Attachment_3_-_SOMS_-_CZQZ170014_-_SOF_Construct_PAD_For_Train_Sim.pdf
PDF 52 KB Posted
- Attached to
- SOF Construct Pad Federal contract opportunity
- Solicitation number
- FA4855-18-R-0013
About this file
Schedule of Material Submittals
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
LI
N
E N
U M
B
ER
ITEM, DESCRIPTION OF ITEM,
CONTRACT REFERENCE,
TYPE OF SUBMITTAL
C
ER
TI
F
O F
C O
M
PL
IA
N
C E
SC
H
ED
U
LE
S/
PL
A
N S
SH
O
P D
R A
W
IN
G S
SA
M
PL
ES
C
O
LO
R S
EL
EC
T
TE
ST
R
ES
U
LT
S
M A
N F'
R R
EC
O
M M
EN
D
A
TI
O N
S
M A
N F'
R . W
A R
R A
N
TY
LI
C
EN
SE
D A
PP
LI
C A
TO
R
M A
N U
F' S
TE
C
H N
IC
A
L D
A
TA
O
M M
A N
U A
LS
O
TH
ER
R
EQ
U
IR
ED
SU
B M
IS
SI
O N
D A
TE
D A
TE
R
EC
EI
VE
D
IN
C
O N
TR
A
C
TI
N G
D A
TE
T
O
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D A
TE
FO
LL
O W
-U P
C O
N
TR
A C
TO
R
N O
TI
FI
A pp ro va l D at e
C O
N
TR
A C
TO
R
N O
TI
FI
ED
D is ap pr ov al
D at e
C O
N
TR
A C
TO
R
E-
SU
B M
IT
TA
L
FI
N
A L
A
PP
R O
VA
L
R
EM
A R
K S
01 45 00. 05 20 Paragraph 1.3.3 Quality Control Plan(QCP)
2 14 business days after NTP
01 32 01.00 10 Paragraph 3.1 subparagraphs .1 thru .5- Project Schedule -
2 14 business days after NTP
01 35 40.00 20 paragraph 1.8 Environmental Protection Plan
2 14 business days after NTP
01 74 19 Paragraph 1.3 Waste Management Plan 2
15 business days after Award
01 35 26.paragraph 1.7 Accident Prevention Plan 2 14 business days after NTP
01 35 26 Paragraph 1.9 Activity Hazard Analysis 2
15 business days prior to each Definable Feature of
Work/Phase
01 01 00.Paragraph 1.9 - AF Form 103 - Work Clearance Request
10 business days prior to
Demolition
01 01 00 Paragraph 1.8 Utility Outage Request
NLT 10 businesss days prior to Outage
01 35 26 Paragraph 1.13.B Accident Report-
2 As Incident Occurs
01 35 26 Paragraph 1.14 Hot Work Permit 2 2 business days prior to Hot
Work
TO BE COMPLETED BY PROJECT ENGINEER
NUMBER OF COPIES REQUIRED
SOLICITATION/CONTRACT NO.
AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALS - 29 NOV 2017
PROJECT #
CZQZ170014
PROJECT TITLE
SOF CONSTRUCT PAD FOR
TRAINING SIMULATION
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
LI
N
E N
U M
B
ER
ITEM, DESCRIPTION OF ITEM,
CONTRACT REFERENCE,
TYPE OF SUBMITTAL
C
ER
TI
F
O F
C O
M
PL
IA
N
C E
SC
H
ED
U
LE
S/
PL
A
N S
SH
O
P D
R A
W
IN
G S
SA
M
PL
ES
C
O
LO
R S
EL
EC
T
TE
ST
R
ES
U
LT
S
M A
N F'
R R
EC
O
M M
EN
D
A
TI
O N
S
M A
N F'
R . W
A R
R A
N
TY
LI
C
EN
SE
D A
PP
LI
C A
TO
R
M A
N U
F' S
TE
C
H N
IC
A
L D
A
TA
O
M M
A N
U A
LS
O
TH
ER
R
EQ
U
IR
SU
B M
IS
SI
O N
D A
TE
D A
TE
R
EC
EI
VE
D
IN
O N
TR
A
C
TI
N G
D A
TE
T
O
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D A
TE
FO
LL
O W
-U P
C O
N
TR
A C
TO
R
N O
TI
FI
A pp ro va l D at e
C O
N
TR
A C
TO
R
N O
TI
FI
ED
D is ap pr ov al
D at e
C O
N
TR
A C
TO
E-
SU
B M
IT
TA
L
FI
N
A L
A
PP
R O
VA
L
R
EM
A R
K S
TO BE COMPLETED BY PROJECT ENGINEER
NUMBER OF COPIES REQUIRED
SOLICITATION/CONTRACT NO.
AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALS - 29 NOV 2017
PROJECT #
CZQZ170014
PROJECT TITLE
SOF CONSTRUCT PAD FOR
TRAINING SIMULATION
01 33 00 paragraph 11.c SD-11 Closeout Submittals
2 30 days Prior to BOD
01 78 23 Paragraph 1.5.5.a Electronic As-Built
3 10 business days after BOD
01 78 23 paragraph 1.5.5.b Hardcopy As-Builts
3 10 business days after BOD
01 33 00 paragraph 1.1.A.10 Operation and Mainteanance Data 2 2 2 2 10 business days after BOD
15 01 33 00 paragraph 1.1.A.4 Product Data 2 15 business days prior to each
Definable Feature of Work/Phase
26 41 00 para 1.4.1.1 LPS shop drawings
14 business days prior to
Construction
Sheet1