 1 year $20,000,000 3 Year 2 End + 1 year $20,000,000 4 Year 3 End + 1 year $20,000,000 5 Year 4 End + 1 year $20,000,000

*6 Year 5 End + 1 year $20,000,000 *7 Year 6 End + 1 year $20,000,000 *8 Year 7 End + 1 year $10,000,000

*These years are included to capture the fly-out period of launch services and may not be funded if future contracts include this scope.

5. AREAS OF EVALUATION/CRITERIA

a. The Contractor will be evaluated using the criteria contained in Annex 2 and additional criteria, as proposed in Paragraph b. below, tailored to events specific to one or more award fee periods. The Areas of Evaluation and their corresponding percentage weightings are set forth below:

Category 1: Support to Government Mission Assurance 60%

Category 2: Support to Fleet Surveillance 25%

Category 3: Responsiveness to Government Need 15%

Total: 100%

b. If the PCO does not give specific notice in writing to the Contractor of any change to the evaluation areas prior to the start of a new evaluation period, then the same standards for the preceding period will be used in the new award fee evaluation period. However, subsequent evaluation areas may require greater or lesser emphasis and other evaluation areas may surface as the effort becomes clearer or as emphasis shifts. Prior to the beginning of any period, the Contractor may provide Award Fee Plan inputs for the upcoming period. Any changes to the Evaluation Areas, Evaluation Criteria, or the corresponding percentage weightings will be unilaterally made by the PCO, with written notice to the contractor prior to the start of the evaluation period. Subsequent to the start of an evaluation period, changes may only be made by mutual agreement of both parties.

c. Except as set forth in paragraph d. below, the Contractor will earn award fee by achieving a level of effectiveness in accordance with the evaluation criteria set forth in Annex 2. The contractor's effort in a particular area shall receive a recommended point score from the performance monitor for that area. The individual area point scores are weighted (per paragraph 5.a. above) and then summed to get a Total (aggregated) performance point score.

See Annex 3 for a sample computation. If the Contractor's "overall performance" (Total Weighted Point Score in Annex 3) is rated 49 or below, the Contractor shall receive zero award fee dollars ($0) for the award fee period and will be rated "Unsatisfactory".

Otherwise, the earned award fee amount is a linear point-to-percentage conversion of overall (Total) performance at or above 50% as per Table 2 below. The award point score will be rounded to the nearest whole number.

d. If in any award fee period a launch service is deemed a Mission Failure as defined per Attachment 4, Acceptance Criteria, only half of the award fee earned will be paid. If multiple launch services are deemed Mission Failures, no award fee amount will be paid.

This is to ensure Category 1: Support to Government Mission Assurance, is the contractor’s highest priority. Any Mission Failure during the award fee period demonstrates a clear lack of support to Government mission assurance and therefore shall automatically disqualify the contractor from receiving half of the earned award fee. This 50% deduction will take place after the ARFB has met and the earned award fee score has been determined.

Table 2: Award Fee Adjectival Rating and Corresponding Award Fee Earned

Rating Description Point Score AFRB Corresponding Percent (%) of Award Fee Earned

Excellent 91-100 91-100% Very Good 76-90 76-90% Good 51-75 51-75% Satisfactory 50 50% Unsatisfactory <50 0%

6. INTERIM FEEDBACK

Interim Feedback shall be conducted on a Semi-Annual basis, once at the midway point of the evaluation and once after the final evaluation. Every effort will be made to provide routine feedback to the Contractor addressing the Contractor's overall performance. The AFRB Chairperson may issue letters at any time when it is deemed necessary to highlight areas of Government concern or commendation. For each letter issued, the Contractor is required to provide a written response within 30 days. The response should set forth plans for increasing effectiveness in the areas addressed or explain why it is not feasible to do so.

7. AWARD FEE INTEGRITY

Although the award fee process is recognized to be subjective in nature, every effort will be made to ensure reasonableness and fairness. The written records of performance provides the checks and balances necessary to ensure award fee integrity.

8. AWARD FEE PLAN CHANGE PROCEDURE

All significant changes to the Award Fee Plan are approved by the FDO; the AFRB Chairperson approves other changes. Examples of significant changes include changing evaluation criteria, adjusting weights to redirect the Contractor's emphasis to areas needing improvement, changing AFRB membership, and revising the distribution of the award fee dollars. After approval by the FDO or AFRB Chairperson, the PCO shall notify the contractor in writing of any change(s).

Unilateral changes may be made to the Award Fee Plan if the Contractor is provided written notification by the PCO before the start of the upcoming evaluation period. Changes affecting the current evaluation period must be by bilateral agreement.

9. TERMINATION FOR CONVENIENCE

In the event of termination of this contract for convenience, the award fee period, in which termination occurs, shall end, and the award fee process shall be implemented as if the period had been completed. The Government will evaluate the Contractor's performance for the period in which the termination occurs and the amount of award fee will be prorated, based upon the amount of work completed as determined by the PCO. The determination of the earned award fee and the amount of work completed are subject to the Contract Disputes. In the event of a termination for default, the award fee is payable only to the extent earned through the last period prior to termination.

