Attachment 1 Statement of Work to MACC

View the file

Other files

File Type Posted
info.pdf PDF
NOTICE.docx DOCX document
Amendment 10 and Attch 5.pdf PDF
Amendment 0009.doc DOC document
95 ISA - 30Sep2010.pdf PDF
95 ID2 - 30Sep2010.pdf PDF
Amendment 0008.doc DOC document
Questions and answers 21 Oct 10.docx DOCX document
FA4809-10-R-0004 SJAFB NC Atch 5 Atch 2 Blank 3052.xls XLS spreadsheet
MACC SOW Revised pages 2 and 9.docx DOCX document
REV 10-10 SOW-Sample Project 35 .docx DOCX document
3803rooff.dwg DWG drawing
Tsaec.mln —
Telecommunications.dwt —
Tsaec_2_0.shx —
Architectural.dwt —
Survey.dwt —
Tsaec8-NJ.lin —
Structural.dwt —
3803elev.dwg DWG drawing
Civil.dwt —
SJAFB CADD Standards.pdf PDF
Tsaec_2_0.mln —
Electrical.dwt —
flyover.dwg DWG drawing
3803sect.dwg DWG drawing
Amendment 0007.rtf RTF text file
3803roofd.dwg DWG drawing
(CAD Standard 4_0) ERDC-ITL-TR-09-2.pdf PDF
G-1 COVERSHEET.dwt —
Bldg 3803 1st Floor.ppt PPT presentation
Tsaec_2_0.lin —
Tsaec.shx —
Fire Protection.dwt —
Plumbing.dwt —
Mechanical.dwt —
3803roofn.dwg DWG drawing
Tsaec32.lin —
Tsaec8.lin —
Bldg 3803 2nd floor.ppt PPT presentation
SJAFB wiring policy.doc DOC document
c1site.dwg DWG drawing
3803-1.dwg DWG drawing
Landscape.dwt —
3803-2.dwg DWG drawing
Tsaec4.lin —
border.dwg DWG drawing
Amendment 0006.rtf RTF text file
Amendment 0005.doc DOC document
Amendment 0004.doc DOC document
Show 40 more

Latest 50 of 233 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4809-10-R-0004

Attachment 1

STATEMENT OF WORK

FOR

VKAG 10-1200

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

SEYMOUR JOHNSON AFB

INDEX

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

1. Definitions

2. Description of Work

3. Contractor Operations

4. Commencement, Prosecution, and Completion of Work

5. Design Documents

a. Drawings

b. Specifications

c. Design Analysis

d. Perspective Drawing

6. Progress of Work

7. Material Approval Submittals

8. As-Built Drawings

9. Operation and Maintenance Manuals

10. Warranty of Construction

11. Program Management

12. Quality Control

13. Subcontracting Support Capability

14. Project Execution and Technical Support

15. Government Furnished Equipment / Materials

16. Government Equipment On Site

17. Disposal of Waste

18. Construction Site Maintenance

19. Work in Special Security Areas

20. Delays in Entering and Leaving Work Area

21. Safety and Health

22. Asbestos Requirements

23. Lead Based Paint Requirements

24. Precautions Against Hazards

25. Use of Tobacco Products in Air Force Facilities

26. Recording and Preserving Historical and Archeological Finds

Appendix A, Section 01000, General Appendix B, Section 01560, Environmental Protection Appendix C, Section 01560, Attachment: Summary for Contractors Appendix D, Section 16721, Fire Detection, Alarm, and Radio Type Reporting Systems Appendix E, SJAFB Architectural Compatibility Standards Appendix F, AF Form 66 Appendix G, Sheet G-1, Location Map

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

1. DEFINITIONS :

a. 35% Design - In general, documents which show the essential components of the proposed design and convey that the contractor fully understands the TO requirements and that his / her proposed price includes all required elements of work to complete the project. The documents will include the following minimum information, as applicable to the project; drawings, a list showing sections to be incorporated in the specifications, design analysis, and any other design components relating to the 35% design as identified in the Task Order. Major mechanical and electrical equipment items shall be shown on the drawings with single line diagrams. All utilities and structures shall be shown. Drawings shall also include the following, as applicable:

(1) All required controlling dimensions. Site plan showing proposed location of work including benchmarks, access from main roads, and surface or sub-surface drainage concepts.

(2) Floor plans with dimensions and functional arrangement of all areas; including corridors, exits, stairs, and utility spaces properly related to exterior access, roads, parking, and service areas, etc. Individual treatment shall be given items involving special design and/or deviations from accepted standards and of complex design. Gross floor areas shall be shown for each floor and for the entire building. Floor and roof framing, and loadings shall be indicated. Built-in, installed, and specialized portable equipment shall be indicated to scale. Pertinent information regarding fire prevention and safety requirements shall be shown. Design live and wind loads shall be shown.

(3) Elevations shall include story heights, fenestration, and adaptation to finished grades at the site.

(4) Sections of structures, including framing, partitions, suspended ceilings, (if any), ducts, etc., shall be shown.

(5) Typical wall sections shall be shown at a scale of no less than 3/4 inch = 1 foot. Sections shall include material and thicknesses, methods of attachment, and type of windows with relation thereof to supporting structural columns or walls.

