FA3047-12-T-0010 Q and A
31 KB Posted
- Attached to
- Replace Existing 300 KVA Transformer Bldg 6300
- Solicitation number
- FA3047-12-T-0010
About this file
FA3047-12-T-0010 Transformer Project Questions 1 through 9 pending Govt. response
Text of this file
802 CONS/LGCAB
FA3047-12-T-0010
Lackland AFB, TX
Replace Existing Transformer B6300, WO# 41977
QUESTIONS & ANSWERS (#1)
(22 Aug 12) Question 1: Will the contractor or the local utility company supply the new transformer, high voltage switch, and 45’ Class 2 pole with pole top hardware and terminations?
Government Response: PENDING RESPONSE Question 2: If the prospective contractor is to supply the new transformer, is there a more detailed specification for the new transformer than was provided in the SOW dated 11 August 2012?
Government Response: PENDING RESPONSE Question 3: Please provide a site plan of the project parking lot & mechanical yard of Building #6300.
Government Response: PENDING RESPONSE Question 4: Please provide a detail of an acceptable Transformer Pad construction from the Base Electric Company, showing dimensions, thickness, support beams, safety bollards that may be required.
Government Response: PENDING RESPONSE Question 5: Does the existing transformer contain PCB that will require hazardous disposal?
Government Response: PENDING RESPONSE Question 6: Please provide a contact for the LAFB Electric Company that we can coordinate the installation of the new power pole & shut down of the existing service.
Government Response: PENDING RESPONSE Question 7: Is there a detailed specification, regarding the high voltage switch for the transformer that can be provided?
Government Response: PENDING RESPONSE Question 8: During the site visit there was mention of the Base providing a temporary generator. Please confirm.
Government Response: PENDING RESPONSE Question 9: V/E – An isolation switch is not being installed, only +/- 50’ of overhead line is being removed and new transformer is being placed near existing service connection pole. There could be a cost and time savings using existing pole and stubbing out of transformer pad for future underground connection.
Government Response: PENDING RESPONSE
(END)
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .