Bid_Schedule.pdf

PDF 21 KB Posted

Attached to
Repair Storm Water System, Basewide
Solicitation number
FA6703-14-B-0003
Issued by

About this file

Bid Schedule Use the attached document as Schedule B.

View the file

Other files

File Type Posted
FA6703-14-B-0003-0003.pdf PDF
Soils_Sediment_Testing.pdf PDF
FA6703-14-B-0003-0002.pdf PDF
Soils_Sediment_Testing.pdf PDF
FA6703-14-B-0003-0002.pdf PDF
Questions_ _answers.pdf PDF
Disposal_Facilities.pdf PDF
Inert_Facilities.pdf PDF
FA6703-14-B-0003-0001.pdf PDF
7._Wage_Determination.pdf PDF
5._GA_Erosion_and_Sedimentation_Control_Education_Program.pdf PDF
8._Financial_Worksheet.pdf PDF
3._Executive_SummaryRev01.pdf PDF
1._Drawings.pdf PDF
FA6703-14-B-0003.pdf PDF
4._Corrected_Final_Civil_Narrative.pdf PDF
9._Limitations_on_Subcontracting.pdf PDF
2._Specifications.pdf PDF
10._DARB4.pdf PDF
6._GA_EPD_NOI_StormWater_Primary_Permitee_Y2008.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot Repair Storm Water System Site A

FFP

FGWB 10-0030, Repair Storm Water System Basewide: Site A consists of the elimination of drainage and erosions issues on both sides of Gym Road on Dobbins ARB in accordance with attached Specifications, 14 Aug 2014, and drawings date 13 Dec 2013. Work under this project will require a NPDES permit. Governement has submitted Notice of Intent. Contractor shall submit Notice of termination at the end of the project completion..FOB: Destination

PURCHASE REQUEST NUMBER: F5B3234213A001

NET AMT

0002 1 Lot Repair Storm Water System Site B

FFP

FGWB 10-0030, Repair Storm Water System Basewide: Site B consists of the repair of an existing drainage feature to prevent drainage flow from entering Little Lake on Dobbins ARB in accordance with attached Specifications, 14 Aug 2014, and drawings date 13 Dec 2013. Work under this project will require a NPDES permit. Governement has submitted Notice of Intent. Contractor shall submit Notice of termination at the end of the project completion.

FOB: Destination

SIGNAL CODE: A

BID SCHEDULE

0003 1 Lot Repair Storm Water System Site C

FFP

FGWB 10-0030, Repair Storm Water System Basewide: Site C consists of the repair to the drainage channel alongside Spill Pone 3 on Dobbins ARB in accordance with attached Specifications, 14 Aug 2014, and drawings date 13 Dec 2013. Work under this project will require a NPDES permit. Governement has submitted Notice of Intent. Contractor shall submit Notice of termination at the end of the project completion.

FOB: Destination

0004 1 Lot Repair Storm Water System Site D

FFP

FGWB 10-0030, Repair Storm Water System Basewide: Site D consists of the constructing measure to prevent sediment from being discharge into a downstream wetland from the USAF Civil Engineering Training Site on Dobbins ARB in accordance with attached Specifications, 14 Aug 2014, and drawings date 13 Dec 2013. Work under this project will require a NPDES permit. Governement has submitted Notice of Intent. Contractor shall submit Notice of termination at the end of the project completion.

FOB: Destination