| File | Type | Posted |
|---|---|---|
| Amendment_05.pdf | ||
| Attachment_5_Blank_Cost_Spreadsheet_(Revision_03).xls | XLS spreadsheet | |
| FA4803-18-B-0001_-_Amendment_4_-_Maintain_Airfield_&_Striping.pdf | ||
| Attachment_5_Blank_Cost_Spreadsheet_(Revision_02).xls | XLS spreadsheet | |
| Attachment_5_Blank_Cost_Spreadsheet_(Revision_01).xls | XLS spreadsheet | |
| Attachment_9_Questions_&_Answers_Vol_02.docx | DOCX document | |
| Amendment_03.pdf | ||
| FA4803-18-B-0001-0002.pdf | ||
| Attachment_8_Questions_&_Answers.docx | DOCX document | |
| Attachment_7_CONTRACTOR__EAL_Base_Pass_Request.docx | DOCX document | |
| FA4803-18-B-0001-0001_Amendment_01.pdf | ||
| Attachment_2_Shaw_AFB_Design_Constr_23_Mar.pdf | ||
| Attachment_6_Flight_Line_Drawings.pdf | ||
| FA4803-18-B-0001.pdf | ||
| Attachment_1_Statement_of_Work.pdf | ||
| Attachment_3_Shaw_AFB_ID2_Handbook--October_201.pdf | ||
| Attachment_4_Wage_Determination.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VSLB 18-0003
| Exihibit A | |||||
| Contract: TBD | |||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||
| For VLSB18-0003 Maintain Airfield and Base Stripping | |||||
| Option Year | Government | ||||
| CLIN | Description | ||||
| 0001 | U/I | PRICE | Total | ||
| SITE WORK/GENERAL TASK | |||||
| AA | Mobilization | EA | $0.00 | ||
| AB | Back fill (Unwashed Sand) | TON | $0.00 | ||
| AC | Back fill (Flowable Fill) | CY | $0.00 | ||
| AD | Back fill (Pea Gravel) | TON | $0.00 | ||
| AE | 4 inch sewer line service | LF | $0.00 | ||
| AF | 4 inch electrical conduit | LF | $0.00 | ||
| AG | Water line service up to two inch | LF | $0.00 | ||
| AH | Hauling | CY | $0.00 | ||
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | $0.00 | ||
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | $0.00 | ||
| AK | Utility Boring, Horizontal, 24 in dia. | LF | $0.00 | ||
| AL | Cross tie timber walls/max 48"H | SF | $0.00 | ||
| AM | Top Soil 4 inches thick and spread | SY | $0.00 | ||
| EARTH WORK | |||||
| AN | Sand Clay Fill | CY | $0.00 | ||
| AO | Surface Preparation | SY | $0.00 | ||
| AP | Subgrade Preparation +or-3" | SY | $0.00 | ||
| AQ | Unclassified Excavation including haul off site | CY | $0.00 | ||
| CLEARING AND GRUBBING | |||||
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | $0.00 | ||
| AS | Remove Trees 6 " to 12 " | EA | $0.00 | ||
| AT | Remove Trees 12 " to 18 " | EA | $0.00 | ||
| AU | Remove Trees 18 " to 28 " | EA | $0.00 | ||
| EROSION CONTRTOL | |||||
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | $0.00 | ||
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | $0.00 | ||
| AX | Anchored Straw Bale | EA | $0.00 | ||
| STORM WATER | |||||
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | $0.00 | ||
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | $0.00 | ||
| BA | 18 Inch RCP Class III | LF | $0.00 | ||
| BB | 24 Inch RCP Class III | LF | $0.00 | ||
| BC | 36 Inch RCP Class III | LF | $0.00 | ||
| BD | Reset Valve Box | EA | $0.00 | ||
| BE | 4" Plastic Under drain with Sock | LF | $0.00 | ||
| BF | Convert Inlets w/frame and grate | EA | $0.00 | ||
| BG | Florida Catch Basin | EA | $0.00 | ||
| ASPHALT PAVING | |||||
| BH | Asphalt Emulsion | SY | $0.00 | ||
| BI | Petrotac Fabric | SF | $0.00 | ||
| BJ | Hand Asphalt Placement | TON | $0.00 | ||
| BK | Slurry Seal | SY | $0.00 | ||
| BL | Pot Hole Repair (per/SY) | SY | $0.00 | ||
| BM | Crack Seal | LF | $0.00 | ||
| BN | 6 inch SABC # 1 Base Course | TON | $0.00 | ||
| BO | 3 inch AC Binder Course | TON | $0.00 | ||
| BP | AC Surface Course Per Inch | TON | $0.00 | ||
| BQ | Surface Sterilization | SY | $0.00 | ||
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | $0.00 | ||
| BS | reflective yellow/with layout | SF | $0.00 | ||
| BT | reflective white/with layout | SF | $0.00 | ||
| BU | Prime Coat | SY | $0.00 | ||
| BV | Haul Spread Asphalt Millings | TON | $0.00 | ||
| BW | Demo Curb & Gutter | LF | $0.00 | ||
| BX | Hooded Catch basin 2x3x4 | EA | $0.00 | ||
| BY | Slurry seal Emulsion | SY | $0.00 | ||
| BZ | Rem /Reinstall wheel stops | EA | $0.00 | ||
| CA | New Wheel Stops | EA | $0.00 | ||
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | $0.00 | ||
| CC | Reserved | N/A | |||
| CD | Demo Wheel Stops | EA | $0.00 | ||
| GRASSING | |||||
| CE | Bermuda Sod 419 | SY | $0.00 | ||
| CF | Hydro seed large area's 80,000 to 350,000 | SY | $0.00 | ||
| CG | Centipede Sod | SY | $0.00 | ||
| CH | Hydroseed and Finish Grade 1 to 80,000 | SY | $0.00 | ||
| CONCRETE PAVING | |||||
| CI | New 24 Inch Concrete Curb and Gutter | LF | $0.00 | ||
| CJ | Replace 24 inch Concrete Curb and Gutter | LF | $0.00 | ||
| CK | Remove and Replace Sidewalk 4" thick (0-200 SF) | SF | $0.00 | ||
| CL | Remove and Replace Sidewalk 4" thick (over 200 SF) | SF | $0.00 | ||
| CM | New Sidewalk 4 Inches (0-200 SF) | SF | $0.00 | ||
| CN | New Side Walk 4 Inches Thick (over 200 SF) | SF | $0.00 | ||
| CO | Install 650 flex PCC pavement 14" thick>5000<10000 | SY | $0.00 | ||
| CP | Install 650 flex PCC pavement 14" thick>1000<5000 | SY | $0.00 | ||
| CQ | Install 650 flex PCC pavement 14" thick>1<1000 | SY | $0.00 | ||
| CR | Partial depth spall repairs-epoxy bonded PCC | SF | $0.00 | ||
| CS | Full depth (up to T=14") spall repair | SF | $0.00 | ||
| CT | Provide/install 1" dia smooth dowels-24"L,drill&epoxy | EA | $0.00 | ||
| CU | Provide/install 1-1/2" dia smooth dowels-24"L,drill&epoxy | EA | $0.00 | ||
| CV | Provide/install #3 rebars, 0.376LBS/LF | PND | $0.00 | ||
| CW | Provide/install #4 rebars, 0.668LBS/LF | PND | $0.00 | ||
| CX | Provide/install #5 rebars, 1.043LBS/LF | PND | $0.00 | ||
| CY | Provide/install #5 deformed tie bars-2.5' L (new pavement) | EA | $0.00 | ||
| CZ | Provide/install 3/4" dia smooth dowels-24"L (new pavement) | EA | $0.00 | ||
| DA | Provide/install 1" dia smooth dowels-24"L (new pavement) | EA | $0.00 | ||
| DB | Provide/install 1-1/2" dia smooth dowels-24"L (new pavement) | EA | $0.00 | ||
| DC | Provide/install expansion joint 3/4" cork | SF | $0.00 | ||
| DD | Provide/install expansion joint 1-1/2" cork | SF | $0.00 | ||
| DE | Provide & install aircraft tie-down | EA | $0.00 | ||
| DF | Weld wire mesh W2.5 x W2.5 | SF | $0.00 | ||
| DG | Concrete joint resealing incl backer mat'l replacement | LF | $0.00 | ||
| DH | Crack routing/sealing (PCC) using crack saw | LF | $0.00 | ||
| DI | Crack routing/sealing (PCC) using crack saw (up to 2"W) | LF | $0.00 | ||
| DJ | Saw cut reservoir then provide & install joint sealant & backer mat'l | LF | $0.00 | ||
| DK | Joint seal neopherene compression seal | LF | $0.00 | ||
| DL | Sawcutting concrete to 4" 1 to 1000 | LF | $0.00 | ||
| DM | Sawcutting concrete full depth / LF inch | LF | $0.00 | ||
| DN | Concrete Driveways 4" thick 1 to 100 SQ-YD, fiber mesh reinforced with 6 inch thickened edge see detail in Section 03300 | SY | $0.00 | ||
| DO | Expansion Board 4" wide (fiber) 1/2 thick | LF | $0.00 | ||
| DP | Expansion Board 14" wide (Cork) 1/2 thick | LF | $0.00 | ||
| DQ | Joint sealer 1/2" wide with backer rod 1 to 100000 LF(Silicone) to include green saw and widen joint | LF | $0.00 | ||
| DR | Joint sealer 1/2" wide with backer rod 10000 to 50000 LF(Silicone) to include green saw and widen joint | LF | $0.00 | ||
| DS | Remove Concrete Pavement 1" to 6 thick with disposal | SY | $0.00 | ||
| DT | Remove Concrete Pavement 6" to 14" thick with disposal | SY | $0.00 | ||
| DU | Install 650 Flex concrete PCC per inch thickness per Square Yard to include white pigmented curing compound | SY | $0.00 | ||
| PAVEMENT MARKINGS | |||||
| DV | Paint Removal Air Field 0to 50,000 SF | SF | $0.00 | ||
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | $0.00 | ||
