This solicitation is for an Arm/Disarm Switch Replacement (ADSR) program. The purpose is to provide a replacement switch for the Minute Man III weapon system as a fit and function replacement that maintains backwards compatibility. It will be conducted as a Multiple Award IDIQ contract with an ordering period from December 2019 to December 2029.
The Government intends to award an initial task order to all participants for development and qualification activities, including completion of Preliminary Design Review activities within 10 weeks of award, production of 25 test units within 12 months of award, and completion of qualification testing within 18 months of award. Future production delivery orders will be competed among only qualified offerors. The program aims to procure enough switches to meet Government supply needs. Intended participants are Ensign-Bickford Aerospace & Defense Company, Moog Space and Defense Group, and Bionetics. Interested parties can request restricted technical data documents by providing a completed DD Form 2345 to the points of contact.
Now includes provision/clause FAR 52.204-24 & FAR 52.204-25
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ADSR_SOO.pdf | ||
| ADSR_GRID.pdf | ||
| ADSR_Contractor_Down_Select_Criteria.pdf | ||
| ADSR_CDRL_Package.pdf | ||
| Technology_Readiness_Levels_Defined.pdf | ||
| ADSR_WBS.xlsx | XLSX spreadsheet | |
| Intro_Letter.docx | DOCX document | |
| FA821419R7003.pdf | ||
| Synopses.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STANDARD FORM 1447 (2/2012)
Prescribed by GSA FAR (48 CFR) 53.215-1(d)
4. SOLICITATION NUMBER
FA8214-19-R-7003
6.SOLICITATION ISSUE DATE
8. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR
SMALL BUSINESS WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOSB PROGRAM
HUBZONE SMALL
BUSINESS EDWOSB
SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS NAICS CODE: 336419
8(A) SIZE STANDARD: 1,000
DATE SIGNED
28. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
26. AWARD OF CONTRACT: YOUR OFFER ON SOLICITATION NUMBER
SHOWN IN BLOCK 4 INCLUDING ANY ADDITIONS OR CHANGES WHICH
ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
ROUTINE
Subject to the terms and conditions stated herein, the Contractor agrees to hold its offered prices firm for 120 days.
SEE LINE ITEM SCHEDULE
22.
AMOUNT
16. AUTHORITY FOR USING OTHER THAN 10 USC 2304 41 USC 253
FULL AND OPEN COMPETITION (c) (1 ) (c) ( )
DATE SIGNED
27. SIGNATURE OF OFFEROR/CONTRACTOR
20.
UNIT
21.
UNIT PRICE
19.
QUANTITY
13. CONTRACTOR OFFEROR CODE FACILITY CODE
11. IF OFFER IS ACCEPTED BY THE GOVERNMENT WITHIN * ___ CALENDAR DAYS (60 CALENDAR
DAYS UNLESS OFFEROR INSERTS A DIFFERENT PERIOD) FROM THE DATE SET FORTH IN BLK 9
ABOVE, THE CONTRACTOR AGREES TO HOLD ITS OFFERED PRICES FIRM FOR THE ITEMS
SOLICITED HEREIN AND TO ACCEPT ANY RESULTING CONTRACT SUBJECT TO THE TERMS AND
CONDITIONS STATED HEREIN. *120
RATING
DO: A2
3. AWARD/EFFECTIVE DATE
FA8214
2. CONTRACT NO.
CHECK IF REMITTANCE IS DIFFERENT
AND PUT SUCH ADDRESS IN OFFER
17.
ITEM NO.
12. ADMINISTERED BY CODE
Total
SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK: 14 EFT:T
SCD:C
NAME AND TITLE OF SIGNER (TYPE OR PRINT) NAME OF CONTRACTING OFFICER
24. AWARD AMOUNT (FOR GOVT USE ONLY)
23. ACCOUNTING AND APPROPRIATION DATA
SEE SCHEDULE
5. SOLICITATION TYPE
SEALED BIDS NEGOTIATED
(IFB) (RFP)
15. PROMPT PAY DISCOUNT
25. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SETFORTH
OR OTHERWISE IDENTIFIED ABOVE AND ON ANY CONTINUATION SHEETS SUBJECT
THE TERMS AND CONDITIONS SPECIFIED HEREIN.
10. ITEMS TO BE PURCHASED (BRIEF DESCRIPTION)
SUPPLIES SERVICES Other Guided Missile and Space Vehicle Parts and Auxiliary Equipment Manu
9.
Solicitation: Offers will be received at the Issuing office until * on * . Late offers are subject to late proposal provisions incorporated herein.
All offers are subject to such provisions, representations certifications and specifications as are attached or incorporated by reference.*
3-SEP-2019 11:59PM
X
18.
SCHEDULE OF SUPPLIES/SERVICES
14. PAYMENT WILL BE MADE BY CODE
(SEE ESP CLAUSE 252.232-7003.)
X
7. ISSUED BY CODE
DEPARTMENT OF THE AIR FORCE, DIRECTORATE OF CONTRACTING
AFNWC PZBB
6008 WARDLEIGH ROAD BLDG 1580
HILL AIR FORCE BASE UT 84056-5837
BUYER: Blake P. Davis/AFNWC blake.davis@us.af.mil Phone: (801) 775- 5550 Fax: (000) 000-0000
X
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 350)SOLICITATION/CONTRACT
BIDDER/OFFEROR TO COMPLETE BLOCKS 11, 13, 15, 21, 22, & 27.
