5-DRAFT CDRL A001-03 RIS O M
View the file
Other files for this federal contract opportunity
Show all 50
Aerial Targets Operations and Maintenance Services has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT AERIAL TARGETS PWS
Solicitation No. FA4890-14-R-0001
APPENDIX B – CONTRACT DATA REQUIREMENTS LIST (CDRL)
Tab 03 (CDRL A001-03)
Range Instrumentation System (RIS) Operations & Maintenance (O&M) Activities
Monthly Reports for RIS O&M shall include the following:
· Operational Availability or A(o) for the Tellabs Switch and Data/Comm circuits
· Report shall include the most recent month and a rolling average of the preceding 12 months. Calculate A(o) IAW PWS Table 1.6 Service Summary section 3.
· Mission Availability or M(a) for the GRDCS, BC3, Orion Communication System, MCS Vans, TPS-75 RADAR, and the Mission Video System,
· Report shall include the most recent month and a rolling average of the preceding 12 months. Calculate M(a) IAW PWS Table 1.6 Service Summary section 3.
· Summary of maintenance actions for RIS equipment/circuits and GRDCS Tracking Pods. Include the following data:
· The number of missions cancelled due to an outage of the GRDCS, BC3, Orion Communication System, MCS Vans, or TPS-75 RADAR equipment.
· Start Date/Time, Stop Date/Time, Duration, Outage, Equipment, Repair Actions, Parts Used.
· Operating hours for GRDCS and BC3, including the number of hours devoted to:
· Mission support.
· Maintenance.
· Engineering and systems programming efforts.
· Administrative or other overhead functions.
· Maintenance and Logistics Problems:
· List of top 5 parts most frequently ordered during preceding 12-month period.
· List of top 5 parts ordered with longest time on order.
· Describe areas which have impacted past mission accomplishment.
· Identify problems which may affect future mission capabilities.
· Summary of information regarding range tower conditions affecting safety or mission operations.
· Summary of Scheduled Maintenance actions for RIS equipment:
· Due in the next 45 days.
· Accomplished during the preceding calendar month.
· Current status of accounts authorized for GRDCS and BC3 operations
· The first report shall include:
· Amount of time used by each account during the month in hours of fractions.
· Name of the individual to whom the account was issued.
· Degree of access provided.
· Subsequent reports shall contain:
· Changes to account status.
· Additions and deletions.
· The times utilized by each account are required each month.
· Synopsis of engineering and systems programming tasks in progress, identified by:
· Short title.
· Date initiated.
· Estimated date of completion.
· Current status.
· Problems anticipated or encountered.
· Special Projects: Provide a summary of GRDCS/BC3/Telecommunications related test projects supported.
AERIAL TARGETS DRAFT PWS
B-A001-03-1