This document provides details for a forthcoming solicitation seeking construction services under the Simplified Acquisition Base Engineering Requirements (SABER) program. The Air Force intends to issue solicitation FA4610-18-R-0001 to establish multiple indefinite-delivery/indefinite-quantity contracts with 8(a) small businesses located in California. Work will include various trades such as carpentry, asbestos abatement, demolition, mechanical, electrical, plumbing, concrete, and painting at Vandenberg Air Force Base and associated sites. The total ceiling value is $60 million over the life of the contracts. The Air Force plans to award three IDIQ contracts following a competitive 8(a) small business set-aside. The North American Industry Classification System code is 236220 and size standard is $36.5 million. The pre-solicitation notice provides point of contact information and advises interested parties to monitor the Federal Business Opportunities website for release of the solicitation planned for February 2, 2018.
FA461018R0001-0001 SF30
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SABER_Q&A.pdf | ||
| Saber_Site_Validation_Visit_Sign-in_FBO.pdf | ||
| Saber_Preproposal_Conference.pdf | ||
| 18R0001_RFP_Conformed_to_Amend_0001.pdf | ||
| Attch_8D_AF3064_3065_Spreadsheet.xls | XLS spreadsheet | |
| Attch_8C_SchMatlSubmittals.xls | XLS spreadsheet | |
| Attch_4_Ventura_County_CA170025_Mod-15_20171013.pdf | ||
| Attch_8A_Demo_Project_SOO.pdf | ||
| Attch_3_SB_County_CA170023_Mod-15_20171013.pdf | ||
| Attch_6_Coefficient_Worksheet_20180125.xlsx | XLSX spreadsheet | |
| FA461018R0001_RFP_20180226.pdf | ||
| Attch_1_SABER_Master_Specs_20180129.pdf | ||
| Attch_8B_Demo_Project_Drawings.pdf | ||
| Attch_2_VAFB_FacExcel_Stds_20170418.pdf | ||
| Attch_7_Executive_Summary_Sheet.docx | DOCX document | |
| Attch_5_Other_County_CA170029_Mod-26_20171124.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The puropose of this modif ication is to correct Sections L & M to reflect the correct positions stated in 01 31 01 of the Master Specif ications.
All other terms and conditions remain unchanged.
POC: Damian Perez, 605-8718, damian.perez.1@us.af.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Mar-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA461018R0001
X 9B. DATED (SEE ITEM 11)
26-Feb-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Mar-2018
CODE
FA4610 - 30TH CONS
1515 ICELAND AVE. (BLDG 8500), RM 150
VANDENBERG AFB CA 93437-5212
FA4610 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA461018R0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
INSTRUCTION TO OFFERORS
L-1 GENERAL INSTRUCTIONS
1.0 General Instructions.
1.1. This section provides general guidance for preparing proposals, as wells as specific instructions on the format and content of the proposal. Throughout this section, the term “offeror” means the prime contractor submitting the proposal. The offeror’s proposal must include all data and information requested by this Section L and must be submitted in accordance with (IAW) these instructions. Any offeror who submits an incomplete package may be considered non-responsive. The offer shall be compliant with the requirements as stated in the Request for Proposal (RFP). A proposal that is sufficiently documented to support cost/price and technical requirements in a complete, orderly and detailed manner will enable the Government to perform a thorough and fair evaluation. Non-compliance with the instructions and RFP may result in an unfavorable proposal evaluation and may be grounds to eliminate the proposal from consideration for contract award. Offerors are cautioned that the Government does not assume the duty to search for data to cure inconsistencies or discrepancies identified in the offeror’s proposal.
1.2. The offeror’s proposal shall be clear, concise, and shall include sufficient detail to support for effective evaluation and for substantiating the validity of stated claims. The proposal should not simply rephrase or restate the Government’s requirements; rather, the proposal shall provide convincing rationale to address how the offeror intends to meet these requirements. Offerors shall assume that the Government has no prior knowledge of their facilities and experience and will base its evaluation on the information presented in the offeror’s proposal. Offerors are also advised that each offeror’s proposal represents the offeror’s best efforts and most complete responses to the RFP. Offerors are cautioned to thoroughly consider all potential costs, risks, economic trends and the proposal environment when developing proposed coefficients. Contract coefficients will remain fixed for the life of the resulting contract and no allowances will be made after award.
1.3. IAW FAR Subpart 4.8, the Government will retain one (1) copy of all unsuccessful proposals. Unless the offeror requests otherwise, the Government will destroy extra copies of such unsuccessful proposals.
2.0 Type of Acquisition.
This acquisition is a competitive 8(a) small business set-aside limited to contractors possessing a California General Contractor’s License (Type A, General Engineering Contractor, and/or Type B, General Building Contractor) with a Small Business Administration (SBA) bona-fide place of business in the state of California.
