J. Atch 8 - Project History.doc

DOC document 26 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER) VIII Federal contract opportunity
Solicitation number
FA4809-10-R-0001
Issued by
Department of the Air Force Air Combat Command

About this file

Attachment 8 Revised Project History 17 May 2010

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition of Base Engineering Requirements (SABER) VIII, newest first.
File Type Posted
Amendment 0005 correcting Amendment 0004.pdf PDF
Additional Questions and Answers 17 May 2010.docx DOCX document
Section J.dot DOT file
Attachment 9 Architectural Compatability 18 Dec 2003.pdf PDF
Amendment 0004.rtf RTF text file
Amendment 0003.pdf PDF
Site Visit Minutes with Attachments.pdf PDF
Amend 02 SABER VIII.doc.pdf PDF
SABER VIII Offeror Questions.doc DOC document
Amendment 0001 SABER VIII.doc DOC document
I. Atch 7 - AF FORM 66.XLS XLS spreadsheet
F. Atch 4 - Deter. of Ktr. Respons..doc DOC document
A. Cover Sheet and Instructions for RFP IFB.doc DOC document
D. Atch 2 - 10 WDs Consolidated.docx DOCX document
G. Atch 5 - Demonstration Project.pdf PDF
J. Atch 8 - Project History.doc DOC document
E. Atch 3 - Past Performance Questionnaire w Cvr Ltr.doc DOC document
H. Atch 6 - Location Plan SABER VIII.pdf PDF
B. Solicitation No. FA4809-10-R-0001 SABER VIII.rtf RTF text file
C. Atch 1 - Environmental Protection Specs.doc DOC document
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4809-10-R-0001

Attachment 8

ATTACHMENT 8

TASK MAGNITUDE PROJECT HISTORY

(REVISED 17 May 2010)

The following information is provided for use in developing pricing for CLINs 0001AH, 0001AJ, 0001AK, 0002AH, 0002AJ, 0002AK, 0003AH, 0003AJ, 0003AK, 0004AH, 0004AJ, 0004AK, 0005AH, 0005AJ, 0005AK.

Task Magnitudes:

Low = Less than $25,000

Medium = Between $25,000 and $100,000

High = Between $100,001 and $5,000,000

Project history for the past three years on all SABER projects at Seymour Johnson AFB:

Number of Projects Total Dollar Amt

Average Project Cost

Low

$225,191

$13,247

Medium

$2,450,693

$54,460

High

$33,875,368

$483,934

Project Estimating Only

$109,150

$2,872 The following notes apply to CLINs 0001AH, 0001AJ, 0001AK, 0002AH, 0002AJ, 0002AK, 0003AH, 0003AJ, 0003AK, 0004AH, 0004AJ, 0004AK, 0005AH, 0005AJ, 0005AK:

· NOTE 1: The contractor will provide whole dollar proposals as the lump sum total price based on his/her tasked actual cost, overhead, profit.

· NOTE 2: For low thru high magnitude, design proposal cost will be firm fix priced.

· NOTE 3: The purpose of paying for the design and negotiation effort of a project is to temporarily reimburse the contractor for his effort. Barring extenuating circumstances the government intends to award the construction of the designed and negotiated delivery order. Subsequently, if the project is awarded for construction the contractor will be paid the negotiated amount for actual construction minus the project design fee already paid to the contractor after negotiation.

Revised, Amendment 0004

Dated 17 May 2010

File details come from the government source that posted it. Updated .