Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
See Block #2
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQ.NO.
5. PROJECT NO. (If applicable)
6. ISSUED BY AFLCMC/PZIEB CODE FA8604 7. ADMINISTERED BY (If other than Item 6) CODE
USAF/AFMC/AFLCMC
AF LIFE CYCLE MANAGEMENT CENTER
2275 D STREET, BLDG 16, RM 128
WRIGHT-PATTERSON AFB OH 45433-7228
ZACHARY P. REYNOLDS 937-656-7381
ZACHARY.REYNOLDS@US.AF.MIL
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
FA860419R8116000
X
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X )
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: ( ) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. ITEM
10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor X is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Non-ACAT MMHS at SHAW AFB, Incorporate revised Appendix E, Section J, Attachment 6, Extend the Proposal Submission Date, and Respond to Questions.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print).
16A. NAME AND TITLE OF SIGNER (Type or print)
15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
16C. DATE SIGNED
(Signature of person authorized to sign)
BY________________________________________
(Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA ConWrite Version 7.1.2.2 FAR (48 CFR) 53.243 Created 15 Jul 2019 3:18 PM
CONTRACT DOCUMENTS, EXHIBITS AND ATTACHMENTS
FA860419R81160003 PAGE 2 OF 3
1. This amendment hereby incorporates:
a. Revised Appendix E, (REV 1), Section J, Attachment 6, dated 15 July 2019.
b. Extend the proposal submission date to 09 Aug 2019.
c. Responses to Questions.
2. All other terms and conditions remain the same.
SCHEDULE
FA860419R81160003
DOCUMENT PGS DATE TITLE
ATTACHMENT 6 14 15 JUL 2019 APPENDIX E FOR MODULAR CABINETS AND
MINI-MEZZANINE AT SHAW AIR FORCE BASE,
SOUTH CAROLINA BUILDINGS 216 AND 1604
CSN: TSH804
APPENDIX E
FOR
MODULAR CABINETS and MINI-MEZZANINE
AT
SHAW AIR FORCE BASE, SOUTH CAROLINA
BUILDINGS 216 and 1604
CSN: TSH804
DATE: 15 MARCH 2019
REVISON 1: 15 JULY 2019
PREPARED BY:
James F. Rowland
JAMES F. ROWLAND
PROJECT ENGINEER
AFLCMC/EZPAE
Megan Blackwell
MEGAN BLACKWELL
REVIEWER
AFLCMC/EZPAE
Shaw AFB, SC – App E – Page ii
Table of Contents
1. SCOPE
2. APPLICABLE DOCUMENTS
3. REQUIREMENTS
3.1. SYSTEM DESCRIPTION
3.2. CHARACTERISTICS
3.2.1. MODULAR CABINETS
3.2.1.1. MODULAR CABINET
3.2.1.2. CABINET HOUSING LOAD CAPACITY
3.2.1.3. PALLET BASE
3.2.1.4. BASE ENCLOSURE
3.2.1.5. DRAWERS
3.2.1.5.1. DRAWER LOAD CAPACITY
3.2.1.5.2. DRAWER DIMENSIONS
3.2.1.5.3. DRAWER PUSH-PULL FORCES
3.2.1.5.4. DRAWER DIVIDER STRIPS
3.2.1.5.5. PARTITIONS
3.2.1.5.6. CROSSWISE DIVIDERS
3.2.1.5.7. DRAWER PULL LABEL HOLDING SYSTEM
3.2.1.5.8. DRAWER STOPS
3.2.1.5.9. CARRIAGES AND BRACKETS
3.2.1.6. DRAWER CONFIGURATION
3.2.1.7. CABINET LOCK (REV 1)
3.2.2. MINI-MEZZANINE CONFIGURATION
3.2.2.1. STAIRWAY
3.2.2.2. HANDRAIL
3.2.2.3. RUBBER MAT
3.2.2.4. ASSEMBLY
3.2.2.5. ALIGNMENT
3.2.2.5.1. STORAGE UNIT VERTICAL ALIGNMENT
4. QUALITY CONFORMANCE
4.1. INSPECTIONS
4.2. TESTS
4.3. CERTIFICATIONS
Shaw AFB, SC - App E - Page 1
1. SCOPE
This appendix establishes the minimum performance, design, fabrication, installation, and test requirements for modular cabinets and a modular cabinet mini-mezzanine system for Buildings 216 and 1604 at Shaw AFB, South Carolina. The work shall be completed in accordance with this appendix, the Cover Purchase Description (PD), and Air Force (AF) Drawings TSH804-02 and -06. This appendix covers all equipment, materials, and labor necessary to complete installation of the system.
