Bldg 590 East Annex SOW.doc
DOC document 198 KB Posted
- Attached to
- Built Up Roofing IDIQ Federal contract opportunity
- Solicitation number
- FA8201-12-R-0016
About this file
Seed Project Bldg 590 SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bldg 590 Cost Estimate.xls | XLS spreadsheet | |
| Roofing Solicitation Amendment.doc | DOC document | |
| 10 July Site Visit Q A.docx | DOCX document | |
| Detail Cost Estimate Final Submittal.xls | XLS spreadsheet | |
| 07510 Built-up Bituminous Roofing.doc | DOC document | |
| Box Elder WD.doc | DOC document | |
| 16859 Heating Cable.doc | DOC document | |
| Davis DW.docx | DOCX document | |
| 01000 General Requirements Bur.doc | DOC document | |
| Seed Project SOW.doc | DOC document | |
| 16610 Lightning Protection.doc | DOC document | |
| Weber WD.doc | DOC document | |
| BUR Solicitation.doc | DOC document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
75TH CIVIL ENGINEER SQUADRON (AFMC)
HILL AIR FORCE BASE, UTAH 84056
Replace Built-up Roof
Bldg 590 East Annex
WO# 54034
KRSM 122046
Project Manager: Alan Dailey 75th CEG/CEOS Ph: 801-777-7280 3 May 2012
STATEMENT OF WORK
1. Repair by replacement the built-up roof on the East Annex of Building 590
2. Remove existing non-friable asbestos flashings. The contractor shall adhere to OSHA regulations 1926 and specifically 1926.1101 regarding the removal of non-friable asbestos containing roof materials. (Note: Asbestos flashings shall be removed by the Base approved asbestos abatement contractor)
3. Remove existing built-up roof system, drip edge, flashings and counter flashings, gutters and downspouts.
4. Remove and dispose of abandoned air conditioning unit on roof.
5. Remove all abandoned pipe jacks, roof penetration curbs, and coverings.
6. Furnish and install approximately 10,800 SF of ¾” perlite cover board, hot-mopped to deck.
7. Furnish and install a 3-ply, hot-mopped 20 year BUR with an SBS modified cap sheet.
8. Install base flashings, metal counter flashings, wall counter-flashings, parapet cap.
9. Install new gutters and downspouts with necessary heat tape and controls.
10. Furnish and install approximately 800 SF of metal siding to cover existing siding on north and south walls of exiting sloping metal roof.
11. Performance period for this contract is 90 days.