Responses to Questions - 2 April 09.doc

DOC document 25 KB Posted

Attached to
Repair/Renovate Dorm 748 (USMC)
Solicitation number
FA4460-09-B-0001
Issued by

About this file

Responses to RFI #s 62-66

View the file

Other files

File Type Posted
Responses to Questions - 2 April 09-2.doc DOC document
Responses to Questions - 1 April 09.doc DOC document
Responses to Questions - 31 March 09.doc DOC document
11 A-8 Layout1 —
RFI 39 Supporting Photo.JPG JPG image
Responses to Questions - 27 Mar 09.doc DOC document
Site Visit Attendees.doc DOC document
08 87 16 FRAGMENT RETENTION FILM FOR GLASS.doc DOC document
28 31 00 FIRE DETECTION AND ALARM SYSTEMS.doc DOC document
Responses to Questions - 26 Mar 09.doc DOC document
Responses to Questions - 13 Mar.doc DOC document
Amendment 1.pdf PDF
drawings.pdf PDF
Attachment 2 EMIS Instruction Guide.doc DOC document
97 - 2003 Schedule of Material Submittals.xls XLS spreadsheet
Solicitation FA4460-09-B-0001.doc DOC document
Attachment 1 - WAGE DETERMINATION 080175 23 JAN 09.docx DOCX document
Attachment 3 Addendum to MOA.doc DOC document
Attachment 4 C&D Report.doc DOC document
SPEC NKAK 09-1025 REPAIR RENOVATE DORM 748 —
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4460-09-B-0001

NKAK 09-1025

Repair Renovate Dorm 748 (USMC)

Little Rock AFB, AR Responses to Questions

2 April 2009

RFI #62: The interior closet doors are not referenced to remove and install new nor is the hardware called to replace. Is this the intent?

Response to # 62 – The closet doors are not scheduled to be removed. The only hardware being replaced is the missing hardware such as door stops that are noted on the plans. Contractor will be responsible for making sure existing doors are clean and useable.

RFI #63: The drawings call to replace 3 dorm bathroom doors. Is this all that is to replace? No hardware is called to change on the remaining bathroom doors.

Response to # 63 – The bathroom doors to be replaced are marked on the plans. Contractor will be responsible for making sure existing doors are clean and useable.

RFI #64: No dimensional drawings can be found. Could you please direct to the correct plan so that the total square footage for painting can be computed?

Response to # 64 – All plans are drawn in the correct scale. There are no known dimensioned drawings of this facility. Contractor will be responsible for field verifying all dimensions/room sizes of the existing facility prior to bid.

RFI #65: If leaks are discovered when the HVAC piping system is refilled, who will be responsible? Will this be an item that can be addressed with a change order if it becomes an issue?

Response #65 – It would be the Government’s responsibility and a change order would be issued.

RFI # 66: Are all the RFI’s and answers to be acknowledged as the amendment will be on the solicitation, offer and award?

Response #66 – RFI responses are not ammendments and thus do not need to be acknowledged.