U
SF 1447 (rev 2/2012) BACK
NO RESPONSE FOR THE REASONS CHECKED
TYPE OR PRINT NAME AND TITLE OF SIGNER
SIGNATURENAME AND ADDRESS OF FIRM (Include Zip Code)
WE DO NOT DESIRE TO BE RETAINED ON THE MAILING LIST FOR FUTURE PROCUREMENT OF THE TYPE OF
ITEMS INVOLVED
WE DO
OTHER (Specify)
CANNOT COMPLY WITH SPECIFICATIONS
CANNOT COMPLY WITH SPECIFICATIONS CANNOT MEET DELIVERY REQUIREMENT
FOLD
FOLD
SOLICITATION NO. FA821419R7003
DUE: 3 SEP 2019 11:59 PM
FROM: AFFIX
STAMP
HERE
TO:
ATTN: Blake P Davis/AFNWC
DEPARTMENT OF THE AIR FORCE, DIRECTORATE OF CONTRACTING
AFNWC PZBB
6008 WARDLEIGH ROAD BLDG 1580
HILL AIR FORCE BASE UT 84056-5837
FA8214-19-R-7003
PART I - THE SCHEDULE
SECTION B
SUPPLIES OR SERVICES AND PRICES/COSTS
Ordering Period One is from XX XXX 2019 to XX XXX 2024
Ordering Period Two is from XX XXX 2024 to XX XXX 2029
PDR
Item No.
Cost Plus Fixed Fee Quantity U/I Estimated Cost Fixed Fee Est Total Cost
1 LO
R425
PDR
Contractor shall complete PDR activities IAW attached SOO/Off Ramp Criteria.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
AS9100 9100
Place of Perf Quantity (U/I) *ARO Each
Individual Order _ Req No / Pri
Required Period of Performance
1 LO *10 Weeks
Proposed Period of Performance
1 LO
Qualification Units (Option)
Item No.
Cost Plus Fixed Fee Quantity U/I Estimated Cost Fixed Fee Est Total Cost
25 EA
Qualification Units (Option)
R425 Production of 25 Qual units Contractor shall produce 25 units for qualification testing IAW attached SOO/Off Ramp Criteria.***CONTRACTOR
SHALL NOT PROCEED TO COMENCE WORK UNDER THIS CLIN UNTIL THEY HAVE SATISFACTORILY
COMPLETED ALL CRITERIA REQUIRED UNDER CLIN 0001 AND RECEIVED WRITTEN AUTHORIZATION TO PROCEED FROM THE CONTRACTING OFFICER. THIS WRITTEN AUTHORIZATION IS SEPERATE FROM THE
NOTIFICATION AND CONTRACT MODIFICATION EXERCISING THIS OPTION.***
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Place of Perf Quantity (U/I) *ARO Notice from
Contracting Officer _ Req No / Pri
Required Period of Performance
A PLANT 25 EA *42 Weeks
Proposed Period of Performance
A PLANT 25 EA
Qualification (Option)
Item No.
Cost Plus Fixed Fee Quantity U/I Estimated Cost Fixed Fee Est Total Cost
1 LO
R425 Qualification Contractor shall qualify thieir design IAW attached SOO/Off Ramp Criteria. ***CONTRACTOR SHALL NOT PROCEED TO COMENCE WORK UNDER THIS CLIN UNTIL THEY HAVE SATISFACTORILY COMPLETED ALL CRITERIA REQUIRED UNDER CLIN 0002 AND RECEIVED WRITTEN AUTHORIZATION TO PROCEED FROM THE CONTRACTING OFFICER. THIS WRITTEN AUTHORIZATION IS SEPERATE FROM THE NOTIFICATION
AND CONTRACT MODIFICATION EXERCISING THIS OPTION.***
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Qualification (Option)
Place of Perf Quantity (U/I) *ARO Notice from
Contracting Officer _ Req No / Pri
Required Period of Performance
1 LO *6 Months
Proposed Period of Performance
1 LO
DATA
Item No.
Not Separately Priced Quantity U/I Unit Price
LO NSP
DATA
DATA IAW DD 1423-1 ATTACHED HERE TO
Exhibit: A Type / Ship To Quantity (U/I) _ Req No / Pri
Required Delivery
LO TBD
Proposed Delivery
LO
SHIP TO / PLACE OF PERFORMANCE
TYPE/CODE: A PLANT
SHIP IN PLACE 00000-0000
MARK FOR: (See Individual Line Item) REQUISITION NUMBER: (See Individual Line Item) REQUISITION PRIORITY: (See Individual Line Item)
AWARD NUMBER:
PART I - THE SCHEDULE
SECTION E
INSPECTION AND ACCEPTANCE
52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE (AUG 1996)
(IAW FAR 46.302)
(Applicable for supplies, services furnishing of supplies, fixed-price and exceeds the simplified acquisition threshold)
52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(IAW FAR 46.311, DFARS 246.202-4(1))
(a) The Contractor shall comply with the higher-level quality standard(s) listed below. [If more than one standard is listed, the offeror shall indicate its selection by checking the appropriate block.]*
Title Number Date Tailoring *See Individual Line Item Schedule
(Applicable only if specified in the individual order/call issued hereunder)
52.246-16 RESPONSIBILITY FOR SUPPLIES (APR 1984)
(IAW FAR 46.316)
(Applicable to the furnishing of supplies, services involving the furnishing of supplies, or research and development, when a fixed-price contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold)
INSPECTION AND ACCEPTANCE (SEP 1999)
(IAW FAR 46.401(b), FAR 46.503) (Applicable to all orders issued hereunder)
Government Contract Quality Assurance Inspection and Acceptance will be at (Final):
[CONTRACTOR FILL-IN]
Item No(s): See schedule for items with the following code(s) listed below :
Inspection Code and Address:
Government Contract Quality Assurance Inspection and Acceptance will be at destination(s) specified herein (Final).
