Appx_J_RealProperty-DRAFT.pdf

PDF 194 KB Posted

Attached to
Forward Operating Location - Base Operating Support (FOL-BOS) Curacao Federal contract opportunity
Solicitation number
FA4890-13-R-0117
Issued by
Department of the Air Force Air Combat Command

About this file

DRAFT Appendix J - Real Property

View the file

Other files for this federal contract opportunity

Other files attached to Forward Operating Location - Base Operating Support (FOL-BOS) Curacao, newest first.
File Type Posted
Questions_and_Answers_Posted_16_Jan_14.pdf PDF
Q_and_A_16_Jan_14_(corrected_from_15_Jan_14_post).pdf PDF
Appx_K_GovernmentFurnishedProperty_15Jan14.docx DOCX document
FA4890-13-R-0117-A004.pdf PDF
Appx_A_DefinitionsAbbreviationsAcronyms_8Jan14 1 .docx DOCX document
FA489013R0117_PWS_10Jan14.docx DOCX document
Q_and_A_10_Jan_14.pdf PDF
Appx_C_PublicationForms_8Jan14.docx DOCX document
Appx_M_Certification_8Jan14.docx DOCX document
Appx_G_EstimatedWorkload_9Jan14.docx DOCX document
App_E_FOL_BOS-MOU_Postal_Support_Curacao.pdf PDF
FOL_Notice_of_Forthcoming_Amendment_and_Extension.pdf PDF
FA4890-13-R-0117-Amendment_0001.doc DOC document
Appx_C_PublicationForms_20Dec13.docx DOCX document
PICT2203.jpg JPG image
PICT2199.jpg JPG image
PICT2201.jpg JPG image
FOL-BOS_Site_Visit_Itinerary_19-20_Nov.pdf PDF
FA4890-13-R-0117_DD254_Atch_1.pdf PDF
FOL-BOS_Q As_25_Nov.pdf PDF
Appx_O_ContractInclusions_5_Dec_13.docx DOCX document
FA4890-13-R-0117_QandAs_5_Dec_13.pdf PDF
Parking_for_Bidders_(Map).pptx PPTX presentation
PreSolicitation_Notice.docx DOCX document
Appx_B_CDRLs(6Nov2013)DRAFT.pdf PDF
FOL_PWS(12Nov13)DRAFT.docx DOCX document
FA4890-13-R-0117_Site_Visit_Letter_-_Reschedule.docx DOCX document
Appx_M_Certification(18Sep13)DRAFT.docx DOCX document
Appx_P_COMSPOT-COMSTAT(13Sep13)DRAFT.docx DOCX document
Appx_I_C4I-PerformanceIndicators(13Sep13)DRAFT.docx DOCX document
Appx_C_PublicationForms(13Sep13)DRAFT.docx DOCX document
Appx_B_CDRLs(13Sep13)DRAFT.pdf PDF
Appx_O_ContractInclusions(13Sep13)DRAFT.docx DOCX document
Appx_D_QualityManagementSystem_(13Sep13)DRAFT.doc DOC document
Q A_-_13_Sep_13.pdf PDF
Request_for_Additional_Information_-_Potential_Small_Business_Set-Aside_Determination_ —
FA4890-13-R-0117-_DRAFT_SECTIONS_L M.docx DOCX document
Appx_N_KeyPersonnelQualifications-DRAFT.pdf PDF
Appx_M_Certifications-DRAFT.pdf PDF
Appx_G_EstimatedWorkload_9Jan14.docx DOCX document
FOL-BOS_Industry_Day_Attendees.pdf PDF
Appx_O_ContractInclusions-DRAFT.pdf PDF
Appx_H_TransientLodging-DRAFT.pdf PDF
FOL-BOS_Industry_Day_Announcement.docx DOCX document
FOL-BOS-Industry_Day_Govt_Questions.docx DOCX document
Appx_K_GovernmentFurnishedProperty_DRAFT.docx DOCX document
FOL-BOS_Industry_Day_Brief.pdf PDF
Appx_E_SupportAgreements-DRAFT.pdf PDF
Appx_A_DefinitionsAbbreviationsAcronyms_8Jan14 1 .docx DOCX document
Appx_M_Certification_8Jan14.docx DOCX document
Show all 50

Forward Operating Location - Base Operating Support (FOL-BOS) Curacao has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. FA4890-13-R-0117

DRAFT

J-1

APPENDIX J

Real Property Listing

1.0 General. Per Paragraph x.xx of the PWS, the listing below will be managed and all property listed will be maintained. This listing will be made available also in MS Excel format for use in developing the annual real property update, CDRL A016.