(6) For heating, air conditioning, fire protection, mechanical ventilation and plumbing, and special features such as elevators, hoists, kitchen equipment, etc., indicate the location, capacity, and space requirements for all major items of mechanical equipment. Single line indication and riser diagrams of ducts, pipes, and equipment and their approximate location shall also be shown. Indication shall be made as to whether piping and duct work are exposed or concealed. Functional areas where pipes are exposed shall be delineated. Approximate operating range or capacity for heating, ventilation, air conditioning, and refrigeration equipment shall be clearly stated.

(7) For electrical systems, indicate lighting arrangements, type of fixtures proposed, general light intensities, special electrical requirements of the user, including communications and electronic facilities where applicable, fire alarm/mass notification devices, emergency lighting, light and power service entrance and distribution arrangement. Conduits, including those to be wired by others, shall be shown together with indication as to whether conduits are exposed. Functional areas having exposed conduits shall be delineated. Riser diagrams, showing service equipment, feeders, and panels, other than branch circuits, shall be shown. Cable sizes, current demand factors and the switch and panel board descriptions are not required at this time. Location capacity and space requirements of all major items of equipment shall be shown including interior substations with service equipment and panels. Power, communication, and electronic features will be indicated in sufficient detail to identify requirements clearly and to indicate the means of satisfying the requirements.

(8) Provide separate lists of all Government-furnished equipment to be installed by the contractor and equipment furnished and installed by the Government, if applicable.

b. 65% Design - Documents building upon the 35% design, including drawings and the complete text of the specifications. The drawings will show an additional 30 % progress in all disciplines which may include site plans, floor plans, elevations, wall sections, details, and all other elements as identified in the 35% design. All cut sections and details shall also be shown on the drawings at this time. Any updated or corrected design analyses of architectural, structural, civil, electric, mechanical, and utility systems shall be included. The contractor shall stop work until the Contracting Officer issues a Notice to Proceed to the next design milestone.

c. 95% Design - Documents building upon the prior design submittal. This will include, for review, final and complete drawings, and specifications. All project requirements identified in the most current TO revision, site visit minutes, modifications, or review comments must be incorporated. The Contractor shall stop work until the Contracting Officer issues a Notice to Proceed to the 100% design.

d. 100% Design - Documents building upon the prior design submittal which include final contractor accomplished corrections based on the Government's review of the prior design documents.

e. Task order (TO) – A document prepared by the government and issued to the contractor which contains the general requirements and parameters of the proposed project. Included in the TO is the Statement of Work defining specific technical requirements for the project. Also included is information such as budget limitations, type of solicitation, and design certifications and drawings required to be prepared by the contractor.

f. Statement of Work (SOW) – A document prepared by the government and issued to the contractor as part of the task order. Included in the SOW are the specific technical requirements for the project.

g. Invitation for Bid (IFB) – A package of documents issued to a contractor requesting a firm price for construction and the required design documents for a project based on the Task Order. Once submitted, no revisions to the bid are permitted. Award is made to the low bidder.

h. Request for Proposal (RFP) – A package of documents issued to the contractor requesting an itemized cost proposal for construction and design documents for a project based on the Task Order. Following submittal of the proposal and at the government’s option, discussions may be held with the contractor to clarify and / or negotiate elements of the proposal.

i. Professional Certification – The process of affixing a seal or statement to a drawing or design document to indicate that the work to which it is affixed has been performed by a person licensed as a professional, in that area of expertise, in the state of North Carolina.

j. Conventional Design-Build – The process by which the same contractor provides both the design and construction services for a project, completing the design before construction activity begins.

k. Fast Track Design-Build – The process by which the same contractor provides both the design and construction services for a project, beginning construction at a mutually agreed point prior to completion of the design and construction drawings.

l. Government Furnished Equipment (GFE) / Government Furnished Material (GFM) – Items of equipment or material which the government will supply to the contractor for use in the construction of a project.

m. Color Board – A visual presentation consisting of samples of the various finishes, grouped together based on location within the project. Samples shall be of adequate size to show the full pattern, texture, and color of each item.

n. Best Value – A process used to evaluate proposals based on the quality of the overall design in addition to the other criteria included in the request for proposal. When used, the “best value” evaluation factors will be included in the Task Order and may vary between projects. Award may be made to other than the low offeror.

(1) Evaluation Factors – Those components of a project design, as identified in the TO, which represent significant importance to the successful execution of the project, used to evaluate the overall quality of the proposed design.

(2) Strength – A substantive aspect, attribute, or specific item in the proposal that exceeds the TO requirements and enhances the probability of successful contract performance.

(3) Weakness – A flaw in the proposal that increases the risk of unsuccessful contract performance.

(4) Deficiency – A material failure of a proposal to meet the TO requirements or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.

(5) Rating – The application of a scale of words, used in conjunction with narrative, to denote the degree to which the proposal has met the requirements established by the TO.

o. Design Costs – Those costs identified by the contractor, on the Bid Schedule and / or AF Form 3052, as part of the RFP process which represent the portion of the overall project cost attributed to preparation of the design and construction documents (level of design to be determined per TO).

p. Investigative Costs – Those costs identified by the contractor, on the Bid Schedule and / or AF Form 3052, as part of the RFP process which represents the portion of the overall project cost attributed to all investigative services necessary to prepare the design and construction documents (level of design to be determined per TO).

q. Investigative Services – For exterior work / new facilities, the investigative services will typically include performing a survey of the project site including topography, cross sections, drainage survey, and bench level circuit. In addition, it may include verification and documentation of the location and size of all existing utilities and pertinent surface features for inclusion on the topographic survey map. For interior work, the investigative services will typically include verification of all existing conditions affecting the design and execution of the work as described in the TO.

r. Designer of Record (DOR) - The individual accountable for specific portions of the design documents. Where professional certification is required for the design, the DOR would be the individual providing certification for that portion of the design. Where professional certification is not required, the DOR would typically be the individual who provided the design or specifications for a particular aspect of the project (i.e.: architectural, civil, structural, mechanical or electrical).

2. DESCRIPTION OF WORK:

a. Contract Scope:

The MACC will be utilized to execute a broad range of maintenance, repair and minor construction projects on real property at Seymour Johnson AFB, North Carolina to include Dare County Bombing Range which is located approximately 200 miles to the northeast of Seymour Johnson AFB proper and Fort Fisher Recreational Area located approximately 100 miles to the south of Seymour Johnson AFB proper. The projects will include tasks in a variety of trades such as demolition, site work, excavation, cast-in-place concrete, masonry, structural steel, fire protection, electrical, mechanical (including HVAC), painting, millwork, and other specialty and general contracting work.

b. Bid / Proposal Preparation

An Invitation for Bid (IFB) or Request for Proposal (RFP) issued under this contract may be issued to more than one contractor and will include a Task Order (TO) defining the project requirements. The project may ultimately require the contractor to produce a full design, partial design, or no design depending on the level of design already available and provided to the contractor in the TO. For example, a new project with no, or partial, previous design accomplished may include requirements to provide a 35% (minimum) design as part of the contractor’s proposal. Conversely, a project for which a 100% design is already available will only require a bid in the prescribed format. If awarded a Task Order (TO) for the project, the successful contractor will, as necessary, complete the design to the 100% level. This will include participating in design reviews, conducted at Seymour Johnson AFB, at each design milestone (35%, 65%, etc) described in the TO. For IFB's, the bid will be submitted on the bid schedule provided by the Government. Cost proposals for RFP's will include a bid schedule and, when required by the Task Order, a construction cost estimate breakdown (AF Form 3052). (To facilitate discussions prior to award, the government may also require submission of an AF Form 3052 after initial proposals are submitted even though the AF Form 3052 was not initially required by the Task Order.) The bid schedule as well as the line item categories to be used on the AF Form 3052 may be provided, to the contractor, by the Government. In addition, the TO may also include but is not limited to, the following, as applicable, based on the level of design required

(1)Government prepared Statement of Work (SOW), sketches, and any available as-builts, specifications, or design information.
(2)Design calculations requirements.
(3)Construction drawings requirements including professional certifications.
(4)Direction regarding fast-track vs. design-build.
(5)Timeframes for preparing the proposal, completing design work (if awarded), and completing construction.
(6)Contractor prepared specification sections and version required
(7)Submittal requirements
(8)Government Furnished Materials (GFM) or Government Furnished Equipment (GFE)

c. Bid / Proposal Evaluation Criteria:

Bids received in the IFB format will be evaluated based on compliance with the TO requirements and the proposed price. Proposals received in the RFP format will be evaluated based on compliance with the TO requirements and the proposed price. In addition, at the government’s discretion, price – performance tradeoff (PPT) and “best value” criteria when described in the TO may also be incorporated into the evaluation process. The TO will indicate the minimum requirements which must be met in order for a proposal to be considered technically acceptable. The government reserves the right to enter into discussions with responsive contractors (those submitting technically acceptable proposals) for the purpose of requesting minor revisions to the proposals. Any proposal which does not address all requirements set forth in the TO will be determined to be technically unacceptable.

d. Access to Work Areas:

The contractor may be required to work within controlled or restricted areas. Refer to paragraphs 19 and 20 and Specification Section 01000 for additional information concerning security.

e. Unfunded Projects:

Occasionally, the government will have a need to establish a final price for a project which is not already funded but for which there is a reasonable expectation that funding will be received in the future. In that case, an RFP will be issued to a single contractor for preparation of a 35% design (if not already designed) and a cost proposal. The 35% design fee (not to exceed an appropriate portion of the 6% statutory limit for a 100% design) shall be negotiated for those projects not already designed. The contractor must provide an acceptance period of 120 calendar days following establishment of a final price. If the project is awarded prior to expiration of the 120 calendar day acceptance period, the contractor will be issued a task order to complete design work as needed and accomplish the construction. If the project is not awarded within the 120 day acceptance period following the establishment of a final price, the contractor will be paid the negotiated 35% design fee.

3. CONTRACTOR OPERATIONS: The Contractor shall conduct all operations in accordance with the Seymour Johnson AFB Specification Section 01000 found in Appendix A.

4. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: The contractor shall commence work and complete the project in accordance with the time frames established in the Task Order (TO) and Notice to Proceed (NTP).