Item No(s): 0001, 0003
PART I - THE SCHEDULE
SECTION F
DELIVERIES OR PERFORMANCE
52.211-8 TIME OF DELIVERY (JUN 1997)
(IAW FAR 11.404(a)(2)) DELIVERY FOR EACH ITEM IS ANNOTATED IN THE SCHEDULE (PART I SECTION B) UNDER EACH LINE
ITEM.
(Applicable when the Government desires delivery by a certain time but requires delivery by a specified later time, and the delivery schedule is to be based on the date of the contract)
52.242-15 STOP-WORK ORDER (AUG 1989)
(IAW FAR 42.1305(b)(1)) (Applicable for supplies, services, or research and development)
52.242-15 STOP-WORK ORDER -- ALTERNATE I (APR 1984)
(IAW FAR 42.1305(b)(2)) (Applicable for Cost-reimbursement line items)
PART I - THE SCHEDULE
SECTION G
CONTRACT ADMINISTRATION DATA
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(IAW DFARS 232.7004(b), PGI 232.7004(b)(1), DFARS 212.301(f)(liii))
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
(Contracting Officer: Insert applicable document type(s).
Note: If a “Combo” document type is identified but not supportable by the Contractor’s business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
(Contracting Officer: Insert inspection and acceptance locations or “Not applicable.”)
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC Issue By DoDAAC Admin DoDAAC Inspect By DoDAAC Ship To Code Ship From Code Mark For Code Service Approver (DoDAAC) Service Acceptor (DoDAAC) Accept at Other DoDAAC LPO DoDAAC DCAA Auditor DoDAAC Other DoDAAC(s) (*Contracting Officer: Insert applicable DoDAAC information or “See schedule” if multiple ship to/acceptance locations apply, or “Not applicable.”)
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the e-mail address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
(Contracting Officer: Insert applicable email addresses or “Not applicable.”)
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
(Applicable when 252.232-7003 is used and neither 232.7003(b) nor (c) apply)
PART II - CONTRACT CLAUSES
SECTION I
CONTRACT CLAUSES
5352.201-9101 OMBUDSMAN (JUN 2016)
(IAW AFFARS 5301.9103)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, the interested party may contact the ombudsman, Anthony Kaiser at 312-263-7666, email anthony.kaiser@us.af.mil ########### . Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU/SMC ombudsman level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-2395, facsimile number (571) 256-2431.
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer.
(The above Clause/Provision has been modified.)
(Applicable to all solicitations and contracts)
52.202-1 DEFINITIONS (NOV 2013)
(IAW FAR 2.201)
(Applicable when the simplified acquisition threshold is exceeded)
52.203-3 GRATUITIES (APR 1984)
(IAW FAR 3.202)
(Applicable when simplified acquisition threshold is exceeded, except for personal services and those between military departments or defense agencies and foreign governments that do not obligate any funds appropriated to the Department of Defense)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
(IAW FAR 3.404)
(Applicable when simplified acquisition threshold is exceeded other than those for commercial items (see Parts 2 and 12))
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)
(IAW FAR 3.503-2)
52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)
(IAW FAR 3.502-3)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR
IMPROPER ACTIVITY (MAY 2014)
(IAW FAR 3.104-9(a))
(Applicable when noncommercial and the simplified acquisition threshold is exceeded)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
(IAW FAR 3.104-9(b))
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS
(OCT 2010)
(IAW FAR 3.808(b))
(Applicable over $150,000)
52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (OCT 2015)
(IAW FAR 3.1004(a)) (Applicable to solicitations and contracts exceeding $5.5 million and the period of performance is greater than 120 days, unless for the acquisition of a commercial item under Part 12 or performed entirely outside the U.S.)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY
AGREEMENTS OR STATEMENTS (JAN 2017)
(IAW FAR 3.909-3 (b))
(Applicable in all solicitations and resultant contracts other than personal services contracts with individuals)
252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS
(SEP 2011)
(IAW DFARS 203.171-4(a), DFARS 212.301(f)(ii))
252.203-7001 PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER
DEFENSE-CONTRACT-RELATED FELONIES (DEC 2008)
(IAW DFARS 203.570-3)
(Applicable when exceeding the simplified acquisition threshold (except for commercial items))
252.203-7002 REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS
(SEP 2013)
(IAW DFARS 203.970)
252.203-7003 AGENCY OFFICE OF THE INSPECTOR GENERAL (DEC 2012)
(IAW DFARS 203.1004(a), DFARS 212.301(f)(iii)) (Applicable to solicitations and contracts when FAR 52.203-13 is included)
252.203-7004 DISPLAY OF HOTLINE POSTERS (MAY 2019)
(IAW DFARS 203.1004(b)(2)(ii)) (Applicable to acquisitions over $5.5 million, except for commercial items)
52.204-2 SECURITY REQUIREMENTS (AUG 1996)
(IAW FAR 4.404(a)) (Applicable when access to classified information may be required)
52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON RECYCLED PAPER (MAY 2011)
(IAW FAR 4.303)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
(IAW FAR 4.1105(b)) (Applicable to solicitations that contain the provision at 52.204-7, and resulting contracts)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2016)
(IAW FAR 4.1804(c), FAR 12.301(d)) (Applicable when there is a requirement to be registered in SAM or to have a DUNS Number)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS
(DEC 2014)
(IAW FAR 4.1202(b))
52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS
(JUN 2016)
(IAW FAR 4.1903)
(Applicable to all solicitations and contracts, except COTs, when a contractor’s system may contain Federal contract information)
52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES
DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED
ENTITIES (JUL 2018)
(IAW FAR 4.2004)
(Applicable on all contracts and solicitations.)