1.1 Items Not Officially RP, RPIE: Near the end of this list are items under the category “Not on

7115 – Maintain”. These are items that, although not on the official 7115 document at 355 th

CES, are part of the facility in question and are included here for completeness. For example, all automated gates are listed even though they are considered part of the fencing in the real property records.

1.2 Document Changes. At the time of this solicitation, not all real property changes are finalized. In red font are anticipated changes to this list to make it as close to end of contract transition as possible.

CUR MAINTAIN

Fac

Nbr Name

Area

Quan

Area

Um

Other

Quan

Other

Um Remarks

11 EXERCISE STATIONS 10 EA

10 exercise stations along base of cliff

100 FIRE STATION 1,658 SF Offices / Kitchen / shower Facility

100 AUTO FR DTECTN SYS 1,650 SF 1 EA

100 MAN FR ALRM/I SYS 2 EA

100 A/C PLT 5 TO 25 TN 5 TN 1-5 ton unit

100 OTHER FR SYS 1 EA Guardian III chemical extinguisher unit for stove hood

200 FIRE STATION 2,270 SF Crew Sleeping Qtrs Facility

200 AUTO FR DTECTN SYS 2,250 SF 1 EA

200 A/C PLT 5 TO 25 TN 12 TN

1-5 ton unit, 1-4 ton unit, and 1-3 ton unit

200 SEWAGE TRMT & DISPL 2 KG Sewage Batch Reactor

220 VEH OPS PKNG SHED 4,429 SF

DRIVEWAY 1,982 SY New PCC pavement and ramps for veh shelter.

DRIVEWAY 702 SY New asphalt pavement next to veh shelter.

SPT STRUCTURE 10 EA New bollards on ramps.

300 FIRE STATION 1,650 SF Crew Sleeping Qtrs Facility

300 AUTO FR DTECTN SYS 1,656 SF 1 EA

300 MAN FR ALRM/I SYS 2 EA

300 A/C PLT 5 TO 25 TN 9 TN 3-3 ton unit units

400 FIRE STATION 3,623 SF Administration and Alarm Room

J-2

CUR MAINTAIN

Fac

Nbr Name

Area

Quan

Area

Um

Other

Quan

Other

Um Remarks

Facility

400 OPG STOR, DIESEL 500 GAL Fuel tank for FDC generator

ELECTRIC E/ PWR GEN

PLT

275 KW 1 EA

Located behind Bldg 400

400 AUTO FR DTECTN SYS 3,600 SF 1 EA

400 MAN FR ALRM/I SYS 4 EA

400 A/C PLT 5 TO 25 TN 16 TN

1-5 ton unit, 2-4 ton units, and 1-3 ton unit

500 TRAFFIC CHK HSE 200 SF NW Guard house

512 POL FACILITY 837 SF

512 A/C PLT 5 TO 25 TN 1 EA 3 TN 2 A/C Units 1- ton and 1-1.5 ton

512 AUTO FR DTECTN SYS 850 SF 1 EA

512 MAN FR ALRM/I SYS 1 EA

ADDITION TO BLDG

FOR FUELS LAB

600 SF

Under construction in FY14.

514 STOR LIQ OXYGEN 2,000 SF Under construction in FY14.

VEHICLE FUELING

STATION

1,291 SF

Concrete Pad

515 OPG STOR, MOGAS 5 KG 5,000 gallon Self Contained

Aboveground Tank (SCAT)

515 OPG STOR, DIESEL 5 KG 5,000 gallon Self Contained

Aboveground Tank (SCAT)

517 VEH PKNG, REFUELER 1,200 SY Refuleing truck parking pad

518 IND WST FL SP COLL 12 KG

12,000 gallon concrete containment basin

520 PAD, ACFT WASH RK 1,937 SY 1 EA Aircraft wash rack

525 STOR LIQ OXYGEN 400 SF Becoming general storage when C-

514 complete.