2. APPLICABLE DOCUMENTS
Applicable documents shall be in accordance with Section 2 of the Cover PD.
3. REQUIREMENTS
3.1. SYSTEM DESCRIPTION
The modular cabinet system as well as the modular cabinet mini-mezzanine shelving system will be used to store small sized items in such a manner as to permit placement and removal of any individual item.
3.2. CHARACTERISTICS
3.2.1. MODULAR CABINETS
A modular cabinet is defined as a unitary set of drawers/shelves and the housing or cabinet used to support the drawers/shelves.
Individual drawers shall be compartmentalized to provide separation between different parts. The modular cabinet storage systems shall be located and configured as shown on AF Drawings TSH804-02 and -06. The system shall be modular in construction for easy dismantling and re-assembly.
3.2.1.1. MODULAR CABINET
Three different cabinet configuration types, shown as Type “MC1”, Type “MC2”, and Type “MC3” on AF Drawings TSH804-02 and - 06, shall be provided for this system. Each cabinet shall have outside dimensions as specified in Table 1.
Shaw AFB, SC - App E - Page 2
Table 1. Outside Cabinet Dimensions
Cabinet Configuration
Type
Quantity Width (inches)
Depth (inches)
Height (inches)
MC1 78 29 +/- 1¼ 28 +/- ½ 89 +/- 1¼
MC2 10 29 +/- 1¼ 28 +/- ½ 148 +/- 1¼
MC3 10 29 +/- 1¼ 28 +/- ½ 60 +/- 1¼
The modular cabinet shall have drawers configured as specified in Table 2.
3.2.1.2. CABINET HOUSING LOAD CAPACITY
Each cabinet housing shall be capable of supporting a minimum static load of 10,000 pounds.
3.2.1.3. PALLET BASE
Each modular cabinet shall be provided with a built-in pallet base. The pallet base shall be an integral part of the modular cabinet. The pallet base shall have a height of 2.5 +/- 0.5 inches.
3.2.1.4. BASE ENCLOSURE
Each modular cabinet shall have removable base enclosure plates to cover the front and rear of the pallet base.
3.2.1.5. DRAWERS
3.2.1.5.1. DRAWER LOAD CAPACITY
Each drawer shall have a minimum capacity of 400 pounds. When fully loaded with 400 pounds, all drawers shall be capable of being opened and closed without jamming or twisting of the carriage. When fully loaded, an open drawer shall not exhibit deflection greater than 0.62 inch from its closed position, when measured from the floor to the middle of the front of the drawer.
3.2.1.5.2. DRAWER DIMENSIONS
For Type “MC1”, “MC2”, and “MC3” cabinet configurations, the inside drawer dimensions shall be 25 inches +/- 1 inch for both width and depth. The height of the sides and back wall of the
Shaw AFB, SC - App E - Page 3 drawer shall not be less than 48 percent of the drawer front height.
3.2.1.5.3. DRAWER PUSH-PULL FORCES
The forces required to move a drawer, loaded to the maximum capacity of 400 pounds per drawer, shall not exceed 25 pounds to start outward, 45 pounds to start inward, and 40 pounds to continue moving.
3.2.1.5.4. DRAWER DIVIDER STRIPS
Divider strips shall be provided around the four inside walls of each drawer. The divider strips shall be factory installed, and an integral part of the drawer. The divider strips shall provide for spacing of partitions and crosswise dividers in a range of 0.50 inch to 1 inch intervals.
3.2.1.5.5. PARTITIONS
Partitions shall be defined as drawer dividers which run from front-to-back of each drawer. All partitions shall be made of steel. Partitions shall have slot spacing to match the drawer divider strips for placement of crosswise dividers. Each partition shall be anchored with a minimum of two bolts and nuts or two self-tapping metal screws to the bottom of the drawer to keep the partition flush against the bottom of the drawer. The height of the partitions and crosswise dividers shall be no less than 75% of the height of the drawer body. All partitions shall be installed across the depth of each drawer.