52.204-25 PROHIBITION ON CONTRACTING FOR CERTIAN TELECOMMUNICATIONS AND
VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2019)
(IAW 4.2105(b))
252.204-7003 CONTROL OF GOVERNMENT PERSONNEL WORK PRODUCT (APR 1992)
(IAW DFARS 204.404-70(b)) (Applicable to all orders issued hereunder)
252.204-7012 SAFEGUARDING COVERED DEFENSE INFORMATION AND CYBER INCIDENT
REPORTING (OCT 2016)
(IAW DFARS 204.7304(c))
(Applicable to all solicitations and contracts, including commercial except when solely for commercial-off-the-shelf items)
252.204-7015 NOTICE OF AUTHORIZED DISCLOSURE OF INFORMATION FOR LITIGATION
SUPPORT (MAY 2016)
(IAW DFARS 204.7403(c), DFARS 212.301(f)(ix))
(Applicable to solicitations and contracts that involve litigation support services when 252.204-7014 is not included)
252.205-7000 PROVISION OF INFORMATION TO COOPERATIVE AGREEMENT HOLDERS
(DEC 1991)
(IAW DFARS 205.470, DFARS 212.301(f)(x))
(Applicable over $1,000,000)
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT
(OCT 2015)
(IAW FAR 9.409)
(Applicable when exceeding $35,000)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (OCT 2018)
(IAW FAR 9.104-7(c))
(Applicable to solicitations and contracts over $550,000 and contracts where the offeror has checked “has” in paragraph (b) clause 52.209-7)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS
(NOV 2015)
(IAW FAR 9.108-5(b))
(Applicable to all solicitations and contracts for the acquisition of products and services (including construction) unless waived IAW FAR 9.108-4)
252.209-7004 SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED BY THE
GOVERNMENT OF A COUNTRY THAT IS A STATE SPONSOR OF TERRORISM
(MAY 2019)
(IAW DFARS 209.409)
(Applicable to solicitations and contracts with a value of $150,000 or more)
52.210-1 MARKET RESEARCH (APR 2011)
(IAW FAR 10.003)
(Applicable to solicitations and contracts over $5.5 million for the procurement of items other than commercial items)
52.211-5 MATERIAL REQUIREMENTS (AUG 2000)
(IAW FAR 11.304)
(Applicable to supplies that are not commercial items)
52.211-15 DEFENSE PRIORITY AND ALLOCATION REQUIREMENTS (APR 2008)
(IAW FAR 11.604(b)) This is a rated order certified for national defense , emergency preparedness, and energy program use, and the Contractor shall follow all the requirements of the Defense Priorities and Allocations System regulation (15 CFR 700).
(Applicable to all rated orders)
252.211-7003 ITEM UNIQUE IDENTIFICATION AND VALUATION (MAR 2016)
(IAW DFARS 211.274-6(a)(1), DFARS 212.301(f)(xii))
(a) Definitions. As used in this clause—
“DoD recognized unique identification equivalent” means a unique identification method that is in commercial use and has been recognized by DoD. All DoD recognized unique identification equivalents are listed at http://www.acq.osd.mil/dpap/pdi/uid/iuid/equivalents.html .
“Unique item identifier type” means a designator to indicate which method of uniquely identifying a part has been used. The current list of accepted unique item identifier types is maintained at http://www.acq.osd.mil/dpap/pdi/uid/uii_types.html .
(c) Unique item identifier.
(1) The Contractor shall provide a unique item identifier for the following:
(i) Delivered items for which the Government’s unit acquisition cost is $5,000 or more, except for the following line items:
Contract Line, Subline, or Exhibit Line Item Number
Item Description
See Schedule as Applicable
(ii) Items for which the Government’s unit acquisition cost is less than $5,000 that are identified in the Schedule or the following table:
Contract Line, Subline, or Exhibit Line Item Number
Item Description
*Items less than $5000, which require UID, will be specifically identified in the schedule.
See Schedule as Applicable
(iii) Subassemblies, components, and parts embedded within delivered items, items with warranty requirements, DoD serially managed reparables and DoD serially managed nonreparables as specified in Attachment Number _____( or See Schedule as Applicable).
(iv) Any item of special tooling or special test equipment as defined in FAR 2.101 that have been designated for preservation and storage for a Major Defense Acquisition Program as specified in Attachment Number _____( or See Schedule as Applicable).
(v) Any item not included in paragraphs (c)(1)(i), (ii), (iii), or (iv) of this clause for which the contractor creates and marks a unique item identifier for traceability.
(f) The Contractor shall submit the information required by paragraphs (d) and (e) of this clause as follows:
(1) End items shall be reported using the receiving report capability in Wide Area WorkFlow (WAWF) in accordance with the clause at 252.232-7003. If WAWF is not required by this contract, and the contractor is not using WAWF, follow the procedures at http://dodprocurementtoolbox.com/site/uidregistry/ .
(2) Embedded items shall be reported by one of the following methods—
(i) Use of the embedded items capability in WAWF;
(ii) Direct data submission to the IUID Registry following the procedures and formats at http://dodprocurementtoolbox.com/site/uidregistry/; or
(iii) Via WAWF as a deliverable attachment for exhibit line item number ______, Unique Item Identifier Report for Embedded Items, Contract Data Requirements List, DD Form 1423.