For this acquisition, selection of the best value offeror(s) will be made using Lowest Priced Technically Acceptable (LPTA) source selection procedures. This solicitation will result in the award of three (3) Firm- Fixed-Price (FFP), Indefinite-Delivery/Indefinite-Quantity (IDIQ) contracts. Proposals may only be submitted by Small Business Certified 8(a) Small Business firms listed under the 236220 North American Industry Classification System Code (NAICS).
3.0 Construction Magnitude.
The total contract value, regardless of the number of contracts awarded for this acquisition is not to exceed the programmed ceiling amount of $60,000,000.00. The estimated magnitude of the task orders will vary between task orders and will be identified on each task order request. Task orders will range in value from $2,000.00 to $5,000,000.00.
4.0 Discrepancies and Ambiguities.
If an offeror believes the requirements in these instructions contain an error, omission, ambiguity, or are otherwise unsound, the offeror shall immediately notify the Contracting Officer (CO) in writing with supporting rationale No Later Than (NLT) seven (7) calendar days after the RFP release date. The offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without discussions.
5.0 Mistakes.
Mistakes in an offeror’s proposal shall be handled IAW FAR 14.407-4 as referenced in FAR 15.508.
6.0 Exchanges With Offerors After Receipt of Proposals.
6.1. Award without discussions.
IAW FAR 15.306(a), offerors may be given the opportunity to clarify certain aspects of the proposal or resolve minor or clerical errors. Clarifications shall be documented on, and conducted via transmittal of, Evaluation Notices (EN) to the applicable offeror. Each EN shall clearly indicate that the type of exchange being conducted is “Clarification”.
6.2. Communications with offerors before establishment of the Competitive Range.
After the decision to conduct discussions has been made and prior to establishment of the Competitive Range, the CO may enter into limited “Communications” with offerors only as described in FAR 15.306(b).
Communications shall be documented on, and conducted via transmittal of, ENs to the applicable offeror. Each EN shall clearly indicated that the type of exchange being conducted is “Communications”.
6.3. Competitive Range.
If discussions are to be conducted, the CO shall establish the Competitive Range comprised of all the most highly rated proposals based on the ratings of each proposal against all evaluation criteria, unless the range is further reduced for purposes of efficiency. IAW FAR 15.306(c), the CO may limit the number of proposals in the Competitive Range to the greatest number that will permit an efficient competition among the most highly rated proposals. IAW FAR 15.503(a)(1), the CO shall provide written notification to unsuccessful offerors of exclusion from the Competitive Range and/or elimination from the competition.
6.4. Exchanges with offerors after establishment of the Competitive Range.
Discussions, negotiations in a competitive acquisition, are tailored to each offeror’s proposal and will be conducted by the CO with every offeror within the Competitive Range. At a minimum, during discussions, the CO shall indicate to, or discuss with, each offeror in the Competitive Range any deficiencies or significant weaknesses that have been identified during the evaluation. Discussions shall be documented on, and conducted via transmittal of, ENs to the applicable offeror. Each EN shall clearly indicate that the type of exchange being conducted is “Discussions”.
6.5. Discussions.
The Government intends to award without discussions. However, the Government reserves the right to conduct discussions if determined necessary. If discussions or requests for revised proposals conducted or requested by the Government, the coefficient prices identified in Schedule B of the Final Proposal Revision (FPR) shall be valid through the proposal acceptance period stated in the request for FPR.
7.0 Amendment of Solicitation Prior to Closing Date.
The Government reserves the right to revise or amend the specifications, drawings, or the solicitation prior to the proposal due time/date. Changes will be communicated by amendment(s) to the Request for Proposal (RFP) and posted to the Federal Business Opportunities (FedBizOpps) website (www.fbo.gov). If such amendments require material changes in quantities or prices, the proposal due time/date may be postponed by enough days to enable offerors to revise their proposals. In such cases, the amendment will include an announcement of the new proposal due time/date. Each offeror is required to acknowledge all solicitation amendments in its proposal, or by written notification which includes a reference to the solicitation and amendment numbers.
8.0 Electronic Reference Documents.
All referenced documents for this solicitation are available on the FedBizOpps website. Potential Offerors are encouraged to subscribe to the FedBizOpps notice via the “Watch This Opportunity” radio button in order to receive real-time notice updates via email notification from FedBizOpps.
9.0. Contract Documents.
Sections K, L and M apply only to the solicitation phase of this acquisition. These sections will be removed and will not be included in the resulting contract documents.
10.0 Points of Contact.
The POCs for this acquisition are the Contracting Officer (CO), Jeffrey Grelck, and the Contract Specialist (CS), Damian Perez. Written requests for clarification shall be sent to the CO and courtesy copied to the CS.
Address any questions or concerns to the POCs using the following contact information:
Jeffrey Grelck Damian Perez Contracting Officer Contract Specialist
30 CONS/PKA 30 CONS/PKA
1515 Iceland Ave, Bldg. 8500, Rm. 150 1515 Iceland Ave, Bldg. 8500 Rm. 150 Vandenberg AFB, CA 93437 Vandenberg AFB, CA 93437 Email: jeffrey.grelck@us.af.mil Email: damian.perez.1@us.af.mil Tel: 805-606-9760 Tel: 805-605-8718
L-2 PROPOSAL PREPARATION INSTRUCTIONS
1.0 The proposal package must be completed and returned to the address in Block 7 of the SF 1442, prior to the time set for closing of proposals, see Block 13A of the SF 1442.