5. DESIGN DOCUMENTS, GENERAL: The design documents developed by the contractor shall comply with the following requirements:

a. Drawings:

(1) The contractor shall receive one copy of the appropriate record drawings (electronic only) if available, with the TO. Record drawings will be available to the contractor for their reproduction. The Government does not guarantee the accuracy or adequacy of the existing as-built drawings. It is the Contractor’s responsibility to field-verify all as-built drawings during preliminary site visits, planning of the project, and prior to issuance of each DO. Contractor shall be responsible for the reproduction of these drawings as needed.

(2) The TO will identify the sizes of drawings, either Standard D (24” x 36”) or Standard B (11” x 17”), to be submitted with the proposal and each subsequent review milestone (65%, 95%, and 100%). The contractor shall supply all contract drawings prepared using the latest release of AutoCAD software (Release 2006 or higher), however, save all drawings in a AutoCAD 2004 format. Line quality shall not be half-toned or gray scaled below 75%. Drawings produced using another software package will be acceptable provided all drawings are converted to standard AutoCAD drawing file format prior to receipt by the Government and comply with the SJAFB CADD standard and U.S. Army Corps of Engineers Cadd STD 4.0 dated July 2009. SJAFB CADD standards manual will be provided upon request by the drafting section. In addition, the A-E shall comply with the following standards:

a. Drawing files shall be delivered in the standard AutoCAD “.dwg” file format for AutoCAD 2004 version. “Model space” shall be the preferred method for drafting all drawing items such as floorplans, sections, details…. Dimensions, leaders, and notes… specific to the drafted item shall accompany the object drawn in “Model Space” and be scaled accordingly to appear in paper space at the correct text height as specified. Only general notes applicable to the entire drawing shall be in paperspace. Drawing units shall be set according to the requirements for the drawing discipline, i.e. civil drawings units shall be set to the decimal format, and architectural drawings set to the architectural format. Civil site plans shall be in North Carolina State Plane (NAD 83 and NADV88) with all site plans oriented with north at the top of the sheet. Any Reorientation of a view for drafting convenience shall be done within the viewport using the “Dview and Twist commands, objects in model space shall not be rotated. The A-E shall supply a written explanation as to how externally referenced drawings are used, view-port scales/settings, viewport layer settings, blocks and any other relevant information necessary for the Drafting Section of Seymour Johnson to make changes or updates to the drawings. The A-E must also be available for phone assistance to clarify any other problems encountered by the Drafting Section. “Paperspace” shall be used to format the final plotted drawing sheet. Standard plotted paper size shall be the “D” size sheet unless otherwise specified. All drawings shall use the standard Seymour Johnson AFB project title block. Title block shall not be altered by the contractor. Title block template files shall not be modified as attributes within the title block are used by other drawing management tools. SJAFB Drawing templates will be made available for each discipline by SJAFB drafting section.

b. All drawings shall be submitted on CD-ROM / DVD-ROM, If CD-ROM’s are delivered at various stages of the project, they shall be labeled accordingly, i.e. 65% review, 100% for construction, or AS-Built.

c. All External Referenced (XREF) drawings will have an “xref_” at the start of the file name (i.e. xref_base.dwg). Xref drawings shall be located and linked correctly as to ensure the xref will load with The A-E shall not layer / nest xref drawings. Multiple xref drawings shall be allowed, but, not nested xref’s Each drawing file will contain only one drawing. If a drawing has an XREF drawing, the XREF shall also be a separate drawing. Xref drawings shall not contain other xref drawings i.e. nested externally referenced drawings. The A-E shall provide complete typewritten instructions for reintegrating the drawings, and must specify which XREF goes with which drawing. Contractor shall use the both the “Drawing Sheet Set” function of AutoCAD and the “E-Transmit” function of AutoCAD to package all drawing sets for delivery.

d. The A-E shall utilize Aerial text. Text shall be 1/8” in height for all normal text, and ¼” in height for headings such as, “DETAILS, SECTIONS, PLANS etc…”. Only text fonts / styles native to the basic AutoCAD package shall be used. No unique or fonts developed by the A&E, or design firm shall be used.

e. The A-E shall be provided a copy of layered standard utilized by the SJAFB Drafting Section upon request. Layer standards are those utilized by the CADD/GIS Technology Center (U.S. Army Corps of Engineers Cadd STD 4.0 dated July 2009, which is based on the NIBS National Cadd Standard v 4.0), standards are found at their web site: https://cadbim.usace.army.mil/CAD. All layers shall have narrative descriptions easily identified (i.e., walls, elec., etc.) Dimensions and annotations shall be placed only in model space. The color yellow shall not be used for any annotation, notes or dimensions.

f. Use of third party development software is acceptable provided all final drawing files submitted are native AutoCAD format. Any features peculiar to the development software used, such as shape files, menus, blocks, etc. that are not accessible using the basic AutoCAD package are not acceptable and shall be modified to ensure the drawing files may be easily edited or changed by government personnel using the basic AutoCAD software package.

