AF_Responses_to_Questions_from_Industry_(draft_RFP_FA8224-15-R-0027).pdf

PDF 42 KB Posted

Attached to
Point of Use (POU) - Services
Solicitation number
FA8224-15-R-0027
Issued by

About this file

AF response to Questions from Industry

View the file

Other files

File Type Posted
Attachment_4_Total_Evaluated_Price_29_May_15.xlsx XLSX spreadsheet
4___29_May_15_AF_Responses_to_Questions_from_Industry_(RFP_FA8224-15-R-0027).pdf PDF
Summary_of_Changes_to_Market_Basket_List_Updated_29_May_2015.xlsx XLSX spreadsheet
Exhibit_C_Price_List_29_May_15.xlsx XLSX spreadsheet
FA8224_15_R_0027_0006_Amendment_0006.pdf PDF
Attachment_4_Total_Evaluated_Price_29_May_15.xlsx XLSX spreadsheet
3___28_May_15_AF_Responses_to_Questions_from_Industry_(RFP_FA8224-15-R-0027).pdf PDF
FA8224_15_R_0027_0005_Amendment_0005.pdf PDF
Exhibit_C_Price_List_20_May_15.xlsx XLSX spreadsheet
Summary_of_Changes_to_Market_Basket_List_Updated_20_May_15.xlsx XLSX spreadsheet
POU_Section_L_Final_20_May_15.pdf PDF
Attachment_4_Total_Evaluated_Price_20_May_15.xlsx XLSX spreadsheet
FA8224_15_R_0027_0004_Amendment_0004.pdf PDF
2___19_May_15_AF_Responses_to_Questions_from_Industry_(RFP_FA8224-15-R-0027).pdf PDF
Attachment_5_Historical_Consumable_Supplies_Expendable_Tools_dtd_12_May_2015.xlsx XLSX spreadsheet
POU_Section_L_Final_12_May_15.pdf PDF
Attachment_4_Total_Evaluated_Price_12_May_15.xlsx XLSX spreadsheet
AbilityOne_Procurement_List_update.xlsx XLSX spreadsheet
Exhibit_C_Price_List.xls.xlsx XLSX spreadsheet
FA8224_15_R_0027_0003_Amendment_0003.pdf PDF
1___07_May_15_AF_Responses_to_Questions_from_Industry_(RFP_FA8224-15-R-0027).pdf PDF
FA8224_15_R_0027_0002_Amendment_2.pdf PDF
Attachment_4_Total_Evaluated_Price_07_May_15.xlsx XLSX spreadsheet
POU_Section_L_Final_07_May_15.pdf PDF
ppi_tool.accdb —
POU_PWS_07_May_2015.pdf PDF
POU_Section_M_Final_v1_07_May_15.pdf PDF
POU_PWS_05_May_2015.pdf PDF
POU_Section_L_Final_05_May_15.pdf PDF
FA8224_15_R__0001_amendment.pdf PDF
Attachment_5_Historical_Consumable_Supplies_Expendable_Tools.xlsx XLSX spreadsheet
POU_Section_M_Final_05_May_15.pdf PDF
Exhibit_C_Price_List.xls.xlsx XLSX spreadsheet
Attachment_3_POU_52_212_2_Addendum.pdf PDF
Attachment_2_POU_52_212_1_Addendum.pdf PDF
POU_RFP.pdf PDF
Attachment_1_POU_PWS_09_Apr_2015.pdf PDF
Attachment_5_Historical_Supplies_Tools_Market_Basket.pdf PDF
Attachment_6_Wage_Determination_Utah.pdf PDF
Attachment_7_Wage_Determination_Arizona.pdf PDF
Exhibit_A_B_CDRLS.pdf PDF
Attachment_4_Total_Evaluated_Price_22_Apr_15.xlsx XLSX spreadsheet
17_Apr_15_AF_Responses_to_Questions_from_Industry_(draft_RFP_FA8224-15-R-0027).pdf PDF
Attachment_1 _Draft_Market_Basket_31_Mar_15.xls XLS spreadsheet
31_Mar_15_AF_Responses_to_Questions_from_Industry_(draft_RFP_FA8224-15-R-0027).pdf PDF
Draft_POU_Section_L_26_Mar_15.pdf PDF
Draft_POU_PWS_23_Mar_2015.pdf PDF
Draft_POU_Section_M_26_Mar_15.pdf PDF
Draft_TEP_draft_31_Mar.xlsx XLSX spreadsheet
25_Mar_15_AF_Responses_to_Questions_from_Industry_(draft_RFP_FA8224-15-R-0027).pdf PDF
Show 40 more

Latest 50 of 60 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Air Force Response to Comments/Questions from Industry

POINT OF USE (POU)

23 February 2015

Below is a list of questions/comments the Air Force has received from industry regarding the draft PWS and Sections L & M for draft solicitation FA8224-15-R-0027 posting on FedBizOpps and the Air Force responses to questions/comments. Air Force responses are based on the best information available at this time and are subject to change in the event the requirement is amended. Only the RFP and RFP Amendments, if issued, should be relied upon while preparing proposals.