1.1. To ensure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein.
Proposals must be complete, self-sufficient, and respond directly to the requirements of this solicitation.
Alternate proposals will not be accepted. The response shall consist of two (2) separate volumes:
Volume I - Executed Contract Documentation & Price Proposal Volume II - Technical Proposal
1.2. Formatting.
1.2.1. A cover sheet shall be included in each binder. The cover sheet shall clearly identify the company name, solicitation number, and volume number. Each binder / CD-ROM / DVD-ROM will be labeled according to the following format:
FA4610-18-R-0001
COMPANY NAME
Volume I - Executed Contract Documentation & Price Proposal “Original” or
FA4610-18-R-0001
COMPANY NAME
Volume II - Technical Proposal “Original”
1.2.2. The header of each page shall include the company name, solicitation number, and page number.
1.2.3. Proposals shall be printed on 8 1/2” x 11” (letter) paper, white or ivory stock. Charts, tables or diagrams may not exceed 11” x 17” (legal) paper. Pages exceeding these dimensions will be removed from the proposal and not evaluated.
mailto:jeffrey.grelck@us.af.mil mailto:damian.perez.1@us.af.mil
1.2.4. A page is defined as one (1) side of a sheet of 8 ½” x 11” paper containing information to include all appendices, charts, graphs, diagrams, tables, photographs, et cetera. If information is printed on one (1) side of 11” x 17” paper, the sheet will be counted as two (2) pages. Covers for volumes, tables of contents, indices, title pages, cross reference indices, and section dividers/tables will not be included in the page count if they are inserted solely to provide ease to the reader in locating volumes/sections of the proposal.
These pages will be included in the page count if they contain any other information (e.g. diagrams, extraneous data, etc.). Material cut sheets and/or product data included in Volume II in support of the technical proposal will not be included in the page count if the pages are clearly identified as appendices and placed at the end of the Volume II. Pages marked “This page intentionally left blank” will not be included in the page count. Pages shall be numbered sequentially by volume.
1.2.5. Each volume shall contain a glossary of all abbreviations and acronyms used, with an explanation for each.
These glossaries will not be included in the page count.
1.2.6. Type face shall not be less than 12 font, with 1” margins on all sides. Smaller, legible font size, no smaller than 6 point, may be used for the construction schedule.
1.2.7. The stated formatting requirements shall also apply to responses to ENs.
1.2.8. If proposal revisions are required by the Contracting Officer, they shall conform to the requirements of this section and must be clearly marked to show the changes, on different color stock as directed by the Contracting Officer.
1.3. Medium, Number of Copies, & Page Limitations.
1.3.1. Volumes shall be submitted in three-ring binders which lie flat when opened and with pages that are side-loaded. Staples shall not be used to bind pages. If the binder used has protective sleeves on the covers or spine (including the exterior), the offeror should not insert anything in these protective sleeves. The original copy of each volume shall also include one (1) CD-ROM/DVD-ROM with digital copies of all volume documents. Acceptable digital formats are Adobe PDF and Microsoft Excel. Elaborate bindings, brochures, color presentations, detailed art work, documentation or other embellishments are unnecessary and are not desired or required.
1.3.2. Electronic copies shall be identical to the hard copies submitted. The electronic copies shall be submitted on a CD-ROM/DVD-ROM only. Submission of electronic copies on other than CD-ROM/DVD-ROM media is not authorized and will result in an offeror being determined non-responsive and not eligible for award. The CD-ROM/DVD-ROM shall be clearly marked with the company name, solicitation number, and volume(s) included on the CD. The electronic files shall be searchable documents compatible with Adobe Reader 9 and/or Microsoft 2010.
1.3.3. Refer to the table below for guidance regarding number of copiers required and page limitations. Page limitations shall be treated as maximums. If an applicable page limitation is exceeded, the excess pages will not be read or considered in the proposal evaluation. Page limitations may also be placed on responses to Evaluation Notices (ENs) when necessary. The specified page limitations for EN responses will be identified in the ENs to offerors.
TITLE # OF COPIES MAXIMUM # OF PAGES
Volume I of Price with Executed Contract Documentation
Original and 3 copies (2 hard paper and 1 electronic)
No Page limitation
Volume II Technical Proposal Original and 3 copies (2 hard paper and 1 electronic)
50 Pages, excluding the demonstration project cost estimate;
no page limitation on the demonstration project cost estimate
1.4. The offeror should be sure to apply all appropriate markings on its proposal, including those prescribed in accordance with FAR 52.215-1(e), Restriction on disclosure and use of data, and FAR 3.104-4, Disclosure, Protection, and Marking of Contractor Bid or Proposal Information and Source Selection Information.
