About this file

FA0021-12-R-0014 Q A 6

View the file

Other files for this federal contract opportunity

Other files attached to Joint Terminal Attack Controller and Small Unmanned Aerial Systems (JTAC/SUAS) Program Management, newest first.
File Type Posted
FA0021-12-R-0014 Q As 10.pdf PDF
FA0021-12-R-0014 Q As 9.pdf PDF
FA0021-12-R-0014 Q As 8.pdf PDF
11 - Atch 6-Cost Proposal Workbook Version 1.1.xls XLS spreadsheet
FA0021-12-R-0014 P0005.pdf PDF
FA0021-12-R-0014 Q As 7.pdf PDF
FA0021-12-R-014 P0004.pdf PDF
13 - Atch 8.1-Relevancy Matrix.pdf PDF
FA0021-12-R-0014 P0003.pdf PDF
FA0021-12-R-0014 Q As 5.pdf PDF
FA0021-12-R-0014 Q As 4.pdf PDF
FA0021-12-R-0014 P0002.pdf PDF
FA0021-12-R-0014 Q As 1.pdf PDF
FA0021-12-R-0014 Q As 3.pdf PDF
Amendment 1.pdf PDF
FA0021-12-R-0014 Q As 2.pdf PDF
8 - Atch 3 -WD 2005-3033.pdf PDF
3 - Atch 2-App A - Mission Description.doc DOC document
15 - Atch 10-Consent Ltr.doc DOC document
13 - Atch 8-Relevancy Matrix.doc DOC document
10 - Atch 5 -WD-2005-2567.pdf PDF
14 - Atch 9-P PP Citation List.doc DOC document
2 - Atch 2 - PWS.doc DOC document
1 - Atch 1-Labor Descriptions.doc DOC document
4 - Atch 2-App B - LOI.doc DOC document
6 - Atch 2 - App D CDRLs Final.pdf PDF
7 - Atch 2-App E - Acronyms.doc DOC document
12 - Atch 7-PPQ and Cvr Ltr.doc DOC document
16 - Atch 11-PPQ Recipient List.doc DOC document
11 - Atch 6-Cost Proposal Workbook.xls XLS spreadsheet
5 - Atch 2 App C - DD254 - Signed.pdf PDF
9 - Atch 4-WD-2005-2393.pdf PDF
FA0021-12-R-0014.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA0021-12-R-0014, JTAC/SUAS Program Management ( Q&A #6)

Questions and Answers:

Reference#1: Responses to Q&A#4. In your response to Question 1, the Government has defined the offeror as the

Prime Contractor. In your response to Question 2, the Government has defined “Lead Contractor” as the Prime

Contractor. In Question 3, the Government states at least 2 citations must be recent (less than 5 years) and relevant.

RESPONSE: Please review response to Q&A 4, Question 3 for correct Government stated verbiage as mis-referenced above.

Reference#2: Amendment 0002, RFP page 7-8 of 20, Section 3.1. Within Volume II, the offeror is to complete the

“Team Matrix” (Table L-0006-1), identifying the “Lead Contractor” and “Other Supporting Contractor(s)” for the

PWS area of the requirement (Program Management, Operations & Maintenance, Mission Support).

Reference#3: Amendment 0002, RFP page 10 of 20, Section 2.1.1. The Offeror is to provide a completed Relevancy

Matrix (RFP Attachment 8). This attachment states the Offeror shall submit no more than 3 “Present and Past

Performance Citations” for all “Prime Contributors” identified in the Team Structure Matrix in Volume II. At least

1 Citation is required for each “Lead Contractor”.

Question 1. Based upon the references above, is it the Government’s intent that “Prime Contributors” be only the

Prime Contractor, based upon the definitions in References #1, #2 and #3. Please clarify.

RESPONSE: No, the Government does not intend for “Primary/Prime Contributors” to solely mean the offeror. Primary Contributors make up the “Team” submitting a proposal. The offeror is a Prime

Contributor along with, if any, subcontractors as included in the Team Matrix, Volume II. See Amendment

0003 for further clarification of L-0007 2.1.2 and a revision of Attachment 8 – Relevancy Matrix.

Question 2. Since “Lead Contractor”, in Reference #2 and #3 above, is defined to be the “Prime Contractor”, is it correct that is the intent of the Government for only the Prime Contractor to present Past Performance Citations and

PPQs to the Government for evaluation?

RESPONSE: See answer to Q&A #4, Question 3 and section L of solicitation FA0021-12-R-0014.

For further clarification on Government intent, the Government expects no more than three (3) past performance citations for each proposal. If the maximum of three (3) citations are received, a minimum of two (2) citations shall be from work performed by the offeror. One (1) citation may be from a subcontractor as identified in Volume II - Team Matrix. See section L of the referenced solicitation for specifics as they relate to Past Performance Citations.