J. Atch 8 - Project History.doc
DOC document 26 KB Posted
- Attached to
- Simplified Acquisition of Base Engineering Requirements (SABER) VIII Federal contract opportunity
- Solicitation number
- FA4809-10-R-0001
About this file
Attachment 8 - Project History
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4809-10-R-0001
Attachment 8
ATTACHMENT 8
TASK MAGNITUDE PROJECT HISTORY
The following information is provided for use in developing pricing for CLINs 0001AH, 0001AJ, 0001AK, 0002AH, 0002AJ, 0002AK, 0003AH, 0003AJ, 0003AK, 0004AH, 0004AJ, 0004AK, 0005AH, 0005AJ, 0005AK.
Task Magnitudes:
Low = Less than $25,000
Medium = Between $25,000 and $100,000
High = Between $100,001 and $5,000,000
Project history for the past three years on all SABER projects at Seymour Johnson AFB:
Number of Projects Total Dollar Amt
Average Project Cost
Low
$379,524
$14,597
Medium
$4,261,674
$52,613
High
$22,138,375
$368,973
Project Estimating Only
$60,800
$2,171
The following notes apply to CLINs 0001AH, 0001AJ, 0001AK, 0002AH, 0002AJ, 0002AK, 0003AH, 0003AJ, 0003AK, 0004AH, 0004AJ, 0004AK, 0005AH, 0005AJ, 0005AK:
· NOTE 1: The contractor will provide whole dollar proposals as the lump sum total price based on his/her tasked actual cost, overhead, profit.
· NOTE 2: For low thru high magnitude, design proposal cost will be firm fix priced.
· NOTE 3: The purpose of paying for the design and negotiation effort of a project is to temporarily reimburse the contractor for his effort. Barring extenuating circumstances the government intends to award the construction of the designed and negotiated delivery order. Subsequently, if the project is awarded for construction the contractor will be paid the negotiated amount for actual construction minus the project design fee already paid to the contractor after negotiation.