1.5. Other Than Certified Cost or Pricing Data.
Based on the market research, the Contracting Officer (CO) has made the determination that there is a high probability of adequate price competition expected for this acquisition. Upon evaluation of initial offers, the CO will review this determination. If, in the CO's opinion, adequate price competition does exist; no additional cost or pricing data will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this acquisition, the CO makes the determination that adequate price competition no longer exists; offerors may be required to submit additional “other than certified cost and pricing data” to the extent necessary for the CO to determine prices to be fair and reasonable.
1.6. USE OF USPS, UPS, FEDEX OR ANY OTHER COMMERCIAL SYSTEMS TO TRANSMIT SOURCE
SELECTION SENSITIVE INFORMATION.
To facilitate review and evaluation for this source selection, the Government proposes to transmit information via commercial systems. Distributed material will be identified as source selection sensitive and distribution will be strictly limited to appropriate personnel, and shall be encrypted per AFFARS MP 5315.3 paragraph 1.4.2.2.3.
1.7. Distribution.
The offeror’s complete proposal package must be received No Later Than (NLT) the proposal submission time/date listed in Block 13. A. of the SF1442. The offeror’s proposal package shall be addressed to the CO and mailed or hand-carried to the following:
30th Contracting Squadron C/o Jeffrey Grelck, Contracting Officer Tel: 805-606-9760 1515 Iceland Ave, Bldg. 8500, Rm. 150 Vandenberg AFB, CA 93437
Note: IAW FAR 15.208(b)(1), any proposal, modification, or revision, that is received at the designated Government office after the exact time specified for receipt of proposals is “late” and will not be considered unless the CO determines that the conditions at FAR 15.208(b) can be met and accepting the proposal is in the best interest of the Government.
1.8. HAND-CARRIED PROPOSALS NOTICE.
1.8.1. Offerors are cautioned that Vandenberg AFB (VAFB) has stringent visitor control procedures. Individuals not affiliated with the installation are required to obtain a visitor’s pass and must be cleared by Security Forces prior to entering VAFB. Offerors should allow sufficient time to obtain a visitor’s pass and arrive at the 30th Contracting Squadron prior to the specified time for receipt of proposals.
1.8.2. To request base access, the offeror shall provide written notification to the POCs. Requests for base access must be received at least three (3) business days prior to the requested date of entry. If the offeror cannot provide written notification to the POCs at least three (3) business days prior to the proposal due date/time, the offeror may try and schedule a time/date with the POCs to pick up the proposal package at the Visitor’s Center, Bldg. 17596, located by the VAFB Santa Maria Gate. Offerors are cautioned that it is possible the POCs may not be available to sponsor offerors on to base or to pick up proposal packages. Consequently, offerors electing to hand-carry proposal packages for submission just prior to the proposal due time/date are cautioned that they are doing so at their own risk.
1.9. Responsiveness.
1.9.1. Documents submitted in response to this solicitation must be fully responsive to and consistent with the following:
1.9.1.1. Requirements of the solicitation, SABER Master Specifications, and Government standards and regulations pertaining to the specifications.
1.9.1.2. Evaluation factors and subfactors for award identified in Section M of this solicitation.
1.9.1.3. Any limitation on the number of pages within the proposal. Pages exceeding the specified page limitations set forth in Section L will not be read or evaluated and will be removed from the proposal.
1.10. Proposal Acceptance Period.
The proposal acceptance period is specified in Block 13. D. of the SF1442. The offeror’s proposed coefficients identified in Schedule B shall be valid through the proposal acceptance period unless the Government determines it is necessary to open discussions and subsequently requests a Final Proposal Revision (FPR).
2.0 Specific Instructions, SUBMIT THE FOLLOWING:
2.1. VOLUME I – EXECUTED CONTRACT DOCUMENTATION & PRICE PROPOSAL
2.1.1. Executive Summary Sheet.
Submit a summary about the company, including the company’s CAGE code, small business categories, and identification of the name(s), email(s), and phone number(s) of the principal person(s) authorized to negotiate on behalf of and obligate the company.
2.1.2. Chapter 1 – SF 1442.
Complete applicable blanks. In doing so, the offeror agrees to the contract terms and conditions as written in the RFP Sections A through J. These sections constitute the model contract. The offeror shall also acknowledge, in writing, all amendments issued against this solicitation and include a signed copy of each amendment in this chapter of the proposal.
2.1.3. Chapter 2 – Section B.
Insert the proposed coefficient in Section B for each coefficient including the option periods. Limit coefficient to four (4) decimal places. Offerors who do not comply with this requirement shall be considered non-responsive and not eligible for award. The offeror shall also prepare and include in this chapter a coefficient worksheet and a detailed narrative identifying the costs (i.e. overhead, profit, minimum design, General & Administrative expenses, bond premium, gross receipt taxes, etc.) included in the development of the proposed coefficients. The narrative shall identify the methodology used to calculate the coefficients proposed in Section B.