3.2.1.5.6. CROSSWISE DIVIDERS
Crosswise dividers shall be defined as dividers placed between adjacent partitions or between a drawer divider strip and a partition. All crosswise dividers shall be made of steel or aluminum. Crosswise dividers shall be easily removable and interchangeable with other crosswise dividers of the same size.
All crosswise dividers shall be installed across the width of each compartment.
3.2.1.5.7. DRAWER PULL LABEL HOLDING SYSTEM
Each drawer pull shall be aluminum and shall have a label holding system. The label holding system shall be at least 20 inches long and shall be designed to accept a label at least one inch high. The label holding system shall have a clear plastic shield covering a paper label with plastic or aluminum end caps
Shaw AFB, SC - App E - Page 4 that provide an enclosed label system. The contractor shall provide two spare label end caps per cabinet. There shall be no sharp protrusions on any part of the drawer pull label holding system.
3.2.1.5.8. DRAWER STOPS
Each drawer shall be equipped with drawer stops to prevent over-travel of the drawer when fully extended. These safety stops shall prevent the drawer from being removed unless released by the operator.
3.2.1.5.9. CARRIAGES AND BRACKETS
The cabinets shall include carriages (defined as rolling intermediate members which permit 100 percent extension of the drawer interior) and minimum 10 gauge steel brackets or side channels (defined as those members fixed to the sides of the cabinets). Carriages shall operate on precision ball and/or roller bearings. All carriages and brackets shall be the same for all drawers and completely interchangeable to preclude any possibility of an unsafe mix-up of lightweight brackets and carriages with heavily loaded drawers.
3.2.1.6. DRAWER CONFIGURATION
The modular cabinet configuration shall be as indicated in Table
1. Each drawer shall be compartmentalized such that the assigned numbers of compartments are provided as shown in Table
1. The compartments within a single drawer shall be approximately equal in size.
TABLE 2 - MODULAR CABINET CONFIGURATION
Number of Drawers
Usable Height
(inches)
Number of Compartments Across Width
Number of Compartments Across Depth
Modular Cabinet Configuration “MC1” – Quantity 78 6 3-7/8” 4 5 4 5-3/8” 4 4
Modular Cabinet Configuration “MC2” – Quantity 10 6 3-7/8” 4 5 4 5-3/8” 4 4
Shaw AFB, SC - App E - Page 5
Modular Cabinet Configuration “MC3” – Quantity 10 6 3-7/8” 4 6 4 5-3/8” 4 3
Open Shelving Unit 1 shelves per unit providing two shelving locations (bottom of cabinet and the 1 shelf). Shelf spacing shall provide approximately equal storage areas.
3.2.1.7. CABINET LOCK (REV 1)
Each cabinet of the modular cabinet system shall have a keyed lock. The lock shall prevent unauthorized entry into a cabinet drawer. Each modular storage cabinet system shall have a minimum of five keys/building. All locks shall be keyed alike.
3.2.2. MINI-MEZZANINE CONFIGURATION
The Contractor shall configure cabinet Types “MC1”, “MC2”, and “MC3” into a mini-mezzanine system as shown on AF Drawing TSH804-02. The mini-mezzanine configuration is obtained by stacked modular cabinets so with the upper levels accessible via a stairway. The top surface of the lower level modular cabinets becomes the walkway to access the upper level cabinets. Safety for personnel walking on top of the cabinets is provided by handrails and rubber mats. There shall be no stacked cabinets at the stairs.
3.2.2.1. STAIRWAY
Stairways shall be made of rigid steel and shall support a 250-pound person without any component exhibiting elastic deflection greater than 0.12 inch or permanent deformation. Stair treads shall have a non-skid surface. Stairways shall be designed and constructed in accordance with IBC. Stairway systems shall be painted safety yellow.
3.2.2.2. HANDRAIL
Handrails shall be provided to completely enclose the top walkways and stairways providing fall protection at all hazardous walking elevations. The railing shall consist of a top rail, mid- rail, kick plate, and support posts. Handrails shall be a minimum of 1.25 inches in diameter and shall be 42 inches +/- 2 inches above the walkway. The distance between handrail support posts shall be maximum 60 inches. Handrails, mid-rails, and kick plates shall have a support post at both ends and shall not be cantilevered beyond the support posts.
Shaw AFB, SC - App E - Page 6
Handrails shall be a closed shape such as a round or square.
Handrails shall withstand a minimum load of 200 pounds applied in any direction on the top rail without permanent deformation or damage. Fall protection shall be securely fastened to prevent movement of the top rail. Kick plates shall extend a minimum of 4 inches above the walkway. Fall protection shall conform to OSHA 1910. Handrails shall be painted safety yellow.
3.2.2.3. RUBBER MAT
A non-skid rubber mat shall be provided for all walkways on top of a modular cabinet. The mat shall be provided in as few pieces as practical to reduce the number of joints that are trip hazards.
3.2.2.4. ASSEMBLY
The Contractor shall assemble all cabinets including: leveling cabinets, installing base enclosures, installing drawers in cabinets, installing compartmentalization (partitions and crosswise dividers), installing shelves, installing stairs, installing handrails, and installing rubber mats. The mini-mezzanine system shall be designed to be a rigid freestanding structure and shall not be connected to any existing building structure. The Contractor shall provide and install all necessary hardware to configure the modular cabinets as a mini-mezzanine. Each upper level cabinet shall be bolted to the top of the cabinet underneath it. All back-to-back modular cabinets shall be bolted together.
3.2.2.5. ALIGNMENT
After assembly, the storage units shall be capable of maintaining the same position in all loaded conditions.
Alignment of each row of storage units shall be in two directions: down the row of storage units, maintaining the proper aisle width between adjacent rows of storage units; and vertically for each drawer/shelf cabinet face.
3.2.2.5.1. STORAGE UNIT VERTICAL ALIGNMENT
Each storage unit face shall be plumb to within 0.12 inch from the floor to the top of the unit.
4. QUALITY CONFORMANCE
4.1. INSPECTIONS
Shaw AFB, SC - App E - Page 7
The system shall be inspected to verify that it meets all the requirements of sections 1, 2, and 3 of this appendix and the Cover Purchase Description. These inspections shall be completed as part of the system checkout test and again as a part of the quality conformance test.
4.2. TESTS
The following tests shall be performed on the system as part of the system checkout test and again as a part of the quality conformance test.
No. Paragraph Description
1. 3.2.1.5.1. A minimum of five cabinet drawers picked at random shall be loaded with 400 pounds. While the drawer is closed, the height to the top of the drawer from the floor shall be measured and recorded. The loaded drawer shall be opened and left for a minimum of four continuous hours. The height of the top of the drawer front shall be recorded while the drawer is fully open. If an open drawer sags more than 0.62-inch when compared to its closed position, the system shall fail the test.
2. 3.2.1.5.3. A minimum of five cabinet drawers picked at random shall be loaded with 400 pounds. This test may be conducted in conjunction with test number one. The amount of force to pull and push the loaded drawer shall be measured with a digital force gauge. If the drawer requires more than 25 pounds to start outward the system shall fail the test. If the drawer requires more than 45 pounds to start inward or more than 40 pounds to continue moving inward, the system shall fail the test.
3. 3.2.1.5.9. Ensure that all drawer interior compartments extend 100 percent out of the housing exposing all contents to reach and visibility. If the drawers do not allow for 100 percent extension, the system shall fail the test.
4.3. CERTIFICATIONS
Shaw AFB, SC - App E - Page 8
The Contractor shall provide certification that the following requirements have been met in accordance with the Contract Data Requirements List.
No. Paragraph Certifications
1. 3.2.1.2. Cabinet housings have a minimum static load capacity of 10,000 pounds.
2. 3.2.2.1.
3.2.2.2.
Stairways and handrails comply with IBC and
OSHA 1910.