530 PMP STN, LF 216 SF Aircraft wash rack pump house

540 ELEC SUBSTATION 134 SF 12 KV

550 WTR TANK STOR 33 KG

Water storage tank for aircraft wash rack

570 SPT STRUCTURE 400 SF SATCOM Pad

580 ELEC SUBSTATION 134 SF 12 KV

600 SQ OPS 14,259 SF

ELECTRIC E/ PWR GEN

PLT

220 KW 1 EA

600 AUTO FR DTECTN SYS 14,259 SF 1 EA

600 MAN FR ALRM/I SYS 6 EA

600 A/C PLT 25 TO 100 TN 46 TN 9 units approx 5 ton each and 1 unit in mech room approx 1 ton

J-3

CUR MAINTAIN

Fac

Nbr Name

Area

Quan

Area

Um

Other

Quan

Other

Um Remarks

610 SPT STRUCTURE 1 EA VHF Antenna Tower

650 BUS SHELTER 108 SF

700 SHP A/M ORGL 14,663 SF

ELECTRIC E/ PWR GEN

275 KW 1 EA

700 AUTO FR DTECTN SYS 8,869 SF 1 EA

700 MAN FR ALRM/I SYS 3 EA

705 ARMAG 128 SF SF Armory

700 A/C PLT 5 TO 25 TN 32 TN 6 units approx 5 ton each and 1 unit in mech room approx 2 ton

710 ELEC SUBSTATION 134 SF 12 KV

800 SHP A/SE STOR FCLT 12,000 SF AGE/Vehicle Maintenance

CLOSED HEAD

SPRINKLERS

119 HD

800 AUTO FR DTECTN SYS 11,560 SF 1 EA

800 MAN FR ALRM/I SYS 4 EA

800 A/C PLT 5 TO 25 TN 10 TN

ADDITION TO BLDG

FOR CE FUNCTION

2,900 SF

Under construction in FY14.

830 BE STORE CV FCLTY 130 SF Civil Engineering storage

AGE STORAGE

FACILITY

7,000 SF

Under construction in FY14.

MAIN DOCK, M/A (HG

MAINT)

30,052 SF

ELECTRIC E/ PWR GEN

275 KW 1 EA

CLOSED HEAD

SPRINKLERS

330 HD

900 AFFF SYSTEM 1 EA

900 AUTO FR DTECTN SYS 29,798 SF 1 EA

900 OTHER FR SYS 1 EA Cease Fire CFF 800 system

900 MAN FR ALRM/I SYS 8 EA

900 A/C PLT 5 TO 25 TN 22 TN 4 units

900 A/C PLT, LS 5 TN 2 TN 1 unit 2.25 tons

905 STOR, BSE 7,000 SF Multi-purpose warehouse

905 CLSD HD A/SPRINKLER 76 HD

905 AUTO FIRE DETC 7,000 SF 1 EA

905 MAN FR ALRM/I SYS 2 EA Manual pull stations

906 WTR FR PMP S 245 SF

Fire pump room on south end of

Bldg 905

J-4

CUR MAINTAIN

Fac

Nbr Name

Area

Quan

Area

Um

Other

Quan

Other

Um Remarks

915 OPEN STOR BSE SUP 380 SY Constructed in 2011 AFCEE

Contract # N69450-C-0029

920 SPT STRUCTURE 1 EA WSTI Tower

930 ELEC SUBSTATION 134 SF 12 KV

940 WTR TANK STOR 166 KG Tank A Fire Suppression

950 WTR TANK STOR 166 KG Tank B Fire Suppression

990 TRAFFIC CHK HSE 200 SF NE Guardhouse

991 TRAFFIC CHK HSE 147 SF ECP Guard house

991 A/C PLT 5 TO 25 TN 1 TN

992 HV SWITCH STATION 134 SF Adjacent to Hato Free Zone ECP

SOLAR COLLECTION

SYSTEM

115 KW Located near Bldg 992 and connected to 930.

1002 TAXIWAY 33,757 SY Hato Airport Property

1003 LIGHT,TWY 2300 LF Hato Airport Property

1004 APRON 30,589 SY

1005 SIDEWALK 1,036 SY Includes concrete pavers between

Bldg 600 and 700

1006 FENCE, BOUNDARY 9228 LF

1007 EXTERIOR AREA LTG 46 EA

Pole mounted street and parking lot lights (39 at FOL compound and 4 at the FDC)