g. Final AutoCAD drawing files should exhibit good drafting practice allowing for each change and minimal storage requirements. Drawings should make use of features to limit drawing size/complexity wherever possible. Over-detailing (drawing features that are not discernible at full or half scale reproduction) is not acceptable and must be avoided. All detail notes, leaders and dimensions must be legible when reproduced at half scale.

h. Drawings shall have no more than one layout tab. Layout tab shall have the same name as the sheet name.

i. Final drawings shall be submitted with a complete hard copy list of drawing file names, layers used, etc. project number and list of drawings on each disk will be written on the label affixed to the disk. Drawing file name shall be in accordance with SJAFB standards and shall appear in the appropriate section of the title block as directed by the SJAFB drafting personnel. SJFAB Title blocks shall not be modified by the contractor as attributes embeded in the title blocks are extracted for use in SJAFB CADD digital vault database. Contractor shall use both the “Drawing Sheet Set” functionality of AutoCAD and the “E-Transmit” function of AutoCAD to package all drawing sets for delivery. This ensures that all blocks, externally referenced files are packaged with the drawing set.

j. Final CAD and PDF format drawings shall be included with the final project CD in separate folders.

k. All contract drawings to be furnished shall be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely type and extent of work to be performed. The A-E shall ensure drawings, specifically any shading or hatching, are reproducible on the Base Engineer’s Xerox 510 printer. All drawings shall be drawn to appropriate scales and dimensioned completely and accurately and shall be legible at when drawings are reproduced at ½ size. Extensive explanatory notes on the drawings are undesirable and should be placed in the specifications. The use of fractions less than 1/8” for building dimensions will be avoided. Standard building material indications and symbols for civil items and for electrical equipment shall be used to the greatest extent possible.

(3) The Contractor shall submit three (3) sets of Standard D or B size drawings (or as otherwise required by the TO) to the Contracting Officer with his / her proposal. Once awarded the TO for a specific project, the successful contractor shall provide a minimum of four (4) complete sets of drawings, (or as otherwise required by the TO), in the same size and format, with each intermediate and final design submittal. Also, unless otherwise stated in the TO, one set of Standard B drawings shall be provided with the 100% submittal. Throughout the design process, each submittal shall be clearly identified as to the level of completion (i.e.: 35% etc.). The “revisions” blocks on the plan sheets shall not be utilized to document changes to the drawings until after the 100% design is completed and accepted by the government.

(4) The Contractor shall prepare drawings, as specified in the TO, for Government approval prior to the start of construction. The drawings developed by the contractor beyond the 35% point shall conform to industry standards relating to good design and drafting practices. All completed drawings shall clearly identify the work being performed under the DO. Unless otherwise identified in the TO, use of existing drawings provided by the government will be allowed provided they are modified by the contractor to accurately reflect the project requirements. Each sheet shall have an approved title block and border with professional certification when required by the TO. The title block shall contain project information including but not limited to Project #, TO #, Project Name, and submitted date. Basic design criteria utilized for each discipline will be included on the appropriate drawings as required by the TO. Examples would include wind and live/dead loads assumed for structural elements, function specific conditions such as lighting levels or future use considerations for electrical systems, site specific climatic design conditions for mechanical systems, and International Building Code analysis (performed to the same level as if being applied to a building permit process). The following is a list of drawings which might typically be required under this contract:

(a)Cover Sheet with Title and Approval Block (showing haul route). See Appendix G for sample.
(b)Existing Site Plan
(c)Final Site Plan
(d)Grading Plan
(e)Underground Utility Plan and Profiles
(f)Demolition Plan
(g)Floor Plans
(h)Elevations
(i)Finish Schedule
(j)Wall and Roof Sections
(k)Window and Door/Hardware Schedules
(l)Ceiling Plan
(m)Details
(n)Structural Plans, Schedules, and Details
(o)Mechanical Plan and Schedules
(p)Plumbing and HVAC Riser Diagrams
(q)HVAC Controls Diagrams
(r)Electrical Site Plan
(s)Power Plan and Panel Schedule
(t)Electrical Plan and Lighting Plan with Schedule and details
(u)Fire Protection Plan
(v)Communications Plan
(w)Landscape Plan

b. Specifications:

(1) For projects not previously designed, the technical specifications to be utilized by the contractor shall be Masterspec, Short Form or Long Form versions. In the TO, the contractor will identify the specification sections, which represent major elements of work and, as a minimum, are to be included in the project. Three (3) sets (or as otherwise required by the TO) of the specifications index for those sections, as well as other specification sections appropriate to the anticipated work and added by the contractor, shall be included in the 35% design submitted with the contractor’s proposal. The TO will also identify whether the Long Form or Short Form version of Masterspec is to be used. Once awarded the TO for a specific project, the successful contractor shall electronically edit the specification sections, previously identified, to correspond with the work proposed in the project. A minimum of four (4) sets of edited specifications (or as otherwise required by the TO) shall be provided with each intermediate and final design submittal.