Shaw AFB, SC - App E - Modular Cabinet Mini-Mezzanine TPQ - Page
TECHNICAL PROPOSAL QUESTIONNAIRE
FOR
MODULAR CABINET MINI-MEZZANINE
Solicitation Number: FA8640- -R- Project Title: Storage Aid System Base: Shaw AFB, South Carolina CSN: TSH804 Appendix E, Modular Cabinet Mini-Mezzanine, 15 March 2019
This questionnaire shall be completed by the Offeror. All entries to this questionnaire shall be typed. The questionnaire will be used to determine the Offeror's understanding of the requirements and acceptability of the proposed equipment.
Please attach product literature/cut sheets for all equipment detailed in this questionnaire and attach any exceptions to the Purchase Description Appendix as detailed below.
Modular Cabinet Manufacturer: _____________________________ Modular Cabinet Model Number: _____________________________
No. Paragraph Characteristic
1. 3.2.1.1.
Quantity of modular cabinets provided: ________
Cabinet configuration dimensions:
Type “MC1” Width: _________ inches Depth: _________ inches Height: _________ inches
Type “MC2” Width: _________ inches Depth: _________ inches Height: _________ inches
Type “MC3” Width: _________ inches Depth: _________ inches Height: _________ inches
2.
3.2.1.2. Cabinet housing vertical static load capacity:
________ pounds
Solicitation Number: FA8604- -R-
3. 3.2.1.3. Is a pallet base provided?
YES NO
4. 3.2.1.3. Height of pallet base: _______ inches
5. 3.2.1.4. Are base enclosure plates provided to cover the front and rear of the pallet base?
6. 3.2.1.5.1. Maximum drawer load capacity: _______ pounds
7. 3.2.1.5.2. Inside drawer dimensions:
Width: _________ inches Depth: _________ inches
8. 3.2.1.5.2. Is the height of the sides and back wall of the drawer greater than 48 percent of the drawer front height? YES NO
9. 3.2.1.5.3. Force to move a fully-loaded drawer outward:
______ pounds Force to move a fully-loader drawer inward:
______ pounds
10. 3.2.1.5.4.
3.2.1.5.5.
3.2.1.5.6.
Are drawer divider strips, metal partitions, and crosswise dividers provided as specified?
11. 3.2.1.5.7. Does each drawer front have an aluminum drawer pull label holding system?
12. 3.2.1.5.8. Is each drawer equipped with drawer stops to prevent over-travel of the drawer?
13. 3.2.1.5.9. Do drawer interior compartments extend 100 percent out of the housing to expose all contents?
14. 3.2.1.5.9. Do the drawer carriages operate on precision ball and or roller bearings?
15. 3.2.1.6. Provide the drawer configuration for modular cabinets:
Cabinet Configuration Type
# of Drawers
Usable Height
Number of compartments
16. 3.2.2. Will the cabinet configurations “MC1”, “MC2”, and “MC3” be arranged in a mini-mezzanine configuration as specified?
17. 3.2.2.1. Number of stairways provided: ______
18. 3.2.2.2. Will handrails be provided as specified?
19. 3.2.2.3. Will rubber mats be provided as specified?
20. 3.2.2.4. Will the mini-mezzanine system be a freestanding structure that is not connected to any building structure?
EXCEPTIONS
Attach any exceptions taken to the Purchase Description.
Outline those concerns in detail. Your exceptions will be reviewed to determine acceptability.
Are exceptions taken? YES NO
Number of pages attached: ____________________________________
| SCOPE |
| APPLICABLE DOCUMENTS |
| REQUIREMENTS |
| System dESCRIPTION |
| Characteristics |
| Modular cabinetS |
| Modular cabinet |
| Cabinet housing load capacity |
| Pallet base |
| Base enclosure |
| Drawers |
| Drawer load capacity |
| Drawer dimensions |
| Drawer Push-pull forces |
| Drawer divider strips |
| Partitions |
| Crosswise dividers |
| Drawer Pull label holding system |
| Drawer stops |
| Carriages and brackets |
| Drawer CONFIGURATION |
| CABINET LOCK (Rev 1) |
| Mini-MEZZANINE CONFIGURATION |
| Stairway |
| HANDRAIL |
| RUBBER MAT |
| ASSEMBLY |
| Alignment |
| Storage unit vertical alignment |
| QUALITY CONFORMANCE |
| Inspections |
| Tests |