| DX | Paint Removal Air Field 100,000 to Infinity | SF | $0.00 | ||
| DY | Rubber Removal Airfield 0 to 400,000 | SF | $0.00 | ||
| DZ | reflective yellow/with layout >10000 <500000 | SF | $0.00 | ||
| EA | Reflective white/with layout <10000 | SF | $0.00 | ||
| EB | reflective white/with layout >10000 <500000 | SF | $0.00 | ||
| EC | Black Non Reflective >5000 <100000 | SF | $0.00 | ||
| ED | Yellow Non Reflective >10000<75,000 Repair Asphalt | SF | $0.00 | ||
| EE | Red Non Reflective <5000 | SF | $0.00 | ||
| EF | Red Non Reflective >5000 <75000 | SF | 0 | $1.23 | $0.00 |
| All cost data contians Overhead, Profit and Labor | Total | $0.00 | |||
| Chain Link Fence& Gates | |||||
| EG | 6 foot Chain link fence with 3 strands barbed wire | LF | $27.99 | $0.00 | |
| EH | 7 foot Chain link fence with 3 strands barbed wire | LF | $41.14 | $0.00 | |
| EI | Double Gate's with 25x6 foot clear opening with 3 strands barbed wire | EA | $1,461.28 | $0.00 | |
| EJ | Double Gate's with 25x7 foot clear opening with 3 strands barbed wire | EA | $1,867.19 | $0.00 | |
| EK | Personal Gate 4 x 6 foot high clear opening with 3 strands barbed wire. | EA | $351.79 | $0.00 | |
| EL | Personal Gate 4 x 7 foot high clear opening with 3 strands barbed wire. | EA | $416.73 | $0.00 | |
| $0.00 | |||||
| FA4803-18-B-0001 |
Blank Bid Sheet
&CPage &P of &[4
IGE Revised081216
| Exihibit A | |||||||||||
| Contract: FA4803-11-D-0008 | |||||||||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||||||||
| PAVEMENT MARKINGS | |||||||||||
| Option Year 4 | IGE081216 rev | ||||||||||
| CLIN | Description | ||||||||||
| 4001 | U/I | QTY | PRICE | Total | |||||||
| PAVEMENT MARKINGS | |||||||||||
| AA | Mobilization/ DO | EA | 1 | $3,247.29 | $3,247.29 | ||||||
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | 8500 | $2.26 | $19,210.00 | ||||||
| DY | Rubber Removal Airfield 0 to 400,000 | SF | 150000 | $0.11 | $16,500.00 | ||||||
| DZ | reflective yellow/with layout >10000 <500000 | SF | 20000 | $1.60 | $32,000.00 | Option Year 4 | Southern Mgt | ||||
| EB | reflective white/with layout >10000 <500000 | SF | 75500 | $1.44 | $108,720.00 | CLIN | Description | ||||
| EC | Black Non Reflective >5000 <100000 | SF | 29795 | $1.23 | $36,647.85 | 4001 | U/I | PRICE | Total | ||
| Total | $216,325.14 | SITE WORK/GENERAL TASK | |||||||||
| AA | Mobilization per Delivery Order, | EA | 1 | $3,247.29 | $3,247.29 | ||||||
| AB | Back fill (Unwashed Sand) | TON | $17.05 | $0.00 | |||||||
| AC | Back fill (Flowable Fill) | CY | $102.30 | $0.00 | |||||||
| AD | Back fill (Pea Gravel) | TON | $14.08 | $0.00 | |||||||
| AE | 4 inch sewer line service | LF | $37.88 | $0.00 | |||||||
| AF | 4 inch electrical conduit | LF | $16.24 | $0.00 | |||||||
| AG | Water line service up to two inch | LF | $37.88 | $0.00 | |||||||
| AH | Hauling | CY | $5.41 | $0.00 | |||||||
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | $34.64 | $0.00 | |||||||
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | $135.30 | $0.00 | |||||||
| AK | Utility Boring, Horizontal, 24 in dia. | LF | $319.32 | $0.00 | |||||||
| AL | Cross tie timber walls/max 48"H | SF | $12.98 | $0.00 | |||||||
| AM | Top Soil 4 inches thick and spread | SY | $2.99 | $0.00 | |||||||
| EARTH WORK | |||||||||||
| AN | Sand Clay Fill | CY | $12.98 | $0.00 | |||||||
| AO | Surface Preparation | SY | $1.18 | $0.00 | |||||||
| AP | Subgrade Preparation +or-3" | SY | $5.15 | $0.00 | |||||||
| AQ | Unclassified Excavation including haul off site | CY | $16.24 | $0.00 | |||||||
| CLEARING AND GRUBBING | |||||||||||
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | $5,412.16 | $0.00 | |||||||
| AS | Remove Trees 6 " to 12 " | EA | $270.61 | $0.00 | |||||||
| AT | Remove Trees 12 " to 18 " | EA | $432.70 | $0.00 | |||||||
| AU | Remove Trees 18 " to 28 " | EA | $541.21 | $0.00 | |||||||
| EROSION CONTRTOL | |||||||||||
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | $1,515.40 | $0.00 | |||||||
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | $3.78 | $0.00 | |||||||
| AX | Anchored Straw Bale | EA | $9.20 | $0.00 | |||||||
| STORM WATER | |||||||||||
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | $319.32 | $0.00 | |||||||
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | $2,056.63 | $0.00 | |||||||
| BA | 18 Inch RCP Class III | LF | $43.30 | $0.00 | |||||||
| BB | 24 Inch RCP Class III | LF | $45.46 | $0.00 | |||||||
| BC | 36 Inch RCP Class III | LF | $51.96 | $0.00 | |||||||
| BD | Reset Valve Box | EA | $54.12 | $0.00 | |||||||
| BE | 4" Plastic Under drain with Sock | LF | $10.28 | $0.00 | |||||||
| BF | Convert Inlets w/frame and grate | EA | $865.95 | $0.00 | |||||||
| BG | Florida Catch Basin | EA | $2,164.87 | $0.00 | |||||||
| ASPHALT PAVING | |||||||||||
| BH | Asphalt Emulsion | SY | $1.96 | $0.00 | |||||||
| BI | Petrotac Fabric | SF | $5.41 | $0.00 | |||||||
| BJ | Hand Asphalt Placement | TON | $303.08 | $0.00 | |||||||
| BK | Slurry Seal | SY | $5.41 | $0.00 | |||||||
| BL | Pot Hole Repair (per/SY) | SY | $96.34 | $0.00 | |||||||
| BM | Crack Seal | LF | $2.26 | $0.00 | |||||||
| BN | 6 inch SABC # 1 Base Course | TON | $30.30 | $0.00 | |||||||
| BO | 3 inch AC Binder Course | TON | $232.72 | $0.00 | |||||||
| BP | AC Surface Course Per Inch | TON | $133.14 | $0.00 | |||||||
| BQ | Surface Sterilization | SY | $1.08 | $0.00 | |||||||
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | $2.16 | $0.00 | |||||||
| BS | reflective yellow/with layout | SF | $1.57 | $0.00 | |||||||
| BT | reflective white/with layout | SF | $1.57 | $0.00 | |||||||
| BU | Prime Coat | SY | $0.83 | $0.00 | |||||||
| BV | Haul Spread Asphalt Millings | TON | $10.82 | $0.00 | |||||||
| BW | Demo Curb & Gutter | LF | $9.74 | $0.00 | |||||||
| BX | Hooded Catch basin 2x3x4 | EA | $1,948.37 | $0.00 | |||||||
| BY | Slurry seal Emulsion | SY | $5.41 | $0.00 | |||||||
| BZ | Rem /Reinstall wheel stops | EA | $43.30 | $0.00 | |||||||
| CA | New Wheel Stops | EA | $86.59 | $0.00 | |||||||
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | $4.32 | $0.00 | |||||||
| CC | Reserved | N/A | |||||||||
| CD | Demo Wheel Stops | EA | $21.65 | $0.00 | |||||||
| GRASSING | |||||||||||
| CE | Bermuda Sod 419 | SY | $5.95 | $0.00 | |||||||
| CF | Hydro seed large area's 80,000 to 350,000 | SY | $0.51 | $0.00 | |||||||
| CG | Centipede Sod | SY | $5.95 | $0.00 | |||||||
| CH | Hydroseed and Finish Grade 1 to 80,000 | SY | $0.58 | $0.00 | |||||||
| CONCRETE PAVING | |||||||||||
| CI | New 24 Inch Concrete Curb and Gutter | LF | $18.94 | $0.00 | |||||||
| CJ | Replace 24 inch Concrete Curb and Gutter | LF | $31.93 | $0.00 | |||||||
| CK | Remove and Replace Sidewalk 4" thick (0-200 SF) | SF | $16.24 | $0.00 | |||||||
| CL | Remove and Replace Sidewalk 4" thick (over 200 SF) | SF | $8.12 | $0.00 | |||||||
| CM | New Sidewalk 4 Inches (0-200 SF) | SF | $7.58 | $0.00 | |||||||
| CN | New Side Walk 4 Inches Thick (over 200 SF) | SF | $6.49 | $0.00 | |||||||
| CO | Install 650 flex PCC pavement 14" thick>5000<10000 | SY | $77.40 | $0.00 | |||||||
| CP | Install 650 flex PCC pavement 14" thick>1000<5000 | SY | $84.71 | $0.00 | |||||||
| CQ | Install 650 flex PCC pavement 14" thick>1<1000 | SY | $110.20 | $0.00 | |||||||
| CR | Partial depth spall repairs-epoxy bonded PCC | SF | $129.90 | $0.00 | |||||||
| CS | Full depth (up to T=14") spall repair | SF | $146.13 | $0.00 | |||||||
| CT | Provide/install 1" dia smooth dowels-24"L,drill&epoxy | EA | $14.08 | $0.00 | |||||||
| CU | Provide/install 1-1/2" dia smooth dowels-24"L,drill&epoxy | EA | $18.40 | $0.00 | |||||||
| CV | Provide/install #3 rebars, 0.376LBS/LF | PND | $1.08 | $0.00 | |||||||
| CW | Provide/install #4 rebars, 0.668LBS/LF | PND | $2.16 | $0.00 | |||||||