(2) In addition to the technical specifications described above, the latest version of the following references is to be utilized in the preparation of project designs;

Seymour Johnson AFB Architectural Design Standards (Appendix E) American Society of Testing and Materials (ASTM) Standards American National Standards Institute (ANSI) Standards National Fire Protection Code (NFPA), with particulate attention paid to:

NFPA 101, Life Safety Code
NFPA 70, National Electrical Code (NEC)
NFPA 72, National Fire Alarm and Signaling Code

Unified Facilities Criteria (UFC), ALL that apply with particulate attention paid to:

UFC 3-600-01, Fire Protection Engineering For Facilities
UFC 4-010-01, DoD Minimum Antiterrorism Standards For Buildings
UFC 4-021-01, Design and O&M: Mass Notification Systems
UFC 3-420-01, Plumbing Systems
UFC 3-530-01, Design: Interior, Exterior Lighting and Controls
UFC 3-230-01, Interior Electrical Systems
UFC 3-550-01, Exterior Electrical Power Distribution

Air Force Instructions, Handbooks, Manuals, etc; ALL that apply International Building Code & NC State Building Code ANSI C-2, National Electrical Safety Code (NESC) ANSI/ASCE 7-95, Minimum Design Loads for Buildings and Other Structures

As well as any applicable manufacturer or industry specifications or recommendations associated with material, supplies, or systems. If a discrepancy exists between these documents, the contractor shall bring this to the attention of the Contracting Officer and shall utilize the most stringent requirement(s) in the preparation of the project design.

During the design period of a project, there will be a Statement of Work along with all the applicable UFCs and various codes as well as Base Architectural Standards. If there is ever an ambiguity, the building codes, Architectural Standards and UFCs will take precedent over the SOW.

(3) A copy of the Architectural Compatibility Standards – Seymour Johnson Air Force Base is included in Appendix E.

(4) Specification Section 01000, Seymour Johnson AFB, shall be edited for all projects, by the contractor, to correspond to the project requirements. This specification and a copy of Specification Section 01560, Environmental Protection shall be included in the contractor prepared specification package for every project. Copies of both these sections are included in Appendix A & B.

(5) The bottom of each page shall have the following relative information indicated in the format noted:

Project Number Section Number Page Number of the Section

When the last page of a section is encountered, the following shall be noted (centered) after the last paragraph:

END OF SECTION

(6) The use or specification of materials not made in the United States is prohibited. Only American made products shall be used in this project.

(7) Submittal Schedule: Required submittals shall be listed on an AF Form 66, ensuring all items requiring submittals are annotated. Normally, three (3) copies of printed matter and one (1) material sample are required. Reference each submittal item on the form to the specification section and paragraph. Consecutively number each page of the submittal, e.g. “Page 1 of 1”. Use all line number rows on one page before starting another. Number all submittals consecutively beginning with “1” for each project. A copy of a sample AF Form 66 is included in Appendix F.

c.. Design Analysis

(1) As specified in the TO, design calculations may be required, to include code references, as applicable for each discipline, to show compliance. Three (3) sets of these calculations shall be provided by the contractor and included with each required design submittal. The following is a list of calculations which might typically be required under this contract

(2) Civil/Site work:

(a) Sizing and grades for sanitary & storm sewers

(b) Sizing for water mains & services

(c) Sizing for gas mains & services

(3) Structural

(a) Foundation and reinforcing sizes

(b) Superstructure framing

(c) Wind & snow loading analysis

(d) LL & DL calculations

(e) Wall sizes and reinforcing

(f) Equipment supports

(g) Elevated platforms

(h) Floor member sizing / reinforcing

(i) Lintel sizing

(j) Sizing for roof joists & decking

(4) Mechanical:

(a) Cooling and heating load analysis.

(b) Pump sizing and pump curves.

(c) Pipe sizing.

(d) Duct size.

(e) Static pressure loss.

(f) Control valve sizing.

(g) Psychometric chart analysis.

(h) Fan sizing and fan curves.

(i) Heat exchanger selection.

(j) DDC Control Single Line

(5) Electrical:

(a) Load calculations

(b) Short circuit calculations

(c) Lighting level calculations

(d) Branch circuit calculations

(e) Motor feed requirements

(f) Panel sizing

(6) Fire Protection: Sprinkler layout and pipe sizing

(7) Others as applicable to a specific project and identified in the TO.

d. Perspective Drawing:

(1) When required by the TO, the contractor shall prepare a black line concept perspective and/or a rendered (color) perspective of the project. (May be computer or hand generated.)

(2) The final colored rendering (if required) shall be approximately 19” x 28” frame size and shall include frame, 3” matting, non-glare glass, and hanging hardware.

(3) The black-line concept perspective shall be provided with the contractor’s bid/proposal as part of the 35% submittal if required. The rendered perspective shall be prepared by the successful contractor and delivered with the final design submittal when requested.

6. PROGRESS OF WORK:

Once awarded Notice to Proceed for Construction, the successful contractor shall submit for approval all work schedules to the Contracting Officer within ten calendar days after start of work unless otherwise specified. The reports contemplated by the clause titled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. This requirement is applicable to a TO with a minimum performance period of 60 calendar days and a minimum dollar value of $100K, unless otherwise specified by Contracting Officer.