252.211-7007 REPORTING OF GOVERNMENT-FURNISHED PROPERTY (AUG 2012)
(IAW DFARS 211.274-6(b), DFARS 212.301(f)(iv)) (Applicable when FAR 52.245-1, Government Property, is used)
52.215-2 AUDIT AND RECORDS--NEGOTIATION (OCT 2010)
(IAW FAR 15.209(b)(1)) (Applicable if negotiated and above the simplified acquisition threshold, except commercial items and utility services at public prices plus reasonable connection charge)
52.215-8 ORDER OF PRECEDENCE--UNIFORM CONTRACT FORMAT (OCT 1997)
(IAW FAR 15.209(h), AFFARS 53.15.209(h)) (Applicable when using uniform contract format that is not commercial or for construction)
52.215-10 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA
(AUG 2011)
(IAW FAR 15.408(b))
(Applicable if negotiated and exceeding $750,000, when certified cost or pricing data is required)
52.215-12 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA (DEVIATION 2018-O0015)
(MAY 2018) (MAY 2018)
(IAW DARS Tracking Number: 2018-O0015)
52.215-14 INTEGRITY OF UNIT PRICES (OCT 2010)
(IAW FAR 15.408(f)(1)) (Applicable when negotiated and exceeding the simplified acquisition threshold)
52.215-14 INTEGRITY OF UNIT PRICES -- ALTERNATE I (OCT 1997)
(IAW FAR 15.408(f)(2)) (Alternate I is applicable when negotiated and exceeding the simplified acquisition threshold and contracting was without full and open competition)
52.215-15 PENSION ADJUSTMENTS AND ASSET REVERSIONS (OCT 2010)
(IAW FAR 15.408(g)) (Applicable exceeding $750,000, when certified cost or pricing data is required, or for which any preaward or postaward cost determinations are subject to Part 31)
52.215-18 REVERSION OR ADJUSTMENT OF PLANS FOR POSTRETIREMENT BENEFITS
(PRB) OTHER THAN PENSIONS (JUL 2005)
(IAW FAR 15.408(j))
(Applicable exceeding $750,000 when cost or pricing data is required, or for which any preaward or postaward cost determinations are subject to Part 31)
52.215-19 NOTIFICATION OF OWNERSHIP CHANGES (OCT 1997)
(IAW FAR 15.408(k)) (Applicable exceeding $750,000 when certified cost or pricing data is required, or for which any preaward or postaward cost determinations are subject to Part 31)
52.215-23 LIMITATIONS ON PASS-THROUGH CHARGES (OCT 2009)
(IAW FAR 15.408(n)(2)) (Applicable to orders issued hereunder)
252.215-7002 COST ESTIMATING SYSTEM REQUIREMENTS (DEC 2012)
(IAW DFARS 215.408(1))
(Applicable to any order awarded on the basis of certified cost or pricing data)
252.215-7014 EXCEPTION FROM CERTIFIED COST OR PRICING DATA REQUIREMENTS FOR
FOREIGN MILITARY SALES INDIRECT OFFSETS (JUL 2018)
(IAW DFARS 215.408 (8))
52.216-7 ALLOWABLE COST AND PAYMENT (AUG 2018)
(IAW FAR 16.307(a))
(a) Invoicing.
(3) The designated payment office will make interim payments for contract financing on the _30th day
(Applicable when specifying cost-reimbursement pricing arrangement)
52.216-8 FIXED FEE (JUN 2011)
(IAW FAR 16.307(b)) (Applicable when specifying cost-plus-fixed-fee pricing arrangement)
52.216-19 ORDER LIMITATIONS (OCT 1995)
(IAW FAR 16.506(b))
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than , the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor--
(1) Any order for a single item in excess of ;
(2) Any order for a combination of items in excess of ; or
(3) A series of orders from the same ordering office within days that together call for quantities exceeding the limitation in subparagraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
52.216-22 INDEFINITE QUANTITY (OCT 1995)
(IAW FAR 16.506(e))
(d) Contractor shall not be required to make any deliveries under this contract after .
52.216-32 TASK-ORDER AND DELIVERY-ORDER OMBUDSMAN (SEP 2019)
(IAW 16.506(j)) As prescribed in 16.506(j), use the following clause: Task-Order and Delivery-Order Ombudsman (Sep 2019)
12. In accordance with 41 U.S.C. 4106(g), the Agency has designated the following task-order and delivery-order Ombudsman for this contract. The Ombudsman must review complaints from the Contractor concerning all task-order and delivery-order actions for this contract and ensure the Contractor is afforded a fair opportunity for consideration in the award of orders, consistent with the procedures in the contract.
Jeffrey L. Sorensen
505 846 1924 jeffrey.sorensen.5@us.af.mil
(b) Consulting an ombudsman does not alter or postpone the timeline for any other process (e.g., protests).
(c) Before consulting with the Ombudsman, the Contractor is encouraged to first address complaints with the Contracting Officer for resolution. When requested by the Contractor, the Ombudsman may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.
(End of clause)
52.216-32 TASK-ORDER AND DELIVERY-ORDER OMBUDSMAN - ALTERNATE I (SEP 2019)
(IAW 16.506(j)) Alternate I. As prescribed in 16.506(j), add the following paragraph (d) to the basic clause.
(d) Contracts used by multiple agencies.
(1) This is a contract that is used by multiple agencies. Complaints from Contractors concerning orders placed under contracts used by multiple agencies are primarily reviewed by the task-order and delivery-order Ombudsman for the ordering activity.
(2) The ordering activity has designated the following task-order and delivery-order Ombudsman for this order:
Jeffrey L. Sorensen
505 846 1924 jeffrey.sorensen.5@us.af.mil
(3) Before consulting with the task-order and delivery-order Ombudsman for the ordering activity, the Contractor is encouraged to first address complaints with the ordering activity’s Contracting Officer for resolution. When requested by the Contractor, the task-order and delivery-order Ombudsman for the ordering activity may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.
