Bldg 590 East Annex SOW.doc

DOC document 198 KB Posted

Attached to
Built Up Roofing IDIQ Federal contract opportunity
Solicitation number
FA8201-12-R-0016
Issued by
Department of the Air Force Materiel Command Ogden Air Logistics Complex

About this file

Seed Project Bldg 590 SOW

View the file

Other files for this federal contract opportunity

Other files attached to Built Up Roofing IDIQ, newest first.
File Type Posted
Bldg 590 Cost Estimate.xls XLS spreadsheet
Roofing Solicitation Amendment.doc DOC document
10 July Site Visit Q A.docx DOCX document
Detail Cost Estimate Final Submittal.xls XLS spreadsheet
07510 Built-up Bituminous Roofing.doc DOC document
Box Elder WD.doc DOC document
16859 Heating Cable.doc DOC document
Davis DW.docx DOCX document
01000 General Requirements Bur.doc DOC document
Seed Project SOW.doc DOC document
16610 Lightning Protection.doc DOC document
Weber WD.doc DOC document
BUR Solicitation.doc DOC document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

75TH CIVIL ENGINEER SQUADRON (AFMC)

HILL AIR FORCE BASE, UTAH 84056

Replace Built-up Roof

Bldg 590 East Annex

WO# 54034

KRSM 122046

Project Manager: Alan Dailey 75th CEG/CEOS Ph: 801-777-7280 3 May 2012

STATEMENT OF WORK

1. Repair by replacement the built-up roof on the East Annex of Building 590

2. Remove existing non-friable asbestos flashings. The contractor shall adhere to OSHA regulations 1926 and specifically 1926.1101 regarding the removal of non-friable asbestos containing roof materials. (Note: Asbestos flashings shall be removed by the Base approved asbestos abatement contractor)

3. Remove existing built-up roof system, drip edge, flashings and counter flashings, gutters and downspouts.

4. Remove and dispose of abandoned air conditioning unit on roof.

5. Remove all abandoned pipe jacks, roof penetration curbs, and coverings.

6. Furnish and install approximately 10,800 SF of ¾” perlite cover board, hot-mopped to deck.

7. Furnish and install a 3-ply, hot-mopped 20 year BUR with an SBS modified cap sheet.

8. Install base flashings, metal counter flashings, wall counter-flashings, parapet cap.

9. Install new gutters and downspouts with necessary heat tape and controls.

10. Furnish and install approximately 800 SF of metal siding to cover existing siding on north and south walls of exiting sloping metal roof.

11. Performance period for this contract is 90 days.