| CX | Provide/install #5 rebars, 1.043LBS/LF | PND | $2.16 | $0.00 | |||||||
| CY | Provide/install #5 deformed tie bars-2.5' L (new pavement) | EA | $7.85 | $0.00 | |||||||
| CZ | Provide/install 3/4" dia smooth dowels-24"L (new pavement) | EA | $7.85 | $0.00 | |||||||
| DA | Provide/install 1" dia smooth dowels-24"L (new pavement) | EA | $7.85 | $0.00 | |||||||
| DB | Provide/install 1-1/2" dia smooth dowels-24"L (new pavement) | EA | $15.16 | $0.00 | |||||||
| DC | Provide/install expansion joint 3/4" cork | SF | $9.74 | $0.00 | |||||||
| DD | Provide/install expansion joint 1-1/2" cork | SF | $18.14 | $0.00 | |||||||
| DE | Provide & install aircraft tie-down | EA | $541.21 | $0.00 | |||||||
| DF | Weld wire mesh W2.5 x W2.5 | SF | $1.67 | $0.00 | |||||||
| DG | Concrete joint resealing incl backer mat'l replacement | LF | $6.49 | $0.00 | |||||||
| DH | Crack routing/sealing (PCC) using crack saw | LF | $10.02 | $0.00 | |||||||
| DI | Crack routing/sealing (PCC) using crack saw (up to 2"W) | LF | $14.08 | $0.00 | |||||||
| DJ | Saw cut reservoir then provide & install joint sealant & backer mat'l | LF | $6.49 | $0.00 | |||||||
| DK | Joint seal neopherene compression seal | LF | $6.49 | $0.00 | |||||||
| DL | Sawcutting concrete to 4" 1 to 1000 | LF | $4.32 | $0.00 | |||||||
| DM | Sawcutting concrete full depth / LF inch | LF | $1.29 | $0.00 | |||||||
| DN | Concrete Driveways 4" thick 1 to 100 SQ-YD, fiber mesh reinforced with 6 inch thickened edge see detail in Section 03300 | SY | $64.94 | $0.00 | |||||||
| DO | Expansion Board 4" wide (fiber) 1/2 thick | LF | $4.32 | $0.00 | |||||||
| DP | Expansion Board 14" wide (Cork) 1/2 thick | LF | $9.74 | $0.00 | |||||||
| DQ | Joint sealer 1/2" wide with backer rod 1 to 100000 LF(Silicone) to include green saw and widen joint | LF | $9.74 | $0.00 | |||||||
| DR | Joint sealer 1/2" wide with backer rod 10000 to 50000 LF(Silicone) to include green saw and widen joint | LF | $5.79 | $0.00 | |||||||
| DS | Remove Concrete Pavement 1" to 6 thick with disposal | SY | $16.24 | $0.00 | |||||||
| DT | Remove Concrete Pavement 6" to 14" thick with disposal | SY | $15.16 | $0.00 | |||||||
| DU | Install 650 Flex concrete PCC per inch thickness per Square Yard to include white pigmented curing compound | SY | $7.84 | $0.00 | |||||||
| PAVEMENT MARKINGS | |||||||||||
| DV | Paint Removal Air Field 0to 50,000 SF | SF | 0 | $2.26 | $0.00 | ||||||
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | 50234 | $2.11 | $105,993.74 | ||||||
| DX | Paint Removal Air Field 100,000 to Infinity | SF | 0 | $1.72 | $0.00 | ||||||
| DY | Rubber Removal Airfield 0 to 400,000 | SF | 200000 | $0.11 | $22,000.00 | ||||||
| DZ | reflective yellow/with layout >10000 <500000 | SF | 46306 | $1.60 | $74,089.60 | ||||||
| EA | Reflective white/with layout <10000 | SF | 0 | $1.60 | $0.00 | ||||||
| EB | reflective white/with layout >10000 <500000 | SF | 106000 | $1.44 | $152,640.00 | ||||||
| EC | Black Non Reflective >5000 <100000 | SF | 67970 | $1.23 | $83,603.10 | ||||||
| ED | Yellow Non Reflective >10000<75,000 | SF | 24000 | $1.44 | $34,560.00 | ||||||
| EE | Red Non Reflective <5000 | SF | 3411 | $1.42 | $4,843.62 | ||||||
| EF | Red Non Reflective >5000 <75000 | SF | 0 | $1.23 | $0.00 | ||||||
| Total | $480,977.35 |
Base
| Exihibit A | |||||
| Contract: FA4803-11-D-0008 | |||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||
| Base Year | Southern Mgt | ||||
| CLIN | Description | ||||
| 0001 | U/I | QTY | PRICE | Total | |
| SITE WORK/GENERAL TASK | |||||
| AA | Mobilization per Delivery Order, | EA | 6 | $3,000.00 | $18,000.00 |
| AB | Back fill (Unwashed Sand) | TON | 100 | $15.75 | $1,575.00 |
| AC | Back fill (Flowable Fill) | CY | 10 | $94.50 | $945.00 |
| AD | Back fill (Pea Gravel) | TON | 10 | $13.00 | $130.00 |
| AE | 4 inch sewer line service | LF | 125 | $35.00 | $4,375.00 |
| AF | 4 inch electrical conduit | LF | 125 | $15.00 | $1,875.00 |
| AG | Water line service up to two inch | LF | 50 | $35.00 | $1,750.00 |
| AH | Hauling | CY | 100 | $5.00 | $500.00 |
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | 125 | $32.00 | $4,000.00 |
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | 500 | $125.00 | $62,500.00 |
| AK | Utility Boring, Horizontal, 24 in dia. | LF | 250 | $295.00 | $73,750.00 |
| AL | Cross tie timber walls/max 48"H | SF | 1500 | $12.00 | $18,000.00 |
| AM | Top Soil 4 inches thick and spread | SY | 5000 | $2.75 | $13,750.00 |
| EARTH WORK | |||||
| AN | Sand Clay Fill | CY | 450 | $12.00 | $5,400.00 |
| AO | Surface Preparation | SY | 114000 | $1.10 | $125,400.00 |
| AP | Subgrade Preparation +or-3" | SY | 72000 | $4.75 | $342,000.00 |
| AQ | Unclassified Excavation including haul off site | CY | 1750 | $15.00 | $26,250.00 |
| CLEARING AND GRUBBING | |||||
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | 1 | $5,000.00 | $5,000.00 |
| AS | Remove Trees 6 " to 12 " | EA | 24 | $250.00 | $6,000.00 |
| AT | Remove Trees 12 " to 18 " | EA | 24 | $400.00 | $9,600.00 |
| AU | Remove Trees 18 " to 28 " | EA | 12 | $500.00 | $6,000.00 |
| EROSION CONTRTOL | |||||
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | 1 | $1,400.00 | $1,400.00 |
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | 1 | $3.50 | $3.50 |
| AX | Anchored Straw Bale | EA | 50 | $8.50 | $425.00 |
| STORM WATER | |||||
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | 200 | $295.00 | $59,000.00 |
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | 10 | $1,900.00 | $19,000.00 |
| BA | 18 Inch RCP Class III | LF | 150 | $40.00 | $6,000.00 |
| BB | 24 Inch RCP Class III | LF | 225 | $42.00 | $9,450.00 |
| BC | 36 Inch RCP Class III | LF | 100 | $48.00 | $4,800.00 |
| BD | Reset Valve Box | EA | 100 | $50.00 | $5,000.00 |
| BE | 4" Plastic Under drain with Sock | LF | 250 | $9.50 | $2,375.00 |
| BF | Convert Inlets w/frame and grate | EA | 2 | $800.00 | $1,600.00 |
| BG | Florida Catch Basin | EA | 5 | $2,000.00 | $10,000.00 |
| ASPHALT PAVING | |||||
| BH | Asphalt Emulsion | SY | 100 | $1.80 | $180.00 |
| BI | Petrotac Fabric | SF | 100 | $5.00 | $500.00 |
| BJ | Hand Asphalt Placement | TON | 100 | $280.00 | $28,000.00 |
| BK | Slurry Seal | SY | 14000 | $5.00 | $70,000.00 |
| BL | Pot Hole Repair (per/SY) | SY | 50 | $89.00 | $4,450.00 |
| BM | Crack Seal | LF | 650 | $2.10 | $1,365.00 |
| BN | 6 inch SABC # 1 Base Course | TON | 2400 | $28.00 | $67,200.00 |
| BO | 3 inch AC Binder Course | TON | 50 | $215.00 | $10,750.00 |
| BP | AC Surface Course Per Inch | TON | 1500 | $123.00 | $184,500.00 |
| BQ | Surface Sterilization | SY | 3500 | $1.00 | $3,500.00 |
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | 25000 | $2.00 | $50,000.00 |
| BS | reflective yellow/with layout | SF | 10000 | $1.45 | $14,500.00 |
| BT | reflective white/with layout | SF | 5000 | $1.45 | $7,250.00 |
| BU | Prime Coat | SY | 1000 | $0.75 | $750.00 |
| BV | Haul Spread Asphalt Millings | TON | 50 | $10.00 | $500.00 |
| BW | Demo Curb & Gutter | LF | 1000 | $9.00 | $9,000.00 |
| BX | Hooded Catch basin 2x3x4 | EA | 2 | $1,800.00 | $3,600.00 |
| BY | Slurry seal Emulsion | SY | 1200 | $5.00 | $6,000.00 |
| BZ | Rem /Reinstall wheel stops | EA | 25 | $40.00 | $1,000.00 |
| CA | New Wheel Stops | EA | 50 | $80.00 | $4,000.00 |
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | 500 | $4.00 | $2,000.00 |
| CC | Reserved | N/A | 0 | $0.00 | |
| CD | Demo Wheel Stops | EA | 10 | $20.00 | $200.00 |
| GRASSING | |||||
| CE | Bermuda Sod 419 | SY | 1000 | $5.50 | $5,500.00 |
| CF | Hydro seed large area's 80,000 to 350,000 | SY | 100000 | $0.47 | $47,000.00 |
| CG | Centipede Sod | SY | 250 | $5.50 | $1,375.00 |
| CH | Hydroseed and Finish Grade 1 to 80,000 | SY | 10000 | $0.54 | $5,400.00 |
