Questions_ _answers.pdf

PDF 14 KB Posted

Attached to
Repair Storm Water System, Basewide
Solicitation number
FA6703-14-B-0003
Issued by

About this file

Questions Answers

View the file

Other files

File Type Posted
Bid_Schedule.pdf PDF
FA6703-14-B-0003-0003.pdf PDF
Soils_Sediment_Testing.pdf PDF
FA6703-14-B-0003-0002.pdf PDF
Soils_Sediment_Testing.pdf PDF
FA6703-14-B-0003-0002.pdf PDF
Inert_Facilities.pdf PDF
Disposal_Facilities.pdf PDF
FA6703-14-B-0003-0001.pdf PDF
7._Wage_Determination.pdf PDF
1._Drawings.pdf PDF
FA6703-14-B-0003.pdf PDF
4._Corrected_Final_Civil_Narrative.pdf PDF
9._Limitations_on_Subcontracting.pdf PDF
5._GA_Erosion_and_Sedimentation_Control_Education_Program.pdf PDF
8._Financial_Worksheet.pdf PDF
3._Executive_SummaryRev01.pdf PDF
2._Specifications.pdf PDF
10._DARB4.pdf PDF
6._GA_EPD_NOI_StormWater_Primary_Permitee_Y2008.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA6703-14-B-0003

Repair Storm Water Drainage, Basewide

FGWB 10-0030

Questions & Answers

9 Sep 2014

Q1. Specification section 01 11 00-1.8, indicates “Scan the construction site with Ground Penetrating Radar and electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered.” Please clarify the requirements since we cannot determine what utilities are expected in the area.

Known utilities are shown on the plans. Exact depths are unknown.

Q2. What record documents/as built surveys are required?

Per Section 01 78 00

Q3. Sheet 30 of 31, Plate No C-127 refers to designated waste or spoil areas to be provided by the Government. Please provide location of the waste site(s) for this project.

See attached spreadsheet

Q4. Re: Sheet 9 of 31, Plate C-106; Does the area need to be dewatered prior to installation of the geotextile and rip rap? The outlet pipe area appears to be constantly wet. Please also clarify what the clearing and grubbing requirements for this area.

Dewatering is a ‘means and method’ way to complete the requirement of this area. If the contractor proposes to dewater this area (or any other areas) then a dewatering plan will be required per the specifications.

Clearing and Grubbing as shown on plans within the limits of disturbance.