16859 Heating Cable.doc
DOC document 26 KB Posted
- Attached to
- Built Up Roofing IDIQ Federal contract opportunity
- Solicitation number
- FA8201-12-R-0016
About this file
Design Standard Section 16859 Heating Cable
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bldg 590 Cost Estimate.xls | XLS spreadsheet | |
| Roofing Solicitation Amendment.doc | DOC document | |
| 10 July Site Visit Q A.docx | DOCX document | |
| Bldg 590 East Annex SOW.doc | DOC document | |
| Box Elder WD.doc | DOC document | |
| Davis DW.docx | DOCX document | |
| 01000 General Requirements Bur.doc | DOC document | |
| Seed Project SOW.doc | DOC document | |
| Detail Cost Estimate Final Submittal.xls | XLS spreadsheet | |
| 07510 Built-up Bituminous Roofing.doc | DOC document | |
| 16610 Lightning Protection.doc | DOC document | |
| Weber WD.doc | DOC document | |
| BUR Solicitation.doc | DOC document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 16859
HEATING CABLE
PART I – GENERAL
1.1 GENERAL REQUIREMENTS:
A. Delivery and Storage:
1. Deliver material to site in undamaged condition.
1.2 REQUIRED SUBMITTALS:
A. General: Submit each item in this Section according to the Condition of the Contract and Division 1 Specification Section.
B. Manufacturers Literature:
1. Technical Data, Catalog Cuts, Installation Procedures and Operation & Maintenance Manuals.
PART II – PRODUCTS
2.1 HEATING CABLE:
A. Heat cable shall be Chromalox SRF5-1RG or SRF5-2RG Roof and Gutter Heating Cable or approved equal. 16 AWG, nickel-coated copper, tinned copper ground braid under jacket, U.V. stabilized weatherproof jacket and 12 watts/ft. output wattage in snow or ice @ 32 degrees F.
2.2 AUTOMATIC TEMPERATURE CONTROLS:
A. Temperature Controls shall be Chromalox RTAS or RTAS-EP Ambient Sensing Single Point On/Off Temperature Controls or approved equal. Ambient sensing thermostats, 0-225 degrees F. temperature rating, 9/16” O.D. x 4” stainless steel probe, stainless steel hardware, Ordinary or Hazardous (Div. 2) Areas and rated NEMA 4X. Set controls at 40 degrees F.
PART III – EXECUTION
3.1 INSTALLATION:
A. Project Work shall include at least a 20 amp circuit breaker installed in an existing power panel. Breakers shall be marked “roof heating cable controls” in the panel.
B. Controls shall be wired through a pilot light mounted next to the existing main power panel. Pilot light shall be red in color.
C. Heat cable shall not be cut or spliced unless absolutely necessary. Heat cable shall be a continuous run along the gutter and twice through the downspout to form a cable run that is free of splices. When splicing is required, the contractor shall use manufacturer recommended splice and tee kits. The contractor shall use manufacturer recommended end seal kits where needed.
D. Install heat Cable in all gutters and downspouts. Install heat cable in a manner that will prevent the wind from lifting the heat cable from the gutter and downspout.