(End of clause)
252.216-7006 ORDERING (MAY 2011)
(IAW DFARS 216.506(a))
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the contract schedule. Such orders may be issued from .
(Applicable to solicitations and contracts when a definite-quantity contract, a requirements contract, or an indefinite-quantity contract is contemplated)
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM
(MAR 1989)
(IAW FAR 17.208(e))
The Contracting Officer may exercise the option by written notice to the Contractor within the PoP of current option
(Applicable when the option quantity is identified as a separately priced line item having the same nomenclature as a corresponding basic contract line item)
52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
(IAW FAR 17.208(g))
(a) The Government may extend the term of this contract by written notice to the Contractor within within the period of performance of the current active contract/option period ; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 1 days before the contract expires.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 11 years .
(Applicable when the inclusion of an option is appropriate and it is necessary to include any or all of the following: 1.
A requirement that the Government must give the contractor a preliminary written notice of its intent to extend the contract; 2. A statement that an extension of the contract includes an extension of the option; 3. A specified limitation on the total duration of the contract.)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2018)
(IAW FAR 19.708(a)) (Applicable when exceeding the simplified acquisition threshold, except for personal service contracts or when performance is entirely outside of the United States and its outlying areas)
52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN (DEVIATION 2018-O0018)
(AUG 2018)
(IAW DARS TRCKING # 2018-O0018)
(Applicable over $700,000)
52.219-16 LIQUIDATED DAMAGES--SUBCONTRACTING PLAN (JAN 1999)
(IAW FAR 19.708(b)(2)) (Applicable when FAR 52.219-9, Small Business Subcontracting Plan, or its Alternate I or Alternate II applies. IAW DFARS 219.708(b)(2), does not apply to DoD in contracts with contractors that have comprehensive subcontracting plans approved under the test program described in DFARS 219.702)
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)
(IAW FAR 19.309(c))
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code _____________ assigned to contract number ______________________________.
[Contractor to sign and date and insert authorized signer's name and title].
(Applicable in solicitations and contracts exceeding the micro-purchase threshold when the contract will be performed in the United States or its outlying areas)
252.219-7003 SMALL BUSINESS SUBCONTRACTING PLAN (DoD CONTRACTS) (MAY 2019)
(IAW DFARS 219.708(b)(1)(A), DFARS 219.708(b)(1)(A)(1)) (Applicable over $700,000)
252.219-7003 SMALL BUSINESS SUBCONTRACTING PLAN (DoD CONTRACTS)--ALTERNATE I
(MAY 2019)
(IAW DFARS 219.708(b)(1)(A)(2), DFARS 219.708(b)(1)(A)(1))
(Applicable over $700,000 and when FAR clause 52.219-9 and its Alternate III are used)
252.219-7004 SMALL BUSINESS SUBCONTRACTING PLAN (TEST PROGRAM) (MAY 2019)
(IAW DFARS 219.708(b)(1)(B)) (Applicable when the contract includes a Comprehensive Subcontracting Plan)
52.222-2 PAYMENT FOR OVERTIME PREMIUMS (JUL 1990)
(IAW FAR 22.103-5(b))
(a) overtime premium does not exceed ___*___
*Overtime Premium $
(Applicable to orders over $150,000 unless for operation of vessels - Blank shall be completed on the individual order)
52.222-19 CHILD LABOR--COOPERATION WITH AUTHORITIES AND REMEDIES (JAN 2018)
(IAW FAR 22.1505(b)) (Applicable for supplies that exceed the micro-purchase threshold)
52.222-20 CONTRACTS FOR MATERIALS, ARTICLES, AND EQUIPMENT EXCEEDING $15,000
(MAY 2014)
(IAW FAR 22.610)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
(IAW FAR 22.810(a)(1)) (Applicable when exceeding $10,000, except those exempted by FAR 22.807 (b) which includes those for work to be performed outside the U.S. by employees who were not recruited within the U.S.)
52.222-26 EQUAL OPPORTUNITY (SEP 2016)
(IAW FAR 22.810(e))
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)
(IAW FAR 22.1310(a)(1), DFARS 222.1310(a)(1)) (Applicable when the expected value is $150,000 or more except when work is performed outside the United States by employees recruited outside the United States or the Director, Office of Federal Contract Compliance Programs, has waived, in accordance with 22.1305(b), all of the terms of the clause)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)
(IAW FAR 22.1408(a)) (Applicable over $15,000 except when performance of work and recruitment of workers will occur outside the United States, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island, or the agency head has waived, in accordance with 22.1403(a) or 22.1403(b) all the terms of the clause)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (FEB 2016)
(IAW FAR 22.1310(b)) (Applicable when the expected value is $150,000 or more and workers were recruited within the United States)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR
RELATIONS ACT (DEC 2010)
(IAW FAR 22.1605)
(Applicable to all solicitations and contracts except under the simplified acquisition threshold, for work performed exclusively outside the U.S., or covered in their entirety by an exemption granted by the Secretary)
52.222-50 COMBATING TRAFFICKING IN PERSONS (JAN 2019)
(IAW FAR 22.1705(a)(1))
252.222-7006 RESTRICTIONS ON THE USE OF MANDATORY ARBITRATION AGREEMENTS
(DEC 2010)
(IAW DFARS 222.7405)
(Applicable to contracts in excess of $1 million utilizing funds appropriated by the FY10 or subsequent DoD appropriations acts, except in contracts for the acquisition of commercial items and commercially available off-the-shelf items)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
(IAW FAR 23.505)
(Applicable when the simplified acquisition threshold is exceeded except if performance is entirely outside the U.S.