2.1.4. Chapter 4 – Section K.
2.1.4.1. Complete the Representations and Certifications in Section K of the RFP. Section K shall be submitted in its entirety.
2.1.4.2. Joint Venture Agreements.
Joint ventures are allowable on competitive 8(a) small business set-asides; however, the joint venture agreement must be received by SBA prior to proposal due date and approved before award of any resulting contract. If the offeror is contemplating a joint venture on this project, the offeror must advise, in writing, its assigned SBA Business Opportunity Specialist (BOS) as soon as possible. It also recommended that the agreement be submitted to your assigned SBA BOS as soon as practicable to ensure compliance with established regulations. Any corrections and/or changes needed can be made only when your BOS has had adequate time for a thorough review before the proposal due date. NO CORRECTIONS AND/OR
CHANGES ARE ALLOWED AFTER TIME OF SUBMISSION OF PROPOSALS.
2.1.4.3. Provide a letter from the Small Business Administration (SBA) showing proof of Section 8(a) status. This letter must also evidence a SBA bona-fide office located within California. Offerors who do not comply with this requirement shall be considered non-responsive and not eligible for award.
2.1.5. Contractor’s License.
Offeror shall provide a copy of its active and current, as of the proposal due date, California General Contractor’s License Type A, General Engineering Contractor, or Type B, General Building Contractor.
2.1.6. Bonding Capacity.
Provide a letter from the offeror’s surety company, stating the offeror’s bonding capacity and ability to meet the bonding requirements ($3M single, $10M aggregate) of the resulting contract. Bonding may be obtained from a surety listed in the Department of the Treasury Circular 570 list of approved surety companies (http://www.fms.treas.gov/c570/) or other security permitted by FAR Subpart 28.2, unless prohibited by law or regulation.
2.1.7. Provide a description of the work the offeror intends to perform within its organization to meet the requirements of FAR clause 52.219-14, Limitations on Subcontracting.
2.2. VOLUME II – TECHNICAL PROPOSAL
2.2.1. General Instructions.
At a minimum, the technical volume shall be divided so that Program Management Plan, Quality Control Plan, and Demonstration Project Proposal are placed in separate tabs within the technical volume. The technical volume should be specific and complete. Legibility, clarity and coherence are very important. The technical volume will be evaluated against the technical sub-factors identified in the Basis of Award in Section M. Using the instructions below, provide as specifically as possible the actual methodology you would use for accomplishing/satisfying these sub-factors. By your proposal submission, you are representing that your firm will perform all the requirements specified in the solicitation and identified in your proposal.
Proposed performance or capabilities that exceed the minimum requirements identified in the solicitation may be incorporated into the contract, but will not result in a more favorable technical rating. Offerors must “pass” in all sub-factors of the Technical Factor in order to be determined “technically acceptable.” The standards are defined in Section M for each sub-factor.
2.2.2. Format and Specific Content.
The technical volume should address your technical solution for meeting the Government’s minimum performance or capability requirements of each technical sub-factor.
2.2.2.1. Sub-factor 1: Program Management Plan.
Offeror shall provide an effective Program Management Plan IAW the requirements in SABER Master Specifications Section 01 31 01 paragraph 1.5, Program Management Plan. The Program Management Plan shall include:
2.2.2.1.1. Position descriptions for key personnel, required minimum qualifications, required job experience (with examples, but without individual names or resumes). Key personnel at a minimum are:
• Program Manager(s)
• Project Manager(s)
• Construction Quality Control Inspector(s)
• Construction Superintendent/Job Foreman
• Lead Craftsman/Tradesman
• Quality Control Officer
• Site Safety and Health Officer
• Draftsmen/CAD Professional
2.2.2.1.2. A chart of offeror’s organizational structure detailing the roles, responsibilities, qualifications, and levels of authority for key personnel within offeror’s organization, to include (but are not necessarily limited to) personnel with the responsibilities, qualifications, and levels of authority similar to the roles identified in SABER Master Specifications Section 01 31 01 paragraphs 1.1.1.1 through 1.1.1.8 and which specifies what positions are being accomplished by subcontractors. The offeror’s organizational chart shall be IAW SABER Master Specifications Section 01 31 01 paragraph 1.5.1.3.
http://www.fms.treas.gov/c570/
2.2.2.1.3. A narrative describing offeror’s approach for recruiting, training and retaining sufficient qualified staffing throughout the contract period; the offeror’s program management policies and procedures to project planning, execution information flow, reporting and Government interface; policies and procedures for selection and management of subcontractors; how subcontractors will be integrated into overall project management; and offeror’s ability to handle the workload of multiple (5 to 10), concurrent projects. The offeror’s narrative shall be IAW SABER Master Specifications Section 01 31 01 paragraph 1.5.1.4.
2.2.2.2. Sub-factor 2: Quality Control Plan.
Offeror shall provide an effective Quality Control Plan IAW the requirements in SABER Master Specifications Section 01 45 00 paragraph 1.2, Quality Control Plan Contents.