1. Reference: Section L, Page L5 / Paragraph 3.18. The offeror shall fill out the proposal section of the Cross Reference Matrix in the 3.18.format as provided in Appendix II of FAR 52.212-1 Addendum.

Industry Question: It appears that the solicitation will contain a cross reference table that will be partially populated by the Government and the contractor will be required to populate only the “Proposal” column. Please confirm this assumption. If so, will this table be provided in an editable format?

Air Force Response: Yes, there will be a Cross Reference Matrix in Section L and the contractor will only be required to fill out the “Proposal” column. The table will not be editable.

2. Reference: Section L, Pages L6 & L7 / Paragraph 3.22. The offeror shall submit Volumes I - IV in electronic format, using read only CDs (i.e. CD-R). The electronic copies of the proposal shall be submitted in a format readable by Microsoft (MS) Word 2010, MS Excel 2010, and MS-Power Point 2010, as applicable.

Industry Question: Understanding that the all CDs will be provided in a Read Only format.

Please confirm that the individual files saved on the CDs will also need to be provided in a Read Only format, exclusive of a PDF version.

Air Force Response: Yes, Individual files should be in read only format.

3. Reference: Section L, Pages L8 & L9 /Paragraphs 5.3 & 5.4.

Industry Question: There appears to be a disconnect in format/structure between the general outline (paragraph 5.3)

1. Table of Contents

2. List of Table and Drawings

3. Glossary

4. Support Plan

(a) Ability to maintain minimum individual item stock levels

(b) Ability to stock POU machines within one business day

(c) Consumable Items and Tool Management Plan to include inventory management

5. Adequate and readily available storage/staging area

And the technical breakdown (paragraph 5.4)

5.4.1. Sub-factor One: Technical Approach-Management of Expendable Tools and Consumable Supplies

5.4.2. Sub-factor Two: Resource Management Approach

5.4.3. Sub-factor Three: Experience

Please clarify.

Air Force Response: Sections L & M have been revised.

4. Reference: Section L, Page L12 / Paragraph 7.6.1. Mission Essential Plan - provide a written plan for continuing performance of the essential Contractor services, outlined in paragraph 20 of the PWS, during a crisis or state of national emergency IAW DFARS Subpart 237.76 and DFARS Clause 252.237-7024(b)(2).

Industry Question: The reference to the Mission Essential Plan in draft PWS occurs in paragraph 24, as opposed to paragraph 20.

Air Force Response: Mission Essential Plan requirement has been removed from the PWS and Sections L & M.

5. Reference: Section L, Page L18 / Paragraph 14 (Figure 9)

Industry Question: The first sub bullet implies that the offerer will be required to “Select from the dropdown the appropriate contractor.” It is assumed that the company name will be “pre-populated” in this dropdown menu utilizing the information previously entered in Step 9 (Page L17)? Please confirm.

Air Force Response: It is our understanding, that this assumption is accurate.

6. Reference: PWS, Page 9 / Paragraph 4.1 CDRL 09 –Safety Plan

Industry Question: The PWS indicates that the CDRL is due during the Initial Ramp-up Phase.

The “Section L” document (reference Paragraph 7.6 & 7.6.2) indicates that this plan is due with proposal submission. Please clarify.

Air Force Response: Removed from Section L, will be due IAW CDRL.

7. Reference: PWS, Page 9 / Paragraph 4.2.1. The report shall include: Date, time, machine and bin number, employee name, item number, description, quantity, unit of issue, unit cost and extension price.

Industry Question: Should “unit cost” be replaced with “unit price”?

Air Force Response: PWS has been updated to reflect “unit price”.

8. Reference: PWS, Page 12 / Paragraph 9.1.1. Upon TO award, the contractor shall implement their Transition Plan. Transition from the incumbent shall be completed no later than 30 days following TO award, as identified in the contractor’s transition plan. In the event there is new Government workload (where there is no incumbent); the contractor shall stand up operations and manning no later than 30 days following TO award. The contractor shall not exceed 60 days following TO award to provide a fully trained staff.

Industry Question: Potential conflicting requirement. If the transition is to be complete in 30 days, doesn’t the staff need to be fully trained in 30 days as well?

Air Force Response: PWS has been updated from 60 days to 30 days.

9. Reference: PWS, Page 12 / Paragraph 9.1.6. Conduct contractor Industrial Hygiene surveys.

Industry Question: How do we acquire information on the Hygiene surveys?

Air Force Response: Bioenvironmental Engineering Flights have produced industrial hygiene assessments of these areas which are for information only and will be provided at the task order level.

10. Reference: PWS, Page 13 / Paragraph 11.2. The contractor shall establish and provide a complete contractor’s QSP to ensure the requirements of this contract are provided as specified.

Industry Question: Is the QSP the same document as the Quality Control Plan (QCP) – CDRL 11?

Air Force Response: PWS has been updated to reflect “QCP”.

11. Reference: PWS, Page 18 / Paragraph 23.1.2 Training Matrix.

Industry Question: What is the significance of the “X” in the “Initial Requirement” and “Annual Requirement” columns of the table?

Air Force Response: There is no significance. The “X” has been removed.