and its outlying areas)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE
DRIVING (AUG 2011)
(IAW FAR 23.1105)
252.223-7004 DRUG-FREE WORK FORCE (SEP 1988)
(IAW DFARS 223.570-2)
(Applicable only when exceeding the simplified acquisition threshold and involving access to classified information; or when the Contracting Officer determines the clause is necessary for reasons of national security or for the purpose of protecting the health or safety of those using or affected by the product of, or performance of, the order; and is not applicable when the order is for commercial or commercial-type products (see FAR 12); or performance or partial performance outside the U.S., its territories, and possessions, unless Contracting Officer determines it to be in the best interest of the Government)
252.223-7008 PROHIBITION OF HEXAVALENT CHROMIUM (JUN 2013)
(IAW DFARS 223.7306, DFARS 212.301(f)(xxi)) (Applicable to solicitations and contracts for supplies, maintenance and repair services, or construction)
52.224-3 PRIVACY TRAINING (JAN 2017)
(IAW FAR 24.302(a)) (Applicable to all solicitations and contracts where contractor employees will have access to a system of records or personally identifiable information)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
(IAW FAR 25.1103(a)) (Applicable to supplies or services involving the furnishing of supplies unless an exception applies)
252.225-7004 REPORT OF INTENDED PERFORMANCE OUTSIDE THE UNITED STATES AND
CANADA -- SUBMISSION AFTER AWARD (MAY 2019)
(IAW DFARS 225.7204(b))
(Applicable to solicitations and contracts for performance outside the United States and Canada over $13.5 million)
252.225-7012 PREFERENCE FOR CERTAIN DOMESTIC COMMODITIES (DEC 2017)
(IAW DFARS 225.7002-3(a)) (Applicable when exceeding the simplified acquisition threshold for food; clothing; tents, tarpaulins or covers; cotton and other natural fiber products; woven silk or woven silk blends; spun silk yarn for cartridge cloth; synthetic fabric, coated synthetic fabric; canvas products; wool; or any item of individual equipment (FSC 8465) manufactured from or containing such fibers, yarns, fabrics, or materials; to waste and byproducts of cotton or wool used in the production of propellants and explosives)
252.225-7048 EXPORT-CONTROLLED ITEMS (JUN 2013)
(IAW DFARS 225.7901-4)
252.225-7052 RESTRICTION ON THE ACQUISITION OF CERTAIN MAGNETS AND TUNGSTEN
(APR 2019)
(IAW DFARS 225.7018-5)
252.226-7001 UTILIZATION OF INDIAN ORGANIZATIONS, INDIAN-OWNED ECONOMIC
ENTERPRISES, AND NATIVE HAWAIIAN SMALL BUSINESS CONCERNS
(APR 2019)
(IAW DFARS 226.104)
(Applicable to supplies or services exceeding $500,000)
52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)
(IAW FAR 27.201-2(a)(1)) (Applicable except when both complete performance and delivery are outside the United States)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT
INFRINGEMENT (DEC 2007)
(IAW FAR 27.201-2(b))
(Applicable when the simplified acquisition threshold is exceeded except when both complete performance and delivery are outside the United States unless supplies are ultimately to be shipped into one of those areas)
52.227-11 PATENT RIGHTS--OWNERSHIP BY THE CONTRACTOR (MAY 2014)
(IAW FAR 27.303(b)(1))
252.227-7013 RIGHTS IN TECHNICAL DATA--NONCOMMERCIAL ITEMS (FEB 2014)
(IAW DFARS 227.7102-4(b), DFARS 227.7103-6(a))
(e) (3) The Contractor asserts for itself, or the persons identified below, that the Government's rights to use, release, or disclose the following technical data should be restricted—
Technical Data to be Furnished With Restrictions*
Basis for Assertion**
Asserted Rights Category***
Name of person Asserting Restrictions****
(LIST) (LIST) (LIST) (LIST)
*If the assertion is applicable to items, components, or processes developed at private expense, identify both the data and each such item, component, or process.
**Generally, the development of an item, component, or process at private expense, either exclusively or partially, is the only basis for asserting restrictions on the Government's rights to use, release, or disclose technical data pertaining to such items, components, or processes. Indicate whether development was exclusively or partially at private expense. If development was not at private expense, enter the specific reason for asserting that the Government's rights should be restricted.
***Enter asserted rights category (e.g., government purpose license rights from a prior contract, rights in SBIR data generated under another contract, limited or government purpose rights under this or a prior contract, or specifically negotiated licenses).
****Corporation, individual, or other person, as appropriate.
Date ___________________________________ Printed Name ___________________________________ and Title ___________________________________ Signature ___________________________________
(End of identification and assertion)
(f) (2) Government purpose rights markings.
Data delivered or otherwise furnished to the Government purpose rights shall be marked as follows:
GOVERNMENT PURPOSE RIGHTS
Contract No __________________________________ Contractor Name __________________________________ Contractor Address
Expiration Date __________________________________
The Government's rights to use, modify, reproduce, release, perform, display, or disclose these technical data are restricted by paragraph (b)(2) of the Rights in Technical Data--Noncommercial Items clause contained in the above identified contract. No restrictions apply after the expiration date shown above. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings.
(End of Legend)
(3) Limited rights markings.