| CONCRETE PAVING | |||||
| CI | New 24 Inch Concrete Curb and Gutter | LF | 600 | $17.50 | $10,500.00 |
| CJ | Replace 24 inch Concrete Curb and Gutter | LF | 1500 | $29.50 | $44,250.00 |
| CK | Remove and Replace Sidewalk 4" thick (0-200 SF) | SF | 10 | $15.00 | $150.00 |
| CL | Remove and Replace Sidewalk 4" thick (over 200 SF) | SF | 1250 | $7.50 | $9,375.00 |
| CM | New Sidewalk 4 Inches (0-200 SF) | SF | 100 | $7.00 | $700.00 |
| CN | New Side Walk 4 Inches Thick (over 200 SF) | SF | 300 | $6.00 | $1,800.00 |
| CO | Install 650 flex PCC pavement 14" thick>5000<10000 | SY | 5000 | $71.50 | $357,500.00 |
| CP | Install 650 flex PCC pavement 14" thick>1000<5000 | SY | 1250 | $78.25 | $97,812.50 |
| CQ | Install 650 flex PCC pavement 14" thick>1<1000 | SY | 250 | $101.80 | $25,450.00 |
| CR | Partial depth spall repairs-epoxy bonded PCC | SF | 125 | $120.00 | $15,000.00 |
| CS | Full depth (up to T=14") spall repair | SF | 125 | $135.00 | $16,875.00 |
| CT | Provide/install 1" dia smooth dowels-24"L,drill&epoxy | EA | 50 | $13.00 | $650.00 |
| CU | Provide/install 1-1/2" dia smooth dowels-24"L,drill&epoxy | EA | 200 | $17.00 | $3,400.00 |
| CV | Provide/install #3 rebars, 0.376LBS/LF | PND | 625 | $1.00 | $625.00 |
| CW | Provide/install #4 rebars, 0.668LBS/LF | PND | 1250 | $2.00 | $2,500.00 |
| CX | Provide/install #5 rebars, 1.043LBS/LF | PND | 1250 | $2.00 | $2,500.00 |
| CY | Provide/install #5 deformed tie bars-2.5' L (new pavement) | EA | 375 | $7.25 | $2,718.75 |
| CZ | Provide/install 3/4" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.25 | $906.25 |
| DA | Provide/install 1" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.25 | $906.25 |
| DB | Provide/install 1-1/2" dia smooth dowels-24"L (new pavement) | EA | 200 | $14.00 | $2,800.00 |
| DC | Provide/install expansion joint 3/4" cork | SF | 375 | $9.00 | $3,375.00 |
| DD | Provide/install expansion joint 1-1/2" cork | SF | 625 | $16.75 | $10,468.75 |
| DE | Provide & install aircraft tie-down | EA | 4 | $500.00 | $2,000.00 |
| DF | Weld wire mesh W2.5 x W2.5 | SF | 500 | $1.55 | $775.00 |
| DG | Concrete joint resealing incl backer mat'l replacement | LF | 1000 | $6.00 | $6,000.00 |
| DH | Crack routing/sealing (PCC) using crack saw | LF | 100 | $9.25 | $925.00 |
| DI | Crack routing/sealing (PCC) using crack saw (up to 2"W) | LF | 50 | $13.00 | $650.00 |
| DJ | Saw cut reservoir then provide & install joint sealant & backer mat'l | LF | 1800 | $6.00 | $10,800.00 |
| DK | Joint seal neopherene compression seal | LF | 5000 | $6.00 | $30,000.00 |
| DL | Sawcutting concrete to 4" 1 to 1000 | LF | 100 | $4.00 | $400.00 |
| DM | Sawcutting concrete full depth / LF inch | LF | 40000 | $1.20 | $48,000.00 |
| DN | Concrete Driveways 4" thick 1 to 100 SQ-YD, fiber mesh reinforced with 6 inch thickened edge see detail in Section 03300 | SY | 440 | $60.00 | $26,400.00 |
| DO | Expansion Board 4" wide (fiber) 1/2 thick | LF | 125 | $4.00 | $500.00 |
| DP | Expansion Board 14" wide (Cork) 1/2 thick | LF | 2500 | $9.00 | $22,500.00 |
| DQ | Joint sealer 1/2" wide with backer rod 1 to 100000 LF(Silicone) to include green saw and widen joint | LF | 500 | $9.00 | $4,500.00 |
| DR | Joint sealer 1/2" wide with backer rod 10000 to 50000 LF(Silicone) to include green saw and widen joint | LF | 5000 | $5.35 | $26,750.00 |
| DS | Remove Concrete Pavement 1" to 6 thick with disposal | SY | 500 | $15.00 | $7,500.00 |
| DT | Remove Concrete Pavement 6" to 14" thick with disposal | SY | 5000 | $14.00 | $70,000.00 |
| DU | Install 650 Flex concrete PCC per inch thickness per Square Yard to include white pigmented curing compound | SY | 26000 | $7.25 | $188,500.00 |
| PAVEMENT MARKINGS | |||||
| DV | Paint Removal Air Field 0to 50,000 SF | SF | 50000 | $2.10 | $105,000.00 |
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | 100000 | $1.95 | $195,000.00 |
| DX | Paint Removal Air Field 100,000 to Infinity | SF | 100000 | $1.60 | $160,000.00 |
| DY | Rubber Removal Airfield 0 to 400,000 | SF | 400000 | $0.10 | $40,000.00 |
| DZ | reflective yellow/with layout >10000 <500000 | SF | 10000 | $1.48 | $14,800.00 |
| EA | Reflective white/with layout <10000 | SF | 9999 | $1.48 | $14,798.52 |
| EB | reflective white/with layout >10000 <500000 | SF | 10000 | $1.32 | $13,200.00 |
| EC | Black Non Reflective >5000 <100000 | SF | 5000 | $1.15 | $5,750.00 |
| ED | Yellow Non Reflective >10000<75,000 | SF | 10000 | $1.32 | $13,200.00 |
| EE | Red Non Reflective <5000 | SF | 5000 | $1.30 | $6,500.00 |
| EF | Red Non Reflective >5000 <75000 | SF | 75000 | $1.15 | $86,250.00 |
| Chain Link Fence& Gates | |||||
| EG | 6 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $25.85 | $258,500.00 |
| EH | 7 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $38.00 | $380,000.00 |
| EI | Double Gate's with 25x6 foot clear opening with 3 strands barbed wire | EA | 15 | $1,350.00 | $20,250.00 |
| EJ | Double Gate's with 25x7 foot clear opening with 3 strands barbed wire | EA | 15 | $1,725.00 | $25,875.00 |
| EK | Personal Gate 4 x 6 foot high clear opening with 3 strands barbed wire. | EA | 15 | $325.00 | $4,875.00 |
| EL | Personal Gate 4 x 7 foot high clear opening with 3 strands barbed wire. | EA | 15 | $385.00 | $5,775.00 |
| Total | $3,780,609.52 | ||||
| Base Year | $3,780,609.52 | ||||
| Option 1 | $3,855,338.81 | ||||
| Option 2 | $3,923,413.68 | ||||
| Option 3 | $4,011,365.89 | ||||
| Option 4 | $4,089,071.22 | ||||
| $19,659,799.12 |
&CPage &P of &[4
OptionYear1
| Exihibit A | |||||
| Contract: FA4803-11-D-0008 | |||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||
| Option Year 1 | Southern Mgt | ||||
| CLIN | Description | ||||
| 1001 | U/I | QTY | PRICE | Total | |
| SITE WORK/GENERAL TASK | |||||
| AA | Mobilization per Delivery Order, | EA | 6 | $3,060.00 | $18,360.00 |
| AB | Back fill (Unwashed Sand) | TON | 100 | $16.07 | $1,607.00 |
| AC | Back fill (Flowable Fill) | CY | 10 | $96.39 | $963.90 |
| AD | Back fill (Pea Gravel) | TON | 10 | $13.26 | $132.60 |
| AE | 4 inch sewer line service | LF | 125 | $35.70 | $4,462.50 |
| AF | 4 inch electrical conduit | LF | 125 | $15.30 | $1,912.50 |
| AG | Water line service up to two inch | LF | 50 | $35.70 | $1,785.00 |
| AH | Hauling | CY | 100 | $5.10 | $510.00 |
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | 125 | $32.64 | $4,080.00 |
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | 500 | $127.50 | $63,750.00 |
| AK | Utility Boring, Horizontal, 24 in dia. | LF | 250 | $300.90 | $75,225.00 |
| AL | Cross tie timber walls/max 48"H | SF | 1500 | $12.24 | $18,360.00 |
| AM | Top Soil 4 inches thick and spread | SY | 5000 | $2.81 | $14,050.00 |
| AN | Sand Clay Fill | CY | 450 | $12.24 | $5,508.00 |
| AO | Surface Preparation | SY | 114000 | $1.12 | $127,680.00 |
| AP | Subgrade Preparation +or-3" | SY | 72000 | $4.85 | $349,200.00 |
| AQ | Unclassified Excavation including haul off site | CY | 1750 | $15.30 | $26,775.00 |
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | 1 | $5,100.00 | $5,100.00 |
| AS | Remove Trees 6 " to 12 " | EA | 24 | $255.00 | $6,120.00 |
| AT | Remove Trees 12 " to 18 " | EA | 24 | $408.00 | $9,792.00 |
| AU | Remove Trees 18 " to 28 " | EA | 12 | $510.00 | $6,120.00 |
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | 1 | $1,428.00 | $1,428.00 |
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | 1 | $3.57 | $3.57 |
| AX | Anchored Straw Bale | EA | 50 | $8.67 | $433.50 |
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | 200 | $300.90 | $60,180.00 |
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | 10 | $1,938.00 | $19,380.00 |
| BA | 18 Inch RCP Class III | LF | 150 | $40.80 | $6,120.00 |
| BB | 24 Inch RCP Class III | LF | 225 | $42.84 | $9,639.00 |