2.2.2.2.1. Demonstrate how offeror’s quality control program meets the requirements in SABER Master
Specifications Section 01 45 00 paragraph 1.2.1.
2.2.2.2.2. Describe offeror’s policies and procedures for quality control.
2.2.2.2.3. Identify personnel or positions, their responsibilities and levels of authority.
2.2.2.2.4. Describe procedures for review and approval of material submissions; inspection and testing of work.
2.2.2.2.5. Describe procedures for documenting compliant and non-compliant work and correction of deficiencies.
2.2.2.3. Sub-factor 3: Demonstration Project.
Offeror shall provide a solution (complete and acceptable proposal package) for the Demonstration Project IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12, Project Proposal. The Demonstration Project will be used for evaluation purposes only and will not be awarded. The Demonstration Project solution shall include:
2.2.2.3.1. A cover page including the project title, total project cost, list of assumptions, list of requirements, performance period, material lead times, and any special considerations such as phasing of construction.
The offeror’s cover page shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1a.
2.2.2.3.2 A Statement of Work (SOW) that describes approach and reflects a complete understanding of the requirement and compliance with local, state and federal building and construction codes. The offeror’s SOW shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1b.
2.2.2.3.3. Design documentation. Drawing(s) showing basic layout and planning of work IAW SABER Master
Specifications Section 01 00 00 paragraph 1.4.12.1c.(1). Design calculations to substantiate appropriate equipment or material selection and sizing, component assembly, and proposed layout and sizing of utilities and structural elements IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1c.(2).
2.2.2.3.4. A detailed line item Project Cost Estimate in RSMeans CostWorks, or equivalent format. At a minimum, the following items must be included in the Project Cost Estimate: line item number, item description, unit of measure, unit cost, quantity, subtotal cost, and total cost. The offeror’s Project Cost Estimate shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1d.
2.2.2.3.5. A Schedule of Material Submittals which identifies all items that have a material effect on the
Demonstration Project. The offeror’s Schedule of Material Submittals shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1e.
2.2.2.3.6. A Construction Schedule IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1f.
Construction Schedule shall be in Microsoft Project, or equivalent format, showing the offeror’s intended progression, breakout of all major tasks/work components, any permits required, etc. for the project. The offeror shall also provide an AF Form 3064, Progress Schedule showing the offeror’s intended progression, breakout of all major tasks/work components, any permits required, etc. for the project and associated progression/percentage of the work effort from task order award to completion.
2.2.2.3.7. An AF Form 3065, Contract Progress Report, detailing the all major tasks/work components and the associated percentage of the Demonstration Project. The offeror’s AF Form 3065 shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1f.
SECTION M - EVALUATION FACTORS FOR AWARD
The following have been modified:
BASIS FOR AWARD
M-1 SOURCE SELECTION
1.0 Basis for Contract Award.
1.1. This acquisition is being conducted as a Lowest Price Technically Acceptable (LPTA) source selection in accordance with (IAW) Federal Acquisition Regulation (FAR) Part 15, Contracting by Negotiation, as supplemented by the Defense Federal Acquisition Regulation Supplement (DFARS), the Air Force Federal Acquisition Regulation Supplement (AFFARS), DoD Source Selection Procedures Appendix C, and AFFARS Mandatory Procedures (MP) 5315.3. These regulations are available electronically at the Air Force FARSite, http://farsite.hill.af.mil or http://acquisition.gov/far. The Government will select the proposal(s) with the lowest total evaluated price from among those rated as “technically acceptable” for all sub-factors of the Technical Factor. Offerors must clearly identify any exception to the solicitation terms and conditions and must provide complete supporting rationale. The Government reserves the right to determine any such exceptions unacceptable.
1.2. Contracts may be awarded to the offerors who are determined to be responsible IAW FAR Subpart 9.1, as supplemented, and are determined eligible by the Small Business Administration (SBA) IAW FAR 19.8, whose proposals conform to the solicitation’s requirements (to include all stated terms, conditions, representations, certifications, and all other information required by Section L of this solicitation) and are judged, based on the evaluation factors and sub-factors, to represent the Lowest Price Technically Acceptable (LPTA) proposal.
While the Government will strive for maximum objectivity, the source selection process, by its nature, is subjective; therefore, professional judgment is implicit throughout the entire process.
2.0 Number of Contracts to be Awarded
The Government intends to award three (3) Firm-Fixed-Price (FFP), Indefinite-Delivery/Indefinite-Quantity (IDIQ) contracts for the Simplified Acquisition Base Engineering Requirements (SABER) Program.
3.0 Solicitation Requirements, Terms and Conditions
Offerors are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements, in addition to those identified as factors or sub-factors. Failure to comply with the terms and conditions of the solicitation may result in the offeror being determined ineligible for contract award. Offerors must clearly identify any exception to the solicitation terms and conditions and must provide complete supporting rationale. The Government reserves the right to determine any such exceptions unacceptable.