Data delivered or otherwise furnished to the Government with limited rights shall be marked with the following legend:
LIMITED RIGHTS
Contract No __________________________________ Contractor Name __________________________________ Contractor Address __________________________________
The Government's rights to use, modify, reproduce, release, perform, display, or disclose these technical data are restricted by paragraph (b)(3) of the Rights in Technical Data--Noncommercial Items clause contained in the above identified contract. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings. Any person, other than the Government, who has been provided access to such data must promptly notify the above name Contractor.
(End of legend)
(4) Special license rights markings.
(i) Data in which the Government's rights stem from a specifically negotiated license shall be marked with the following legend:
SPECIAL LICENSE RIGHTS
The Government's rights to use, modify, reproduce, release, perform, display, or disclose these data are restricted by Contract No. __________ (Insert contract number)_______, License No. __________ (Insert license identifier)______. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings.
(End of legend)
(Applicable when noncommercial items are specified and the successful offeror(s) will be required to deliver technical data to the Government)
252.227-7016 RIGHTS IN BID OR PROPOSAL INFORMATION (JAN 2011)
(IAW DFARS 227.7103-6(e)(1), DFARS 227.7104(e)(1), DFARS 227.7203-6(b)) (Applicable to orders that include the clause at 252.227-7013, 252.227-7018, or 252.227-7014)
252.227-7030 TECHNICAL DATA--WITHHOLDING OF PAYMENT (MAR 2000)
(IAW DFARS 227.7103-6(e)(2), DFARS 227.7104(e)(4))
(a) the Contracting Officer may until such data is accepted by the Government, withhold payment to the Contractor of ten percent (10%) of the total contract price or amount
(Applicable when order specifies technical data to be delivered)
252.227-7037 VALIDATION OF RESTRICTIVE MARKINGS ON TECHNICAL DATA (SEP 2016)
(IAW DFARS 227.7102-4(c), DFARS 227.7103-6(e)(3), DFARS 227.7104(e)(5), DFARS 227.7203-6(f))
(Applicable to commercial items that include the clause at 252.227-7015 or the clause at 252.227-7013; also when clause 252.227-7013 is included or SBIR, include paragraph (e) of the clause - contains information that must be included in a challenge; and when order includes the clause 252.227-7014 when the contractor will be required to deliver noncommercial computer software documentation (technical data))
52.228-7 INSURANCE--LIABILITY TO THIRD PERSONS (MAR 1996)
(IAW FAR 28.311-1)
(Applicable to cost-reimbursement line items)
52.230-2 COST ACCOUNTING STANDARDS (DEVIATION 2018-O0015) (MAY 2018)
(MAY 2018)
52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS (JUN 2010)
(IAW FAR 30.201-4(d)(1)) (Applicable when either clause FAR 52.230-2, 52.230-3, 52.230-4, or 52.230-5 are incorporated)
252.231-7000 SUPPLEMENTAL COST PRINCIPLES (DEC 1991)
(IAW DFARS 231.100-70)
(Applicable over $500,000)
52.232-17 INTEREST (MAY 2014)
(IAW FAR 32.611(a), FAR 32.611(b)) (Applicable when exceeding the simplified acquisition threshold)
52.232-20 LIMITATION OF COST (APR 1984)
(IAW FAR 32.706-2(a)) (Applicable when fully funded and cost-reimbursement)
52.232-22 LIMITATION OF FUNDS (APR 1984)
(IAW FAR 32.706-2(b))
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
(IAW FAR 32.806(a)(1)) (Applicable when the micro-purchase threshold is exceeded, unless the contract will prohibit the assignment of claims (see 32.803(b))
52.232-25 PROMPT PAYMENT (JAN 2017)
(IAW FAR 32.908(c))
(a) Invoice payments—
(5) Computing penalty amount. The Government will compute the interest penalty in accordance with the Office of Management and Budget prompt payment regulations at 5 CFR part 1315.
(i) For the sole purpose of computing an interest penalty that might be due the Contractor, Government acceptance is deemed to occur constructively on the 7th day (unless otherwise specified in this contract) after the Contractor delivers the supplies or performs the services in accordance with the terms and conditions of the contract, unless there is a disagreement over quantity, quality, or Contractor compliance with a contract provision. If actual acceptance occurs within the constructive acceptance period, the Government will base the determination of an interest penalty on the actual date of acceptance. The constructive acceptance requirement does not, however, compel Government officials to accept supplies or services, perform contract administration functions, or make payment prior to fulfilling their responsibilities.
(Applicable except when the clause at 52.212-4, Contract Terms and Conditions--Commercial Items is included)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER--SYSTEM FOR AWARD
MANAGEMENT (OCT 2018)
(IAW FAR 32.1110(a)(1))
(Applicable for solicitations and contracts that include the provision at 52.204-7 or an agency clause that requires a contractor to be registered in the SAM database and maintain registration until final payment, unless (i) Payment will be made through a third party arrangement; or (ii) An exception listed in 32.1103(a) through (i) applies.)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
(IAW FAR 32.706-3)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS (DEC 2013)
(IAW FAR 32.009-2)
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(DEC 2018)
(IAW DFARS 232.7004(a))
(a) Definitions. As used in this clause—
(1) “Contract financing payment” and “invoice payment” have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) “Electronic form” means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) “Payment request” means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/ .
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when—
(1) The Contracting Officer authorizes use of another electronic form. With such an authorization, the Contractor and the Contracting Officer shall agree to a plan, which shall include a timeline, specifying when the Contractor will transfer to WAWF;
(2) DoD is unable to receive a payment request or provide acceptance in electronic form;
(3) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer’s determination with each request for payment; or
(4) DoD makes a payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System).
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.
252.232-7007 LIMITATION OF GOVERNMENT'S OBLIGATION (APR 2014)
(IAW DFARS 232.705-70)