7. MATERIAL APPROVAL SUBMITTALS

a. Technical Data, Samples, and Color Boards:

All equipment, products, material, and articles requiring approval, as indicated on the AF Form 66, shall be submitted by the contractor using AF Form 3000. All wall covering, carpet and other fabric type submittals will show the full pattern of material as a minimum. When required by the TO, all applicable product samples shall be submitted on a color board grouped to correspond with the anticipated installation. i.e.: floor covering, paint, paneling, chair-rail, wall covering and ceiling tile. The contractor shall include technical data with the products presented on the color board so that the items may be approved for technical compliance as well as architectural compatibility. Contractor is responsible for identifying and locating required materials for submittals to include matching any existing materials.

b. Designer of Record Approval:

When required by the TO, the DOR shall review and approve equipment, product, or material submittals and indicate compliance with the design documents prior to the submittal being forwarded to the government for review. Those submittals requiring DOR approval shall be included on the AF Form 66. (Re: Paragraph 5.b.(7) above)

8. AS-BUILT DOCUMENTS:

a. Drawings:

During the progress of the work, the contractor shall keep a careful record at the job site of all changes and deviations to the layouts shown on the drawings. The contractor shall manually enter such changes and corrections on record drawings promptly. If the project was designed by the government, submittal and approval of the “red-line” as-builts and GPS data referenced below, at the project’s conclusion, completes the contractor’s responsibility for this item. If the project was designed by the contractor, he/she shall provide the Government with a draft of the as-built drawings in Standard D size, on paper for review at the project’s conclusion. Following government approval of the draft, the contractor shall submit the GPS data referenced below and the final as-built drawings; one (1) copy of Standard D (24” x 36”) size drawings on Mylar and a CD ROM containing the Auto CAD 2004 (or higher) as-built drawings. The drawings shall indicate, in addition to all changes and corrections, the actual location of all subsurface utility lines.

b. GPS Data:

The contractor shall furnish survey data showing the horizontal/vertical location of all site improvements constructed under the Task Order to include, but not limited to, topography, buildings, pavements, utilities, and all similar construction. Site improvements such as buried utility lines require one survey shot every 50’ of straight line, at each turn or bend in the line, hydrants, fittings, valves, valve boxes, curb stops, relocations and crossings of existing utilities, structures, or other appurtenances relocated or affected by the construction. Also provide elevations for the topmost point of visible appurtenances such as fire hydrants and valve boxes, and provide rim and invert elevations for all manholes in the project area. The contractor shall use conventional surveying methods such as total stations, automatic levels, or Global Positioning System (GPS) for field data collection at an accuracy of +/-2cm. A copy of all survey data deliverables shall be a submittal item. All survey work shall be tie to existing grid through use of on base monuments as published by National Geodetic Survey (NGS) NAD 83, NADV 88. Assumed elevations with temporary benchmarks will not be acceptable. Survey deliverables include field notes, field book data, and/or data collector files compatable with Trimble software. Drawing data shall delivered in an AutoCAD format (NC State Plane, units set to unitless, one AutoCAD drawing unit = 1.0’, decimal unit format), and ESRI geodatabase must have an external spatial reference (.prj) file attached that specifies the parameters of the coordinate system in standard ERSI format. All electronic data deliverables shall be a CD-ROM in format that conforms to the latest version of both the CADD/GIS Technology Center’s Spatial Data Standards and A/E/C CAD Standards. These standards can be found at:

https://cadbim.usace.army.mil/CAD https://cadbim.usace.army.mil/GIS

All AutoCAD files shall conform to the SJAFB Cadd standards and USACE CADD Standards v 4.0. AutoCAD survey drawings layering conventions shall conform to USACE CADD standard for the “V” survey drawings.

9. OPERATION AND MAINTENANCE MANUALS:

For those projects which include mechanical / electrical / fire protection/specialty systems requiring periodic or routine maintenance, the contractor shall prepare and submit operation and maintenance manuals in three (3), bound, hard copies as well as one (1) electronic copy on CD ROM. As a minimum, the manuals shall contain technical data, diagrams, parts listings, maintenance instructions, and the name, address, and phone number of the manufacturer and servicing / replacement parts source. These manuals shall be submitted prior to the final inspection and in accordance with paragraph 7 above.

10. WARRANTY OF CONSTRUCTION:

a. Listing of Warranty Items:

The contractor shall prepare a listing of all equipment or material subject to a manufacturer’s warranty or extended warranty as required by the TO. The listing shall include a description of the item, the expiration date of the warranty, and the point of contact for warranty service. Three (3) copies of this information shall be submitted in hard copy and one (1) copy in electronic format (CD ROM) as a project submittal in accordance with paragraph 7.

b. Scope of Coverage:

In addition to any other warranties in this contract, the contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material or design furnished, or workmanship performed by the contractor or any subcontractor or supplier at any tier. This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes or fraud.

c. Period Of Coverage:

This warranty shall continue for a period of one (1) year from the date of final acceptance of the work, unless otherwise specified in the individual TO. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of one year from the date of beneficial occupancy. In the event the contractor’s warranty of this clause has expired, the Government may bring suit, at its expense, to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.

d. Remedies of Defects:

The contractor shall remedy, at the contractor’s expense, any failure to conform to contract requirements or any equipment/material/workmanship defect. In addition, the contractor shall remedy, at the contractor’s expense, any damage to Government-owned or controlled real or personal property when that damage is the result of:

(1) The contractor’s failure to conform to contract requirements or

(2) Any defect of equipment, material, workmanship, or design furnished.

The contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The contractor’s warranty with respect to work repaired or replaced will run for one year from the date of repair or replacement.

e. Notification to Contractor:

The Contracting Officer shall notify the contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. If the contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the contractor’s expense.

f. Subcontractor and Supplier Warranties:

With respect to all warranties, express or implied, from subcontractors, manufacturers or suppliers for work performed and materials furnished under this contract, the contractor shall:

(1) Obtain all warranties that would be given in normal commercial practice

(2) Require all warranties to be executed, in writing, for the benefit of the Government if directed by the Contracting Officer, and

(3) Enforce all warranties for the benefit of the Government if directed by the Contracting Officer. Emergency warranty calls shall not exceed a 4-hour response time, while routine warranty response time shall not exceed 3 workdays. The warranty enumerated herein does not preclude any manufacturer warranties in excess of one year as noted in the individual specifications sections. The contractor should read each section carefully to ensure that he/she is aware of all warranties called for in each project.

g. GFE / GFM:

Unless a defect is caused by the negligence of the contractor, subcontractor, or supplier at any tier, the contractor shall not be liable for the repair of any defects of material or design furnished by the Government or the repair of any damage that results from any defect in Government-furnished material or design.

11. PROGRAM MANAGEMENT:

Contractor shall provide a program manager and staff for executing TO’s awarded under this contract. The program management staff shall have project design, quality control, and construction and financial management capability. The program manager shall have a minimum of 5 years experience in that capacity and shall have the authority to negotiate delivery orders and modifications thereto and obligate the company to TO’s. The program manager shall have the authority to hire / fire subcontractors and must be experienced in subcontract management. The program manager must be available via local phone service throughout the duration of all ongoing TO’s and his / her phone number shall be provided to the government immediately following award of any TO.

12. QUALITY CONTROL PLAN:

Contractor’s Quality Control Plan shall be developed and submitted to the contracting officer within 10 calendar days after Notice to Proceed is issued for acceptance to ensure that work is accomplished and all problems are documented and resolved in accordance with the specifications and drawings. The contractor shall designate on-staff personnel as project superintendents to document and resolve all quality control problems and accomplish daily quality control inspections. The contractor shall establish a method to identify poor performance and specify appropriate corrective action. The quality control plan will become a compliance document. Project personnel will interface with Government personnel to ensure that the quality control plan functions properly.

13. SUBCONTRACTING SUPPORT CAPABILITY:

Contractor shall provide subcontractor management including surveillance, quality control, and scheduling. Subcontractors must be available to ensure quick response times. The contractor must have the ability to manage and control multiple subcontracts at multiple job locations. The contractor must ensure subcontractors are competent and capable of handling all tasks assigned to them and shall ensure that each subcontractor is not assigned more work than they can accomplish satisfactorily.

14. PROJECT EXECUTION AND TECHNICAL CAPABILITY:

Contractor shall have a support staff that includes clerical, quality control, project superintendent, drafting and design personnel as necessary to prepare bids/proposals and execute the construction phase of all TOs.

15. GOVERNMENT FURNISHED EQUIPMENT/MATERIALS:

The Government reserves the right to provide Government furnished equipment/materials (GFE/GFM) that is on hand if it can be used by the contractor to complete a TO. The GFE/GFM shall be transported by the Contractor, from the Government storage area, to the work site indicated on the TO. The contractor assumes the risk and responsibility for the loss or damage to GFE/GFM once the contractor receives possession of the GFE/GFM. The contractor shall follow the instructions of the Contracting Officer or his/her representative regarding the disposition of all GFE/GFM not consumed in performance of a delivery order.

16. GOVERNMENT EQUIPMENT ON THE SITE:

All government equipment and material on each project is the property of the Government unless specifically noted otherwise. Contractor shall relocate all property that the Government retains title to on the installation as specified in the TO or follow the instructions of the Contracting Officer or his/her representative. Contractor is required to cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss and store equipment that is removed in performance of work where directed or reuse in work as required by drawings and specifications. Equipment temporarily removed shall be protected and returned equal to its condition prior to starting work at no additional expense to the Government. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the contractor.

17. DISPOSAL OF WASTE:

Loose debris on trucks leaving the site shall be loaded in a manner that will prevent spillage from the vehicle. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The contractor shall be responsible for cleaning up any materials that fall from trucks and held liable for any resulting damages. Contractor shall submit, upon request, all trip tickets from the landfill facility to show all debris is being disposed of in accordance with all Federal requirements and in an approved location.

18. CONSTRUCTION SITE MAINTENANCE:

Contractor shall store all supplies and equipment on project site so as to preclude theft or damage. Maintain site in a neat and orderly manner at all times. Protection and security for materials and equipment on site is the sole responsibility of the contractor. The contractor may be required to install temporary fencing to protect the site as indicated in the TO.

19. WORK IN SPECIAL SECURITY AREAS:

Government shall provide all escorts required for contractor access to restricted/controlled areas, while working on construction projects at Seymour Johnson AFB.

20. DELAYS IN ENTERING AND LEAVING WORK AREA:

If…