| BC | 36 Inch RCP Class III | LF | 100 | $48.96 | $4,896.00 |
| BD | Reset Valve Box | EA | 100 | $51.00 | $5,100.00 |
| BE | 4" Plastic Under drain with Sock | LF | 250 | $9.69 | $2,422.50 |
| BF | Convert Inlets w/frame and grate | EA | 2 | $816.00 | $1,632.00 |
| BG | Florida Catch Basin | EA | 5 | $2,040.00 | $10,200.00 |
| BH | Asphalt Emulsion | SY | 100 | $1.84 | $184.00 |
| BI | Petrotac Fabric | SF | 100 | $5.10 | $510.00 |
| BJ | Hand Asphalt Placement | TON | 100 | $285.60 | $28,560.00 |
| BK | Slurry Seal | SY | 14000 | $5.10 | $71,400.00 |
| BL | Pot Hole Repair (per/SY) | SY | 50 | $90.78 | $4,539.00 |
| BM | Crack Seal | LF | 650 | $2.14 | $1,391.00 |
| BN | 6 inch SABC # 1 Base Course | TON | 2400 | $28.56 | $68,544.00 |
| BO | 3 inch AC Binder Course | TON | 50 | $219.30 | $10,965.00 |
| BP | AC Surface Course Per Inch | TON | 1500 | $125.46 | $188,190.00 |
| BQ | Surface Sterilization | SY | 3500 | $1.02 | $3,570.00 |
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | 25000 | $2.04 | $51,000.00 |
| BS | reflective yellow/with layout | SF | 10000 | $1.48 | $14,800.00 |
| BT | reflective white/with layout | SF | 5000 | $1.48 | $7,400.00 |
| BU | Prime Coat | SY | 1000 | $0.77 | $770.00 |
| BV | Haul Spread Asphalt Millings | TON | 50 | $10.20 | $510.00 |
| BW | Demo Curb & Gutter | LF | 1000 | $9.18 | $9,180.00 |
| BX | Hooded Catch basin 2x3x4 | EA | 2 | $1,836.00 | $3,672.00 |
| BY | Slurry seal Emulsion | SY | 1200 | $5.10 | $6,120.00 |
| BZ | Rem /Reinstall wheel stops | EA | 25 | $40.80 | $1,020.00 |
| CA | New Wheel Stops | EA | 50 | $81.60 | $4,080.00 |
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | 500 | $4.08 | $2,040.00 |
| CC | Reserved | N/A | 0 | ||
| CD | Demo Wheel Stops | EA | 10 | $20.40 | $204.00 |
| CE | Bermuda Sod 419 | SY | 1000 | $5.61 | $5,610.00 |
| CF | Hydro seed large area's 80,000 to 350,000 | SY | 100000 | $0.48 | $48,000.00 |
| CG | Centipede Sod | SY | 250 | $5.61 | $1,402.50 |
| CH | Hydroseed and Finish Grade 1 to 80,000 | SY | 10000 | $0.55 | $5,500.00 |
| CI | New 24 Inch Concrete Curb and Gutter | LF | 600 | $17.85 | $10,710.00 |
| CJ | Replace 24 inch Concrete Curb and Gutter | LF | 1500 | $30.09 | $45,135.00 |
| CK | Remove and Replace Sidewalk 4" thick (0-200 SF) | SF | 10 | $15.30 | $153.00 |
| CL | Remove and Replace Sidewalk 4" thick (over 200 SF) | SF | 1250 | $7.65 | $9,562.50 |
| CM | New Sidewalk 4 Inches (0-200 SF) | SF | 100 | $7.14 | $714.00 |
| CN | New Side Walk 4 Inches Thick (over 200 SF) | SF | 300 | $6.12 | $1,836.00 |
| CO | Install 650 flex PCC pavement 14" thick>5000<10000 | SY | 5000 | $72.93 | $364,650.00 |
| CP | Install 650 flex PCC pavement 14" thick>1000<5000 | SY | 1250 | $79.82 | $99,775.00 |
| CQ | Install 650 flex PCC pavement 14" thick>1<1000 | SY | 250 | $103.84 | $25,960.00 |
| CR | Partial depth spall repairs-epoxy bonded PCC | SF | 125 | $122.40 | $15,300.00 |
| CS | Full depth (up to T=14") spall repair | SF | 125 | $137.70 | $17,212.50 |
| CT | Provide/install 1" dia smooth dowels-24"L,drill&epoxy | EA | 50 | $13.26 | $663.00 |
| CU | Provide/install 1-1/2" dia smooth dowels-24"L,drill&epoxy | EA | 200 | $17.34 | $3,468.00 |
| CV | Provide/install #3 rebars, 0.376LBS/LF | PND | 625 | $1.02 | $637.50 |
| CW | Provide/install #4 rebars, 0.668LBS/LF | PND | 1250 | $2.04 | $2,550.00 |
| CX | Provide/install #5 rebars, 1.043LBS/LF | PND | 1250 | $2.04 | $2,550.00 |
| CY | Provide/install #5 deformed tie bars-2.5' L (new pavement) | EA | 375 | $7.40 | $2,775.00 |
| CZ | Provide/install 3/4" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.40 | $925.00 |
| DA | Provide/install 1" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.40 | $925.00 |
| DB | Provide/install 1-1/2" dia smooth dowels-24"L (new pavement) | EA | 200 | $14.28 | $2,856.00 |
| DC | Provide/install expansion joint 3/4" cork | SF | 375 | $9.18 | $3,442.50 |
| DD | Provide/install expansion joint 1-1/2" cork | SF | 625 | $17.09 | $10,681.25 |
| DE | Provide & install aircraft tie-down | EA | 4 | $510.00 | $2,040.00 |
| DF | Weld wire mesh W2.5 x W2.5 | SF | 500 | $1.58 | $790.00 |
| DG | Concrete joint resealing incl backer mat'l replacement | LF | 1000 | $6.12 | $6,120.00 |
| DH | Crack routing/sealing (PCC) using crack saw | LF | 100 | $9.44 | $944.00 |
| DI | Crack routing/sealing (PCC) using crack saw (up to 2"W) | LF | 50 | $13.26 | $663.00 |
| DJ | Saw cut reservoir then provide & install joint sealant & backer mat'l | LF | 1800 | $6.12 | $11,016.00 |
| DK | Joint seal neopherene compression seal | LF | 5000 | $6.12 | $30,600.00 |
| DL | Sawcutting concrete to 4" 1 to 1000 | LF | 100 | $4.08 | $408.00 |
| DM | Sawcutting concrete full depth / LF inch | LF | 40000 | $1.22 | $48,800.00 |
| DN | Concrete Driveways 4" thick 1 to 100 SQ-YD, fiber mesh reinforced with 6 inch thickened edge see detail in Section 03300 | SY | 440 | $61.20 | $26,928.00 |
| DO | Expansion Board 4" wide (fiber) 1/2 thick | LF | 125 | $4.08 | $510.00 |
| DP | Expansion Board 14" wide (Cork) 1/2 thick | LF | 2500 | $9.18 | $22,950.00 |
| DQ | Joint sealer 1/2" wide with backer rod 1 to 100000 LF(Silicone) to include green saw and widen joint | LF | 500 | $9.18 | $4,590.00 |
| DR | Joint sealer 1/2" wide with backer rod 10000 to 50000 LF(Silicone) to include green saw and widen joint | LF | 5000 | $5.46 | $27,300.00 |
| DS | Remove Concrete Pavement 1" to 6 thick with disposal | SY | 500 | $15.30 | $7,650.00 |
| DT | Remove Concrete Pavement 6" to 14" thick with disposal | SY | 5000 | $14.28 | $71,400.00 |
| DU | Install 650 Flex concrete PCC per inch thickness per Square Yard to include white pigmented curing compound | SY | 26000 | $7.40 | $192,400.00 |
| DV | Paint Removal Air Field 0to 50,000 SF | SF | 50000 | $2.14 | $107,000.00 |
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | 100000 | $1.99 | $199,000.00 |
| DX | Paint Removal Air Field 100,000 to Infinity | SF | 100000 | $1.63 | $163,000.00 |
| DY | Rubber Removal Airfield 0 to 400,000 | SF | 400000 | $0.10 | $40,000.00 |
| DZ | reflective yellow/with layout >10000 <500000 | SF | 10000 | $1.51 | $15,100.00 |
| EA | Reflective white/with layout <10000 | SF | 9999 | $1.51 | $15,098.49 |
| EB | reflective white/with layout >10000 <500000 | SF | 10000 | $1.35 | $13,500.00 |
| EC | Black Non Reflective >5000 <100000 | SF | 5000 | $1.17 | $5,850.00 |
| ED | Yellow Non Reflective >10000<75,000 | SF | 10000 | $1.35 | $13,500.00 |
| EE | Red Non Reflective <5000 | SF | 5000 | $1.33 | $6,650.00 |
| EF | Red Non Reflective >5000 <75000 | SF | 75000 | $1.17 | $87,750.00 |
| EG | 6 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $26.37 | $263,700.00 |
| EH | 7 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $38.76 | $387,600.00 |
| EI | Double Gate's with 25x6 foot clear opening with 3 strands barbed wire | EA | 15 | $1,377.00 | $20,655.00 |
| EJ | Double Gate's with 25x7 foot clear opening with 3 strands barbed wire | EA | 15 | $1,759.50 | $26,392.50 |
| EK | Personal Gate 4 x 6 foot high clear opening with 3 strands barbed wire. | EA | 15 | $331.50 | $4,972.50 |
| EL | Personal Gate 4 x 7 foot high clear opening with 3 strands barbed wire. | EA | 15 | $392.70 | $5,890.50 |
| $3,855,338.81 |
&CPage &P of &[3
OptionYear2
| Exihibit A | |||||
| Contract: FA4803-11-D-0008 | |||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||
| Option Year 2 | Southern Mgt | ||||
| CLIN | Description | ||||
| 2001 | U/I | QTY | PRICE | Total | |
| SITE WORK/GENERAL TASK | |||||
| AA | Mobilization per Delivery Order, | EA | 6 | $3,121.20 | $18,727.20 |
| AB | Back fill (Unwashed Sand) | TON | 100 | $16.39 | $1,639.00 |
| AC | Back fill (Flowable Fill) | CY | 10 | $98.32 | $983.20 |