4.0 Evaluation Process
The evaluation process to be used is as follows:
http://farsite.hill.af.mil/ http://acquisition.gov/far
Step 1. Perform compliance review on all proposals to assess compliance with terms and conditions of the solicitation. Non-compliance with the terms and conditions of the solicitation may result in an unfavorable proposal evaluation and may be grounds to eliminate the proposal from consideration for contract award.
Step 2. Perform price evaluations on all proposals not eliminated from consideration in Step 1 and rank them from lowest to highest based on their Total Evaluated Price.
Step 3. Conduct technical evaluations beginning with the lowest priced offeror. If the lowest priced Offeror is determined to be technically unacceptable, then the next lowest priced Offeror will be evaluated. This process will be repeated until the government has identified the three lowest priced technically acceptable offerors. The government reserves the right to open discussions. Only those offerors determined to be technically acceptable, either initially or as a result of discussions, will be considered for award.
Step 4. Perform a responsibility determination on the three (3) lowest priced technically acceptable offerors. In order to be determined a responsible, an offeror must meet the following conditions:
• Offeror must meet the standards identified in FAR 9.104-1;
• Offeror must possess an active California General Contractor’s License, “Class A” or “Class B”, registered in the prime contractor’s name;
• Offeror must provide evidence that it is able to obtain a minimum single project bonding capacity of $3M and an aggregate bonding capacity of $10M from an approved surety listed in the Department of the Treasury Circular 570 (http://www.fms.treas.gov/c570/) or other security permitted by FAR Subpart 28.2, unless prohibited by law or regulation.
If one or more of the three technically acceptable offerors are determined non-responsible, the government will resume technical evaluations as detailed in Step 3. Technical evaluations will continue until the Government identifies the three (3) Lowest Priced Technically Acceptable (LPTA) responsible offerors.
Following the completion of Steps 3 and 4; the Contracting Officer, with the approval of the Source Selection Authority (SSA), will determine if it is in the Government’s best interest to open discussions. If the determination is made to open discussions, the Government will conduct discussions with all offerors included in the Competitive Range. If the offeror’s proposal has been evaluated as acceptable at the time discussions are closed, any changes or exceptions in the Final Proposal Revision are subject to evaluation and may introduce risk that the offeror’s proposal be determined unacceptable and ineligible for award. The Government reserves the right to award without discussions. The Government also reserves the right to perform both price and technical evaluations on non-responsive Offerors to determine if it is in the Government’s best interest to open discussions. Only those Offerors determined to be technically acceptable, either initially or as a result of discussions, will be considered for award.
M-2 EVALUATION FACTORS AND SUBFACTORS
1.0 Evaluation of Proposals
The following evaluation factors and sub-factors will be used to evaluate each proposal. The Government will evaluate proposals for technical acceptability, but will not rank the proposals by non-price factors or sub-factors.
Factor 1: Price Factor 2: Technical Sub-factor 1: Program Management Plan Sub-factor 2: Quality Control Plan Sub-factor 3: Demonstration Project
2.0 Evaluation Factors and Standards
2.1. Factor 1 - Price Factor
The offeror’s Price proposal will be evaluated by reviewing the proposed coefficients for each year (base and four options). For evaluation purposes the price proposals will be calculated by adding CLIN’s 0001 thru 4001.
http://www.fms.treas.gov/c570/
The sum of coefficients will be averaged, and evaluated for reasonableness. This average of the coefficients will be the Total Evaluated Price (TEP) and offerors will be ranked from lowest TEP to highest.
The offeror's Price Proposal will be evaluated, using one or more of the techniques defined in FAR 15.404(b), in order to determine if it is reasonable. For a price to be determined reasonable, it must represent a price to the Government that a prudent person would pay in the conduct of competitive business. Normally, price reasonableness is established through cost and price analysis techniques as described in FAR 15.404. For additional information see FAR 31.201-3.
2.2. Factor 2 - Technical Factor
The Government’s technical evaluation team shall evaluate the technical proposals on an “Acceptable” or “Unacceptable” basis, assigning one of the ratings described below for each sub-factor. Any sub-factor evaluated as “Unacceptable” will render the entire proposal unacceptable and, therefore, not eligible for award.
Only those proposals determined to be “technically acceptable”, either initially or as a result of discussions, will be considered for award. However, the offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without discussions.
TABLE 1 - TECHNICAL RATINGS
Rating Description Acceptable Proposal meets the requirements of the solicitation.
Unacceptable Proposal does not meet the requirements of the solicitation.
2.2.1. Sub-factor 1: Program Management Plan
2.2.1.1. Description.
This sub-factor evaluates the offeror’s (prime contractor) management approach, organizational structure and experience relating to projects similar in scope to those expected under SABER in accordance with SABER Master Specifications Section 01 31 01 paragraph 1.5, Program Management Plan.