1008 SEC DISTR LNE UG 5500 LF Underground cable

1009 DRIVEWAY 2,943 SY

1010 SAN SEWAGE MAIN 771 LF FDC Lateral

1011 WTR DISTR MAINS 1515 LF

1012 STRM DRN DSPL 6050 LF

1013 VEH PKNG, OPS 65,319 SY

1014 SHLDR,PAVED 22,731 SY Around aircraft apron

1018 FR PROTEC WTR MAIN 3609 LF 800 & 900 fire suppression

1019 FR HYDR 11 EA

1021 FENCE, INTERIOR 3149 LF

1022 FENCE, INTERIOR 110 LF Fence and masonry wall at new

HAZMAT Yard 915

1023 SAT COM GND TRML 220 SF TADIL

1023 ELEC PWR GEN PLANT 40 KW

1023 AUTO FR DTECTN SYS 220 SF 1 EA

1023 MAN FR ALRM/I SYS 1 EA

1023 A/C PLT 5 TO 25 TN 10 TN 2 units approximately 5 ton each

1025 SPT STRUCTURE 5 EA utility poles for HF antennas

J-5

CUR MAINTAIN

Fac

Nbr Name

Area

Quan

Area

Um

Other

Quan

Other

Um Remarks

1028 SPT STRUCTURE 2 EA

COMMUNICATION

DUCT

5500 LF

runs parallel to underground electric

1031 SPT STRUCTURE 1 EA

1032 ACFT ARES SYS SPT 240 SF 1 EA BAK-12 shacks and system

1035 TRAFFIC CHK HSE 78 SF Red Gate guard shack

1035 A/C PLT, LS 5 TN 1 EA 1-window type A/C

1037 SPT STRUCTURE 1 EA Concrete foundation

1038 STRM DRN DSPL 125 LF

1039 SPT STRUCTURE 82 EA

Bollards (added 3 in 2011 at Facility

915 an 18 at Facility 517 for a new total of 82)

1040 SPT STRUCTURE 3 EA

1041 OBSTRUCTION LIGHTS 16 EA

83100 SEPTIC TANK 1 KG 1 EA

Percolating septic pit Serves building 512

83110 SEPTIC TANK 7 KG Percolating septic pit for 900

83111 SEPTIC TANK 1 KG Percolating septic pit for ECP

Guard house

83112 SEPTIC TANK 1 KG

Percolating septic pit--unused East of 800

83113 SEPTIC TANK 13 KG

Percolating septic pit for 600, 700, and 800

85114 ROAD 120 LF

85115 ROAD 122 SY 56 LF

Concrete road in front of Fuel

Station leading to the aircraft parking apron

85116 ROAD 605 SY 279 LF Asphalt Perimeter road leading to the Fuel Station

85117 ROAD 118 SY 80 LF Gravel access road to drainage basin on west of the west fence line

NOT ON 7115-

MAINTAIN

70 AUTOMATIC GATE 1 EA Vehicle gate on the FDC compound

FDC GEN COVERED

STORAGE

526 SF

Wood temporary cover installed in

90 AUTOMATIC GATE 1 EA

Red Gate on Hato property near the

FDC

510 STORAGE MAG 200 SF Portable ARMAG

565 AUTOMATIC GATE 1 EA Flight line (w-600)

566 AUTOMATIC GATE 1 EA South of TADIL near refueling truck parking pad.

J-6

CUR MAINTAIN

Fac

Nbr Name

Area

Quan

Area

Um

Other

Quan

Other

Um Remarks

SECURITY ALARM

SYSTEM

1 EA For entrance doors never connected during installation in 2003

SECURITY ALARM

SYSTEM

1 EA For entrance doors never connected during installation in 2003

ACFT COR CON (PAINT

BOOTH)

400 SF

SECURITY ALARM

SYSTEM

1 EA

800 COMPRESSOR 2 each

SECURITY ALARM

SYSTEM

1 EA For entrance doors never connected during installation in 2003

900 COMPRESSOR 29,000 SF 1 EA

960 AUTOMATIC GATE 1 EA ECP

961 AUTOMATIC GATE 1 EA ECP

962 AUTOMATIC GATE 1 EA Free Zone, Manual gate

1033 BARRIER SIGNS 2 EA

1050 A/C PLT 5 TO 25 TN 2 EA TACAN facility

TACAN GENERATOR

BUILDING

200 SF

1051 GENERATOR 30 KW

1054 TACAN SIGNS 3 EA

DISTANCE TO GO

MARKERS

20 EA

85115

DRIP IRRIGATION

SYSTEM

600 LF

At Bldg 600, 700 and 800

File details come from the government source that posted it. Updated .