| AD | Back fill (Pea Gravel) | TON | 10 | $13.53 | $135.30 |
| AE | 4 inch sewer line service | LF | 125 | $36.41 | $4,551.25 |
| AF | 4 inch electrical conduit | LF | 125 | $15.61 | $1,951.25 |
| AG | Water line service up to two inch | LF | 50 | $36.41 | $1,820.50 |
| AH | Hauling | CY | 100 | $5.20 | $520.00 |
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | 125 | $33.29 | $4,161.25 |
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | 500 | $130.05 | $65,025.00 |
| AK | Utility Boring, Horizontal, 24 in dia. | LF | 250 | $306.92 | $76,730.00 |
| AL | Cross tie timber walls/max 48"H | SF | 1500 | $12.48 | $18,720.00 |
| AM | Top Soil 4 inches thick and spread | SY | 5000 | $2.87 | $14,350.00 |
| EARTH WORK | |||||
| AN | Sand Clay Fill | CY | 450 | $12.48 | $5,616.00 |
| AO | Surface Preparation | SY | 114000 | $1.14 | $129,960.00 |
| AP | Subgrade Preparation +or-3" | SY | 72000 | $4.95 | $356,400.00 |
| AQ | Unclassified Excavation including haul off site | CY | 1750 | $15.61 | $27,317.50 |
| CLEARING AND GRUBBING | |||||
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | 1 | $5,202.00 | $5,202.00 |
| AS | Remove Trees 6 " to 12 " | EA | 24 | $260.10 | $6,242.40 |
| AT | Remove Trees 12 " to 18 " | EA | 24 | $416.61 | $9,998.64 |
| AU | Remove Trees 18 " to 28 " | EA | 12 | $520.20 | $6,242.40 |
| EROSION CONTRTOL | |||||
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | 1 | $1,456.56 | $1,456.56 |
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | 1 | $3.64 | $3.64 |
| AX | Anchored Straw Bale | EA | 50 | $8.84 | $442.00 |
| STORM WATER | |||||
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | 200 | $306.92 | $61,384.00 |
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | 10 | $1,976.76 | $19,767.60 |
| BA | 18 Inch RCP Class III | LF | 150 | $41.62 | $6,243.00 |
| BB | 24 Inch RCP Class III | LF | 225 | $43.70 | $9,832.50 |
| BC | 36 Inch RCP Class III | LF | 100 | $49.94 | $4,994.00 |
| BD | Reset Valve Box | EA | 100 | $52.02 | $5,202.00 |
| BE | 4" Plastic Under drain with Sock | LF | 250 | $9.88 | $2,470.00 |
| BF | Convert Inlets w/frame and grate | EA | 2 | $832.32 | $1,664.64 |
| BG | Florida Catch Basin | EA | 5 | $2,080.80 | $10,404.00 |
| ASPHALT PAVING | |||||
| BH | Asphalt Emulsion | SY | 100 | $1.88 | $188.00 |
| BI | Petrotac Fabric | SF | 100 | $5.20 | $520.00 |
| BJ | Hand Asphalt Placement | TON | 100 | $291.31 | $29,131.00 |
| BK | Slurry Seal | SY | 14000 | $5.20 | $72,800.00 |
| BL | Pot Hole Repair (per/SY) | SY | 50 | $92.60 | $4,630.00 |
| BM | Crack Seal | LF | 650 | $2.18 | $1,417.00 |
| BN | 6 inch SABC # 1 Base Course | TON | 2400 | $29.13 | $69,912.00 |
| BO | 3 inch AC Binder Course | TON | 50 | $223.69 | $11,184.50 |
| BP | AC Surface Course Per Inch | TON | 1500 | $122.97 | $184,455.00 |
| BQ | Surface Sterilization | SY | 3500 | $1.04 | $3,640.00 |
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | 25000 | $2.08 | $52,000.00 |
| BS | reflective yellow/with layout | SF | 10000 | $1.51 | $15,100.00 |
| BT | reflective white/with layout | SF | 5000 | $1.51 | $7,550.00 |
| BU | Prime Coat | SY | 1000 | $0.79 | $790.00 |
| BV | Haul Spread Asphalt Millings | TON | 50 | $10.40 | $520.00 |
| BW | Demo Curb & Gutter | LF | 1000 | $9.36 | $9,360.00 |
| BX | Hooded Catch basin 2x3x4 | EA | 2 | $1,872.72 | $3,745.44 |
| BY | Slurry seal Emulsion | SY | 1200 | $5.20 | $6,240.00 |
| BZ | Rem /Reinstall wheel stops | EA | 25 | $41.62 | $1,040.50 |
| CA | New Wheel Stops | EA | 50 | $83.23 | $4,161.50 |
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | 500 | $4.16 | $2,080.00 |
| CC | Reserved | N/A | 0 | ||
| CD | Demo Wheel Stops | EA | 10 | $20.81 | $208.10 |
| GRASSING | |||||
| CE | Bermuda Sod 419 | SY | 1000 | $5.72 | $5,720.00 |
| CF | Hydro seed large area's 80,000 to 350,000 | SY | 100000 | $0.49 | $49,000.00 |
| CG | Centipede Sod | SY | 250 | $5.72 | $1,430.00 |
| CH | Hydroseed and Finish Grade 1 to 80,000 | SY | 10000 | $0.56 | $5,600.00 |
| CONCRETE PAVING | |||||
| CI | New 24 Inch Concrete Curb and Gutter | LF | 600 | $18.21 | $10,926.00 |
| CJ | Replace 24 inch Concrete Curb and Gutter | LF | 1500 | $30.69 | $46,035.00 |
| CK | Remove and Replace Sidewalk 4" thick (0-200 SF) | SF | 10 | $15.61 | $156.10 |
| CL | Remove and Replace Sidewalk 4" thick (over 200 SF) | SF | 1250 | $7.80 | $9,750.00 |
| CM | New Sidewalk 4 Inches (0-200 SF) | SF | 100 | $7.28 | $728.00 |
| CN | New Side Walk 4 Inches Thick (over 200 SF) | SF | 300 | $6.24 | $1,872.00 |
| CO | Install 650 flex PCC pavement 14" thick>5000<10000 | SY | 5000 | $74.39 | $371,950.00 |
| CP | Install 650 flex PCC pavement 14" thick>1000<5000 | SY | 1250 | $81.42 | $101,775.00 |
| CQ | Install 650 flex PCC pavement 14" thick>1<1000 | SY | 250 | $105.92 | $26,480.00 |
| CR | Partial depth spall repairs-epoxy bonded PCC | SF | 125 | $124.85 | $15,606.25 |
| CS | Full depth (up to T=14") spall repair | SF | 125 | $140.45 | $17,556.25 |
| CT | Provide/install 1" dia smooth dowels-24"L,drill&epoxy | EA | 50 | $13.53 | $676.50 |
| CU | Provide/install 1-1/2" dia smooth dowels-24"L,drill&epoxy | EA | 200 | $17.69 | $3,538.00 |
| CV | Provide/install #3 rebars, 0.376LBS/LF | PND | 625 | $1.04 | $650.00 |
| CW | Provide/install #4 rebars, 0.668LBS/LF | PND | 1250 | $2.08 | $2,600.00 |
| CX | Provide/install #5 rebars, 1.043LBS/LF | PND | 1250 | $2.08 | $2,600.00 |
| CY | Provide/install #5 deformed tie bars-2.5' L (new pavement) | EA | 375 | $7.55 | $2,831.25 |
| CZ | Provide/install 3/4" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.55 | $943.75 |
| DA | Provide/install 1" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.55 | $943.75 |
| DB | Provide/install 1-1/2" dia smooth dowels-24"L (new pavement) | EA | 200 | $14.57 | $2,914.00 |
| DC | Provide/install expansion joint 3/4" cork | SF | 375 | $9.36 | $3,510.00 |
| DD | Provide/install expansion joint 1-1/2" cork | SF | 625 | $17.43 | $10,893.75 |
| DE | Provide & install aircraft tie-down | EA | 4 | $520.20 | $2,080.80 |
| DF | Weld wire mesh W2.5 x W2.5 | SF | 500 | $1.61 | $805.00 |
| DG | Concrete joint resealing incl backer mat'l replacement | LF | 1000 | $6.24 | $6,240.00 |
| DH | Crack routing/sealing (PCC) using crack saw | LF | 100 | $9.63 | $963.00 |
| DI | Crack routing/sealing (PCC) using crack saw (up to 2"W) | LF | 50 | $13.53 | $676.50 |
| DJ | Saw cut reservoir then provide & install joint sealant & backer mat'l | LF | 1800 | $6.24 | $11,232.00 |
| DK | Joint seal neopherene compression seal | LF | 5000 | $6.24 | $31,200.00 |
| DL | Sawcutting concrete to 4" 1 to 1000 | LF | 100 | $4.16 | $416.00 |
| DM | Sawcutting concrete full depth / LF inch | LF | 40000 | $1.24 | $49,600.00 |
| DN | Concrete Driveways 4" thick 1 to 100 SQ-YD, fiber mesh reinforced with 6 inch thickened edge see detail in Section 03300 | SY | 440 | $62.42 | $27,464.80 |
| DO | Expansion Board 4" wide (fiber) 1/2 thick | LF | 125 | $4.16 | $520.00 |
| DP | Expansion Board 14" wide (Cork) 1/2 thick | LF | 2500 | $9.36 | $23,400.00 |
| DQ | Joint sealer 1/2" wide with backer rod 1 to 100000 LF(Silicone) to include green saw and widen joint | LF | 500 | $9.36 | $4,680.00 |
| DR | Joint sealer 1/2" wide with backer rod 10000 to 50000 LF(Silicone) to include green saw and widen joint | LF | 5000 | $5.57 | $27,850.00 |
| DS | Remove Concrete Pavement 1" to 6 thick with disposal | SY | 500 | $15.61 | $7,805.00 |
| DT | Remove Concrete Pavement 6" to 14" thick with disposal | SY | 5000 | $14.57 | $72,850.00 |
| DU | Install 650 Flex concrete PCC per inch thickness per Square Yard to include white pigmented curing compound | SY | 26000 | $7.55 | $196,248.00 |
| PAVEMENT MARKINGS | |||||
| DV | Paint Removal Air Field 0to 50,000 SF | SF | 50000 | $2.18 | $109,000.00 |