2.2.1.2. Standard.
This requirement is met when the offeror provides an effective Program Management Plan that complies with the requirements of SABER Master Specifications Section 01 31 01 paragraph 1.5, Program Management Plan. Sub-factor must be met at time of proposal submission. The Program Management Plan is acceptable when:
2.2.1.2.1. The position descriptions meet the required minimum qualifications of each Key Personnel listed below, and contain the required job experience with examples to demonstrate the ability to meet all elements of the technical requirements as stated in SABER Master Specifications Section 01 31 01 paragraphs 1.1.1.1 through 1.1.1.8:
• Program Manager
• Project Manager(s)
• Construction Quality Control Inspector(s)
• Construction Superintendent/Job Foreman
• Lead Craftsman/Tradesman
• Quality Control Officer
• Site Safety and Health Officer
• Draftsmen/CAD Professional
2.2.1.2.2. The chart of the offeror’s organizational structure and narrative detail the roles, responsibilities, qualifications and levels of authority for personnel within its organization include (but are not necessarily be limited to) personnel with the responsibilities, qualifications, and levels of authority similar to the following roles as identified in SABER Master Specifications Section 01 31 00, and specifies what positions are being accomplished by subcontractors, to successfully manage task orders.
2.2.1.2.3. Offeror provides a narrative which utilizes effective and sound business practices to detail the following:
• An approach for recruiting, training, and retaining sufficient qualified staffing throughout the contract period
• Program management policies and procedures to project planning, execution information flow, reporting and Government interface
• Policies and procedures for selection and management of subcontractors
• How subcontractors will be integrated into overall project management
• Ability to handle multiple (5-10), concurrent projects to successfully manage the workload through the life of the SABER program.
2.2.2. Sub-factor 2: Quality Control Plan
2.2.2.1. Description.
This sub-factor evaluates the offeror’s (prime contractor’s) ability to create an effective Quality Control Plan IAW the requirements of SABER Master Specifications Section 01 45 00 paragraph 1.2, Quality Control Plan Contents.
2.2.2.2. Standard.
This requirement is met when the offeror (prime contractor) submits an effective Quality Control Plan that utilizes sound business practices and complies with the requirements of SABER Master Specifications Section 01 45 00 paragraph 1.2.1, Quality Control Plan Contents. Sub-factor must be met at time of proposal submission. The Quality Control Plan is acceptable when it details the following and utilizes effective and sound business practices to quality control:
• Personnel, procedures, instructions, tests, forms, and records to be used
• The person(s) within the contractor’s organization identified as the Quality Control Officer
• The authority and responsibilities of all the quality control personnel
• Procedures for reviewing and approving all shop drawings, product data samples or other submittals before submission to the Contracting Officer to include procedures for obtaining field measurements
• Method of documenting quality control operation, inspection, and testing of both prime and subcontract work including samples of proposed forms
• Method of documenting and tracking deficiencies including responsibilities and procedures for correcting deficiencies
2.2.3. Sub-factor 3: Demonstration Project (This project will be used for evaluation purposes only and will not be awarded)
2.2.3.1. Description.
This sub-factor evaluates the offeror’s (prime contractor’s) ability to provide a solution (complete and acceptable proposal package) for the Demonstration Project in accordance with the SABER Master Specifications Section 01 00 00 paragraph 1.4.12, Project Proposal.
2.2.3.2. Standard.
This requirement is met when the offeror (prime contractor) submits complete and acceptable proposal package for the Demonstration Project in accordance with SABER Master Specifications Section 01 00 00 paragraph 1.4.12, Project Proposal. Sub-factor must be met at time of proposal submission. The Demonstration Project proposal package will be determined to be acceptable when the proposal adequately addresses the following:
• A cover page including the project title, total project cost, list of assumptions, list of requirements, performance period, material lead times, and any special considerations such as phasing of construction which demonstrate an understanding of the project and how it should be accomplished.
The offeror’s cover page shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1a.
• Offeror’s Statement of Work (SOW) clearly demonstrates a thorough understanding of the construction effort and applicable codes and regulations associated with the Demonstration Project.
The offeror’s SOW shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1b.
• Drawing(s) demonstrate the Offeror’s clear understanding of the project and drafting capability.
Design documentation IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1c.(2).
• Offeror’s Project Cost Estimate demonstrates a reasonable and complete approach in construction methodology for line items, labor classifications, materials, quantities, and is consistent with the coefficient proposed. The offeror’s Project Cost Estimate shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1d.
• Offeror’s Schedule of Material Submittals identifies all items that have a material effect on the Demonstration Project and demonstrates an understanding of the projects requirements. The offeror’s Schedule of Material Submittals shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1e.
• Offeror’s Construction Schedule demonstrates a realistic timeframe, a reasonable breakout of the major tasks/work components (to include any permits required, etc.) and the associated completion percentages assigned for the Demonstration Project follows a logical progression of the work effort from task order award to closeout. The offeror’s Construction Schedule shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1f.
• AF Form 3065, Contract Progress Report, provides a reasonable breakout of the major tasks/work components and the associated percentage assigned for the Demonstration Project. The offeror’s AF Form 3065 shall be IAW SABER Master Specifications Section 01 00 00 paragraph 1.4.12.1f.
(End of Summary of Changes)