ANNEX 1: AWARD FEE REVIEW BOARD MEMBERSHIP

1. Division Chief (Chairperson), Cognizant Launch Service Provider Division

2. Chief Engineer, Launch Systems Enterprise Directorate

3. Commander, 30th Launch Group (30 LCG)

4. Commander, 45th Launch Group (45 LCG)

5. Director, Office of Space Launch (NRO/OSL)

6. Chief of the Contracting Office, Launch Enterprise Systems Directorate (SMC/LEK)

7. Contracting Officer, Cognizant Launch Service Provider (SMC/LEK)

8. Commander, Cognizant Defense Contract Management Agency (DCMA)

Advisors: Non-Voting Members

1. AFRB Recorder (SMC/ Cognizant Launch Service Provider)

2. Other LE Division Chiefs

Performance Monitors

1. Contracting Officer Representative for LSS CLIN Support to Government Mission

Assurance

2. Contracting Officer Representative for FS CLIN Support to Fleet Surveillance

3. Branch Chief (Cognizant Launch Service Provider) Responsiveness to Government Need

ANNEX 2: EVALUATION CRITERIA

SUPPORT TO GOVERNMENT MISSION ASSURANCE

Meets

Expectations Exceeds

Expectations Greatly Exceeds

Expectations 51 to 90 points 91 to 100 points

Maintains an effective team relationship with the Government Mission Assurance team

Meets Mission Assurance requirements and ensures delivery of quality products and services

Provides timely notification to the Government for any significant Mission Assurance issue

Responds to government inquiries in timely and complete manner

Conducts all contractually required meetings, reviews, etc. in an organized and comprehensive manner

Provides timely updates on outstanding issues and risk items

Maintains and complies with current approved policies, practices, and procedures

Identifies, tracks, and provides updates on key risks

Supports execution of Mission Assurance processes IAW PWS

IDE has high MTBF and low MTTR

Meets all “Meets Expectations” requirements plus the following:

Establishes an efficient battle rhythm with the Government, FFRDC and support contractors.

Identifies and executes efficiencies for mission assurance activities in partnership with mission stakeholders

Holds special meetings, reviews, etc. to address specific issue areas

Provides continuous updates on issues and risk items

Submits improvement recommendations for existing policies, practices, and procedures with analysis and rationale

IDE has very high MTBF and low MTTR

Meets all “Meets Expectations and “Exceeds Expectations” requirements plus the following:

Proactively engages the

Government, FFRDC, and support contractors to resolve Mission Assurance issues

Exceeds Mission Assurance data requirements and delivers exceptional quality products and services

Proactively engages the Government, FFRDC and support contractors, with actionable recommendations to enhance agility in mission assurance activities

Anticipates Government, FFRDC, and support contractors’ requests for information and analysis

IDE has very high mean time between failures (MTBF) & very low mean time to repair (MTTR)

Doesn’t Meet Expectations - Contractor fails to meet criteria for “Meets Expectations” performance.

ANNEX 2 EVALUATION CRITERIA (Cont.)

SUPPORT TO FLEET SURVEILLANCE

Meets Expectations

Exceeds Expectations

Greatly Exceeds Expectations

51 to 90 points 91 to 100 points Maintains an effective team relationship with the Government, Fleet Surveillance team

Meets Fleet Surveillance requirements and ensures delivery of quality products and services

Provides timely notification to the Government for any significant Fleet Surveillance issue

Responds to government inquiries in timely and complete manner

Provides timely updates on outstanding issues and risk items

Maintains and complies with current approved policies, practices, and procedures

Identifies, tracks, and provides updates on key fleet risks

Supports execution of Fleet Surveillance processes IAW the PWS plus the following:

Establishes an efficient battle rhythm with government, FFRDC, and support contractors

Identifies and executes efficiencies in partnership with mission stakeholders such as launch operations, subcontractors, etc.

Identifies and executes efficiencies for Fleet Surveillance activities in partnership with mission stakeholders

Holds special meetings, reviews, etc. to address specific fleet issue areas

Provides continuous updates on fleet issues and risk items

Submits improvement recommendations for existing policies, practices, and procedures with analysis and rationale requirements plus the following:

Proactively engages the

Government, FFRDC, and support contractors to resolve Fleet Surveillance issues

Exceeds Fleet Surveillance requirements and delivers exceptional quality products and services

Anticipates Government, FFRDC, and support contractors’ requests for information and analysis

ANNEX 2 EVALUATION CRITERIA (Cont.)

RESPONSIVENESS TO GOVERNMENT NEED

Meets

Expectations Exceeds

Expectations Greatly Exceeds

Expectations 51 to 90 points 91 to 100 points

Maintains an effective team relationship with the Government, FFRDC, and support contractors

Meets PWS requirements and ensures delivery of quality products and services

Provides timely notification to the Government for any significant management issue

Responds to government inquiries in timely and complete manner

Conducts all contractually required meetings, reviews, etc. in an organized and comprehensive manner

Provides timely updates on outstanding issues and risk items

Maintains and complies with current approved policies, practices, and procedures

Identifies, tracks, and provides updates on key risks

Supports execution of the contract IAW the PWS plus the following:

Establishes an efficient battle rhythm with government, FFRDC, and support contractors

Identifies and executes efficiencies in partnership with mission stakeholders such as satellite SPO, launch operations, subcontractors, etc.

Identifies and executes efficiencies for program activities in partnership with mission stakeholders Holds special meetings, reviews, etc. to address specific issue areas

Provides continuous updates on issues and risk items

Submits improvement recommendations for existing policies, practices, and procedures with analysis and rationale requirements plus the following:

Proactively engages the

Government, FFRDC, and support contractors to resolve issues

Exceeds PWS requirements and delivers exceptional quality products and services

Anticipates Government, FFRDC, and support contractors’ requests for information and analysis