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | 100000 | $2.03 | $203,000.00 |
| DX | Paint Removal Air Field 100,000 to Infinity | SF | 100000 | $1.66 | $166,000.00 |
| DY | Rubber Removal Airfield 0 to 400,000 | SF | 400000 | $0.10 | $40,000.00 |
| DZ | reflective yellow/with layout >10000 <500000 | SF | 10000 | $1.54 | $15,400.00 |
| EA | Reflective white/with layout <10000 | SF | 9999 | $1.54 | $15,398.46 |
| EB | reflective white/with layout >10000 <500000 | SF | 10000 | $1.38 | $13,800.00 |
| EC | Black Non Reflective >5000 <100000 | SF | 5000 | $1.19 | $5,950.00 |
| ED | Yellow Non Reflective >10000<75,000 | SF | 10000 | $1.38 | $13,800.00 |
| EE | Red Non Reflective <5000 | SF | 5000 | $1.36 | $6,800.00 |
| EF | Red Non Reflective >5000 <75000 | SF | 75000 | $1.19 | $89,250.00 |
| Chain Link Fence& Gates | |||||
| EG | 6 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $26.90 | $269,000.00 |
| EH | 7 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $39.54 | $395,400.00 |
| EI | Double Gate's with 25x6 foot clear opening with 3 strands barbed wire | EA | 15 | $1,404.54 | $21,068.10 |
| EJ | Double Gate's with 25x7 foot clear opening with 3 strands barbed wire | EA | 15 | $1,794.69 | $26,920.35 |
| EK | Personal Gate 4 x 6 foot high clear opening with 3 strands barbed wire. | EA | 15 | $338.13 | $5,071.95 |
| EL | Personal Gate 4 x 7 foot high clear opening with 3 strands barbed wire. | EA | 15 | $400.55 | $6,008.25 |
| $3,923,413.68 |
&CPage &P of &[3
OptionYear3
| Exihibit A | |||||
| Contract: FA4803-11-D-0008 | |||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||
| Option Year 3 | Southern Mgt | ||||
| CLIN | Description | ||||
| 3001 | U/I | QTY | PRICE | Total | |
| SITE WORK/GENERAL TASK | |||||
| AA | Mobilization per Delivery Order, | EA | 6 | $3,183.62 | $19,101.72 |
| AB | Back fill (Unwashed Sand) | TON | 100 | $16.72 | $1,672.00 |
| AC | Back fill (Flowable Fill) | CY | 10 | $100.29 | $1,002.90 |
| AD | Back fill (Pea Gravel) | TON | 10 | $13.80 | $138.00 |
| AE | 4 inch sewer line service | LF | 125 | $37.14 | $4,642.50 |
| AF | 4 inch electrical conduit | LF | 125 | $15.92 | $1,990.00 |
| AG | Water line service up to two inch | LF | 50 | $37.14 | $1,857.00 |
| AH | Hauling | CY | 100 | $5.30 | $530.00 |
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | 125 | $33.96 | $4,245.00 |
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | 500 | $132.65 | $66,325.00 |
| AK | Utility Boring, Horizontal, 24 in dia. | LF | 250 | $313.06 | $78,265.00 |
| AL | Cross tie timber walls/max 48"H | SF | 1500 | $12.73 | $19,095.00 |
| AM | Top Soil 4 inches thick and spread | SY | 5000 | $2.93 | $14,650.00 |
| EARTH WORK | |||||
| AN | Sand Clay Fill | CY | 450 | $12.73 | $5,728.50 |
| AO | Surface Preparation | SY | 114000 | $1.16 | $132,240.00 |
| AP | Subgrade Preparation +or-3" | SY | 72000 | $5.05 | $363,600.00 |
| AQ | Unclassified Excavation including haul off site | CY | 1750 | $15.92 | $27,860.00 |
| CLEARING AND GRUBBING | |||||
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | 1 | $5,306.04 | $5,306.04 |
| AS | Remove Trees 6 " to 12 " | EA | 24 | $265.30 | $6,367.20 |
| AT | Remove Trees 12 " to 18 " | EA | 24 | $424.48 | $10,187.52 |
| AU | Remove Trees 18 " to 28 " | EA | 12 | $530.60 | $6,367.20 |
| EROSION CONTRTOL | |||||
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | 1 | $1,485.69 | $1,485.69 |
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | 1 | $3.71 | $3.71 |
| AX | Anchored Straw Bale | EA | 50 | $9.02 | $451.00 |
| STORM WATER | |||||
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | 200 | $313.06 | $62,612.00 |
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | 10 | $2,016.30 | $20,163.00 |
| BA | 18 Inch RCP Class III | LF | 150 | $42.45 | $6,367.50 |
| BB | 24 Inch RCP Class III | LF | 225 | $44.57 | $10,028.25 |
| BC | 36 Inch RCP Class III | LF | 100 | $50.94 | $5,094.00 |
| BD | Reset Valve Box | EA | 100 | $53.06 | $5,306.00 |
| BE | 4" Plastic Under drain with Sock | LF | 250 | $10.08 | $2,520.00 |
| BF | Convert Inlets w/frame and grate | EA | 2 | $848.97 | $1,697.94 |
| BG | Florida Catch Basin | EA | 5 | $2,122.42 | $10,612.10 |
| ASPHALT PAVING | |||||
| BH | Asphalt Emulsion | SY | 100 | $1.92 | $192.00 |
| BI | Petrotac Fabric | SF | 100 | $5.30 | $530.00 |
| BJ | Hand Asphalt Placement | TON | 100 | $297.14 | $29,714.00 |
| BK | Slurry Seal | SY | 14000 | $5.30 | $74,200.00 |
| BL | Pot Hole Repair (per/SY) | SY | 50 | $94.45 | $4,722.50 |
| BM | Crack Seal | LF | 650 | $2.22 | $1,443.00 |
| BN | 6 inch SABC # 1 Base Course | TON | 2400 | $29.71 | $71,304.00 |
| BO | 3 inch AC Binder Course | TON | 50 | $228.16 | $11,408.00 |
| BP | AC Surface Course Per Inch | TON | 1500 | $130.53 | $195,795.00 |
| BQ | Surface Sterilization | SY | 3500 | $1.06 | $3,710.00 |
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | 25000 | $2.12 | $53,000.00 |
| BS | reflective yellow/with layout | SF | 10000 | $1.54 | $15,400.00 |
| BT | reflective white/with layout | SF | 5000 | $1.54 | $7,700.00 |
| BU | Prime Coat | SY | 1000 | $0.81 | $810.00 |
| BV | Haul Spread Asphalt Millings | TON | 50 | $10.61 | $530.50 |
| BW | Demo Curb & Gutter | LF | 1000 | $9.55 | $9,550.00 |
| BX | Hooded Catch basin 2x3x4 | EA | 2 | $1,910.17 | $3,820.34 |
| BY | Slurry seal Emulsion | SY | 1200 | $5.30 | $6,360.00 |
| BZ | Rem /Reinstall wheel stops | EA | 25 | $42.45 | $1,061.25 |
| CA | New Wheel Stops | EA | 50 | $84.89 | $4,244.50 |
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | 500 | $4.24 | $2,120.00 |
| CC | Reserved | N/A | 0 | ||
| CD | Demo Wheel Stops | EA | 10 | $21.23 | $212.30 |
| GRASSING | |||||
| CE | Bermuda Sod 419 | SY | 1000 | $5.83 | $5,830.00 |
| CF | Hydro seed large area's 80,000 to 350,000 | SY | 100000 | $0.50 | $50,000.00 |
| CG | Centipede Sod | SY | 250 | $5.83 | $1,457.50 |
| CH | Hydroseed and Finish Grade 1 to 80,000 | SY | 10000 | $0.57 | $5,700.00 |
| CONCRETE PAVING | |||||
| CI | New 24 Inch Concrete Curb and Gutter | LF | 600 | $18.57 | $11,142.00 |
| CJ | Replace 24 inch Concrete Curb and Gutter | LF | 1500 | $31.30 | $46,950.00 |
| CK | Remove and Replace Sidewalk 4" thick (0-200 SF) | SF | 10 | $15.92 | $159.20 |
| CL | Remove and Replace Sidewalk 4" thick (over 200 SF) | SF | 1250 | $7.96 | $9,950.00 |
| CM | New Sidewalk 4 Inches (0-200 SF) | SF | 100 | $7.43 | $743.00 |
| CN | New Side Walk 4 Inches Thick (over 200 SF) | SF | 300 | $6.36 | $1,908.00 |
| CO | Install 650 flex PCC pavement 14" thick>5000<10000 | SY | 5000 | $75.88 | $379,400.00 |
| CP | Install 650 flex PCC pavement 14" thick>1000<5000 | SY | 1250 | $83.05 | $103,812.50 |
| CQ | Install 650 flex PCC pavement 14" thick>1<1000 | SY | 250 | $108.04 | $27,010.00 |
| CR | Partial depth spall repairs-epoxy bonded PCC | SF | 125 | $127.35 | $15,918.75 |
| CS | Full depth (up to T=14") spall repair | SF | 125 | $143.26 | $17,907.50 |
| CT | Provide/install 1" dia smooth dowels-24"L,drill&epoxy | EA | 50 | $13.80 | $690.00 |
| CU | Provide/install 1-1/2" dia smooth dowels-24"L,drill&epoxy | EA | 200 | $18.04 | $3,608.00 |
| CV | Provide/install #3 rebars, 0.376LBS/LF | PND | 625 | $1.06 | $662.50 |
| CW | Provide/install #4 rebars, 0.668LBS/LF | PND | 1250 | $2.12 | $2,650.00 |
| CX | Provide/install #5 rebars, 1.043LBS/LF | PND | 1250 | $2.12 | $2,650.00 |
| CY | Provide/install #5 deformed tie bars-2.5' L (new pavement) | EA | 375 | $7.70 | $2,887.50 |
| CZ | Provide/install 3/4" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.70 | $962.50 |
| DA | Provide/install 1" dia smooth dowels-24"L (new pavement) | EA | 125 | $7.70 | $962.50 |
| DB | Provide/install 1-1/2" dia smooth dowels-24"L (new pavement) | EA | 200 | $14.86 | $2,972.00 |
| DC | Provide/install expansion joint 3/4" cork | SF | 375 | $9.55 | $3,581.25 |
| DD | Provide/install expansion joint 1-1/2" cork | SF | 625 | $17.78 | $11,112.50 |
| DE | Provide & install aircraft tie-down | EA | 4 | $530.60 | $2,122.40 |
| DF | Weld wire mesh W2.5 x W2.5 | SF | 500 | $1.64 | $820.00 |
| DG | Concrete joint resealing incl backer mat'l replacement | LF | 1000 | $6.36 | $6,360.00 |
| DH | Crack routing/sealing (PCC) using crack saw | LF | 100 | $9.82 | $982.00 |
| DI | Crack routing/sealing (PCC) using crack saw (up to 2"W) | LF | 50 | $13.80 | $690.00 |
| DJ | Saw cut reservoir then provide & install joint sealant & backer mat'l | LF | 1800 | $6.36 | $11,448.00 |
| DK | Joint seal neopherene compression seal | LF | 5000 | $6.36 | $31,800.00 |
| DL | Sawcutting concrete to 4" 1 to 1000 | LF | 100 | $4.24 | $424.00 |
| DM | Sawcutting concrete full depth / LF inch | LF | 40000 | $1.26 | $50,400.00 |
| DN | Concrete Driveways 4" thick 1 to 100 SQ-YD, fiber mesh reinforced with 6 inch thickened edge see detail in Section 03300 | SY | 440 | $63.67 | $28,014.80 |
| DO | Expansion Board 4" wide (fiber) 1/2 thick | LF | 125 | $4.24 | $530.00 |
| DP | Expansion Board 14" wide (Cork) 1/2 thick | LF | 2500 | $9.55 | $23,875.00 |
| DQ | Joint sealer 1/2" wide with backer rod 1 to 100000 LF(Silicone) to include green saw and widen joint | LF | 500 | $9.55 | $4,775.00 |
| DR | Joint sealer 1/2" wide with backer rod 10000 to 50000 LF(Silicone) to include green saw and widen joint | LF | 5000 | $5.68 | $28,400.00 |
| DS | Remove Concrete Pavement 1" to 6 thick with disposal | SY | 500 | $15.92 | $7,960.00 |
| DT | Remove Concrete Pavement 6" to 14" thick with disposal | SY | 5000 | $14.86 | $74,300.00 |
| DU | Install 650 Flex concrete PCC per inch thickness per Square Yard to include white pigmented curing compound | SY | 26000 | $7.70 | $200,200.00 |
| PAVEMENT MARKINGS | |||||
| DV | Paint Removal Air Field 0to 50,000 SF | SF | 50000 | $2.22 | $111,000.00 |
| DW | Paint Removal Air Field 50,000to 100,000 SF | SF | 100000 | $2.07 | $207,000.00 |
| DX | Paint Removal Air Field 100,000 to Infinity | SF | 100000 | $1.69 | $169,000.00 |
| DY | Rubber Removal Airfield 0 to 400,000 | SF | 400000 | $0.11 | $44,000.00 |
| DZ | reflective yellow/with layout >10000 <500000 | SF | 10000 | $1.57 | $15,700.00 |
| EA | Reflective white/with layout <10000 | SF | 9999 | $1.57 | $15,698.43 |
| EB | reflective white/with layout >10000 <500000 | SF | 10000 | $1.41 | $14,100.00 |
| EC | Black Non Reflective >5000 <100000 | SF | 5000 | $1.21 | $6,050.00 |
| ED | Yellow Non Reflective >10000<75,000 | SF | 10000 | $1.41 | $14,100.00 |
| EE | Red Non Reflective <5000 | SF | 5000 | $1.39 | $6,950.00 |
| EF | Red Non Reflective >5000 <75000 | SF | 75000 | $1.21 | $90,750.00 |
| Chain Link Fence& Gates | |||||
| EG | 6 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $27.44 | $274,400.00 |
| EH | 7 foot Chain link fence with 3 strands barbed wire | LF | 10000 | $40.33 | $403,300.00 |
| EI | Double Gate's with 25x6 foot clear opening with 3 strands barbed wire | EA | 15 | $1,432.63 | $21,489.45 |
| EJ | Double Gate's with 25x7 foot clear opening with 3 strands barbed wire | EA | 15 | $1,830.58 | $27,458.70 |
| EK | Personal Gate 4 x 6 foot high clear opening with 3 strands barbed wire. | EA | 15 | $344.89 | $5,173.35 |
| EL | Personal Gate 4 x 7 foot high clear opening with 3 strands barbed wire. | EA | 15 | $408.56 | $6,128.40 |
| $4,011,365.89 |
&CPage &P of &[4
OptionYear4
| Exihibit A | |||||
| Contract: FA4803-11-D-0008 | |||||
| REPAIR BASE PAVEMENTS VLSB 10-0064 | |||||
| Option Year 4 | Southern Mgt | ||||
| CLIN | Description | ||||
| 4001 | U/I | QTY | PRICE | Total | |
| SITE WORK/GENERAL TASK | |||||
| AA | Mobilization per Delivery Order, | EA | 6 | $3,247.29 | $19,483.74 |
| AB | Back fill (Unwashed Sand) | TON | 100 | $17.05 | $1,705.00 |
| AC | Back fill (Flowable Fill) | CY | 10 | $102.30 | $1,023.00 |
| AD | Back fill (Pea Gravel) | TON | 10 | $14.08 | $140.80 |
| AE | 4 inch sewer line service | LF | 125 | $37.88 | $4,735.00 |
| AF | 4 inch electrical conduit | LF | 125 | $16.24 | $2,030.00 |
| AG | Water line service up to two inch | LF | 50 | $37.88 | $1,894.00 |
| AH | Hauling | CY | 100 | $5.41 | $541.00 |
| AI | Key Stone Retaining Wall with Back Fill and footings | LF | 125 | $34.64 | $4,330.00 |
| AJ | Utility Boring, Horizontal, 6 in dia. | LF | 500 | $135.30 | $67,650.00 |
| AK | Utility Boring, Horizontal, 24 in dia. | LF | 250 | $319.32 | $79,830.00 |
| AL | Cross tie timber walls/max 48"H | SF | 1500 | $12.98 | $19,470.00 |
| AM | Top Soil 4 inches thick and spread | SY | 5000 | $2.99 | $14,950.00 |
| EARTH WORK | |||||
| AN | Sand Clay Fill | CY | 450 | $12.98 | $5,841.00 |
| AO | Surface Preparation | SY | 114000 | $1.18 | $134,520.00 |
| AP | Subgrade Preparation +or-3" | SY | 72000 | $5.15 | $370,800.00 |
| AQ | Unclassified Excavation including haul off site | CY | 1750 | $16.24 | $28,420.00 |
| CLEARING AND GRUBBING | |||||
| AR | Clearing and grubbing/all roots and stumps1-500 ACRES | ACRE | 1 | $5,412.16 | $5,412.16 |
| AS | Remove Trees 6 " to 12 " | EA | 24 | $270.61 | $6,494.64 |
| AT | Remove Trees 12 " to 18 " | EA | 24 | $432.70 | $10,384.80 |
| AU | Remove Trees 18 " to 28 " | EA | 12 | $541.21 | $6,494.52 |
| EROSION CONTRTOL | |||||
| AV | Erosion Control Temporary Seeding /Acre 1-500 | ACRE | 1 | $1,515.40 | $1,515.40 |
| AW | Silt Fence Erosion Control Temporary Seeding 1 to 2500 | LF | 1 | $3.78 | $3.78 |
| AX | Anchored Straw Bale | EA | 50 | $9.20 | $460.00 |
| STORM WATER | |||||
| AY | Headwalls 8 inch Thick x 15 Long x 5' H RPCC | CY | 200 | $319.32 | $63,864.00 |
| AZ | 4' Dia. Manhole 6 ' Deep precast concrete w/frame & cover | EA | 10 | $2,056.63 | $20,566.30 |
| BA | 18 Inch RCP Class III | LF | 150 | $43.30 | $6,495.00 |
| BB | 24 Inch RCP Class III | LF | 225 | $45.46 | $10,228.50 |
| BC | 36 Inch RCP Class III | LF | 100 | $51.96 | $5,196.00 |
| BD | Reset Valve Box | EA | 100 | $54.12 | $5,412.00 |
| BE | 4" Plastic Under drain with Sock | LF | 250 | $10.28 | $2,570.00 |
| BF | Convert Inlets w/frame and grate | EA | 2 | $865.95 | $1,731.90 |
| BG | Florida Catch Basin | EA | 5 | $2,164.87 | $10,824.35 |
| ASPHALT PAVING | |||||
| BH | Asphalt Emulsion | SY | 100 | $1.96 | $196.00 |
| BI | Petrotac Fabric | SF | 100 | $5.41 | $541.00 |
| BJ | Hand Asphalt Placement | TON | 100 | $303.08 | $30,308.00 |
| BK | Slurry Seal | SY | 14000 | $5.41 | $75,740.00 |
| BL | Pot Hole Repair (per/SY) | SY | 50 | $96.34 | $4,817.00 |
| BM | Crack Seal | LF | 650 | $2.26 | $1,469.00 |
| BN | 6 inch SABC # 1 Base Course | TON | 2400 | $30.30 | $72,720.00 |
| BO | 3 inch AC Binder Course | TON | 50 | $232.72 | $11,636.00 |
| BP | AC Surface Course Per Inch | TON | 1500 | $133.14 | $199,710.00 |
| BQ | Surface Sterilization | SY | 3500 | $1.08 | $3,780.00 |
| BR | Asphalt Pavement Removal Per Inch thickness (asphalt) 1 to 25,000.00 | SY | 25000 | $2.16 | $54,000.00 |
| BS | reflective yellow/with layout | SF | 10000 | $1.57 | $15,700.00 |
| BT | reflective white/with layout | SF | 5000 | $1.57 | $7,850.00 |
| BU | Prime Coat | SY | 1000 | $0.83 | $830.00 |
| BV | Haul Spread Asphalt Millings | TON | 50 | $10.82 | $541.00 |
| BW | Demo Curb & Gutter | LF | 1000 | $9.74 | $9,740.00 |
| BX | Hooded Catch basin 2x3x4 | EA | 2 | $1,948.37 | $3,896.74 |
| BY | Slurry seal Emulsion | SY | 1200 | $5.41 | $6,492.00 |
| BZ | Rem /Reinstall wheel stops | EA | 25 | $43.30 | $1,082.50 |
| CA | New Wheel Stops | EA | 50 | $86.59 | $4,329.50 |
| CB | Sawcutting asphalt to 4" 1 to 1000 | LF | 500 | $4.32 | $2,160.00 |
| CC | Reserved | N/A | 0 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.